ACG METALS LIMITED: Q3 2025 YTD Operations and Capital Structure Update
ACG Metals (LSE: ACGAF) reported Q3 2025 YTD operating and capital-structure results on 20 October 2025. Key points: production on track for full-year guidance of 36–38 koz AuEq; AISC YTD $1,131/oz AuEq within guidance; C1 cash costs fell 30% to $432/oz AuEq. Gold and silver realised prices rose to $3,054/oz and $34.19/oz, supporting revenues. Net debt was $64M and cash balance $137M (including $46M restricted). Gediktepe Sulphide Expansion reached design/procurement/construction milestones (58%/56%/27%) and targets full commercial production by end H1 2026.
ACG Metals (LSE: ACGAF) ha riportato i risultati operativi e di struttura del capitale per Q3 2025 YTD il 20 ottobre 2025. Punti chiave: la produzione è in linea per la guidance annuale di 36–38 koz AuEq; AISC YTD $1,131/oz AuEq entro la guida; i costi cash C1 sono diminuiti del 30% a $432/oz AuEq. I prezzi realizzati dell’oro e dell’argento sono saliti a $3,054/oz e $34.19/oz, sostenendo i ricavi. Il debito netto era $64M e la liquidità $137M (inclusi $46M ristretti). Gediktepe Sulphide Expansion ha raggiunto traguardi di design/approvvigionamento/costruzione (58%/56%/27%) e punta alla piena produzione commerciale entro la seconda metà del 2026.
ACG Metals (LSE: ACGAF) informó los resultados operativos y de estructura de capital para el 3T 2025 YTD el 20 de octubre de 2025. Puntos clave: la producción está en camino para la orientación anual de 36–38 koz AuEq; AISC YTD $1,131/oz AuEq dentro de la guía; los costes en efectivo C1 cayeron un 30% a $432/oz AuEq. Los precios realizados del oro y la plata subieron a $3,054/oz y $34.19/oz, apoyando los ingresos. La deuda neta fue de $64M y el saldo de caja $137M (incluidos $46M restringidos). la Expansión Gediktepe Sulphide alcanzó hitos de diseño/procurement/construcción (58%/56%/27%) y apunta a producción comercial total para finales de la primera mitad de 2026.
ACG Metals (LSE: ACGAF) 2025년 3분기 연간 누적 영업 및 자본구조 결과를 2025년 10월 20일 발표했습니다. 요점: 생산은 연간 가이던스 36–38 koz AuEq에 대해 순조롭다; AISC YTD $1,131/oz AuEq는 가이던스 내에 있으며; C1 현금비용은 30% 감소하여 $432/oz AuEq. 금과 은의 실현가가 각각 $3,054/oz 및 $34.19/oz로 상승하여 매출을 뒷받침했다. 순부채는 $64M, 현금 잔고는 $137M (포함된 $46M 제한자산)이었다. Gediktepe Sulphide Expansion은 설계/조달/시공의 이정표를 달성했으며(설계 58%/조달 56%/시공 27%) 2026년 상반기 말 전체 상업생산을 목표로 한다.
ACG Metals (LSE: ACGAF) a publié les résultats opérationnels et de structure du capital pour le T3 2025 YTD le 20 octobre 2025. Points clés : la production est en ligne avec les prévisions annuelles de 36–38 koz AuEq; le AISC YTD $1,131/oz AuEq dans la fourchette; les coûts en cash C1 ont chuté de 30% à $432/oz AuEq. Les prix réalisés de l’or et de l’argent ont augmenté jusqu’à $3,054/oz et $34.19/oz, soutenant les revenus. La dette nette était de $64M et la trésorerie $137M (dont $46M bloqués). L’expansion Gediktepe Sulfide a atteint des jalons de conception/approvisionnement/construction (58%/56%/27%) et vise une production commerciale intégrale d’ici la fin du premier semestre 2026.
ACG Metals (LSE: ACGAF) berichtete am 20. Oktober 2025 über die Ergebnisse für Q3 2025 YTD Betrieb und Kapitalstruktur. Kernpunkte: Produktion im Plan für die Jahresprognose von 36–38 koz AuEq; AISC YTD $1,131/oz AuEq innerhalb der Guidance; C1-Barmittel Kosten sanken um 30% auf $432/oz AuEq. Die realisierten Preise für Gold und Silber stiegen auf $3,054/oz bzw. $34.19/oz, was die Einnahmen unterstützt. Net debt war $64M und Cash-Bestand $137M (einschließlich $46M eingeschränkt). Gediktepe Sulphide Expansion erreichte Design-/Beschaffung-/Konstruktion-Meilensteine (58%/56%/27%) und zielt auf volle kommerzielle Produktion bis Ende H1 2026 ab.
ACG Metals (LSE: ACGAF) أبلغت عن نتائج التشغيل وهيكل رأس المال للفترة حتى تاريخه Q3 2025 في 20 أكتوبر 2025. النقاط الأساسية: الإنتاج ضمن المسار للوتيرة السنوية المقدرة بـ 36–38 koz AuEq; AISC YTD $1,131/oz AuEq ضمن الإرشاد؛ تكاليف النقد C1 انخفضت 30% إلى $432/oz AuEq. ازدادت أسعار الذهب والفضة المحققة إلى $3,054/oz و$34.19/oz، وهو ما دعم الإيرادات. الدين الصافي كان $64M ورصيد النقد $137M (بما في ذلك $46M مقيد). توسعة Gediktepe Sulphide وصلت إلى مراحل التصميم/التوريد/البناء (58%/56%/27%) وتستهدف الإنتاج التجاري الكامل بحلول النصف الأول من 2026.
ACG Metals (LSE: ACGAF) 于 2025 年 10 月 20 日公布了 2025 年第 3 季至今的运营与资本结构业绩。要点:产量按计划,全年指引为 36–38 koz AuEq;AISC YTD $1,131/oz AuEq 在指引范围内;C1 现款成本 下降 30% 至 $432/oz AuEq。黄金与白银的实现价格分别上涨至 $3,054/oz 和 $34.19/oz,支撑收入。净债务为 $64M,现金余额为 $137M(其中 $46M 限制性)。Gediktepe 硫化物扩张达到设计/采购/施工里程碑(58%/56%/27%),目标在 2026 年上半年末实现全面商业生产。
- Production on track for 36–38 koz AuEq full-year guidance
- C1 cash costs down 30% to $432/oz AuEq
- AISC within guidance at $1,131/oz AuEq
- Strong liquidity: $137M cash balance supporting $64M net debt
- Gediktepe expansion at 58% design, targeting H1 2026 commercial production
- Total ore mined fell 60% YTD vs Q3 2024
- Total ore processed fell 68% YTD vs Q3 2024
- AuEq production declined 26% YTD vs Q3 2024
- Process plant construction only 27% complete as of 30 Sep 2025
("ACG" or the "Company")
Q3 2025 YTD Operations and Capital Structure Update
ACG on track for annual production and AISC guidance
Q3 2025 YTD Summary
- Q3 2025 YTD production remains on track to meet full-year guidance of 36–38koz AuEq.
- AISC costs YTD were
US /oz AuEq, remaining within guidance; YTD C1 cash costs fell by$1,131 30% toUS /oz AuEq compared to Q3 2024 YTD, reflecting continued operational efficiency.$432 - Q3 2025 production was seasonally lower, consistent with the mine plan and previous years' production sequencing.
- The Gediktepe Sulphide Expansion Project continues to progress on schedule and budget, with first concrete and steel, and significant site infrastructure milestones being achieved in Q3 2025.
- ACG Metals continues to advance technical work to unlock value from transitional ore.
- Gold and silver prices increased in Q3 YTD 2025 compared to Q3 YTD 2024 by
34% and26% , toUS /oz Au and$3,054 US /oz Ag, supporting strong revenues.$34.19 - ACG's net debt as of September 30, 2025 of
remains low, supported by a strong cash balance of$64 million (including a restricted balance of$137 million ).$46 million
Artem Volynets, Chairman and CEO of ACG, said:
"We delivered solid progress in Q3 2025 and remain firmly on track to achieve our full-year guidance. With disciplined execution, the Sulphide expansion is on schedule and within budget, targeting full commercial production by the end of H1 2026. Major milestones have been achieved, including concrete pouring and steel installation. "
Q3 YTD 2025 Operating Summary
|
|
Q3 YTD 2025 |
vs Q3 YTD 2024 |
|
|
|
|
|
|
Total Ore Mined |
t |
209,098 |
-60 % |
Mining |
Au Grade |
g/t |
1.90 |
17 % |
|
Ag Grade |
g/t |
67 |
22 % |
|
|
|
|
|
|
Total Ore Processed |
t |
184,250 |
-68 % |
Process |
Au Grade |
g/t |
2.17 |
8 % |
|
Ag Grade |
g/t |
86 |
33 % |
|
|
|
|
|
|
Au |
oz |
23,869 |
-30 % |
Production |
Ag |
oz |
490,995 |
-1 % |
|
AuEq |
oz |
29,291 |
-26 % |
|
|
|
|
|
|
Au |
oz |
24,984 |
-30 % |
Sales |
Ag |
oz |
480,843 |
3 % |
|
AuEq |
oz |
30,297 |
-26 % |
|
|
|
|
|
|
Au |
$/oz |
3,054 |
34 % |
Realised Price |
Ag |
$/oz |
34.19 |
26 % |
|
|
|
|
|
|
C1 Cash Costs (produced) |
$/oz |
432 |
-30 % |
Cost |
AISC (sold) |
$/oz |
1,131 |
-2 % |
Strong Momentum Continues Across Sulphide Expansion Works
- The Gediktepe Copper Sulphide Expansion Project has achieved key milestones, including the completion of the MSE wall administration area, a significant step in the site's infrastructure development.
- Earthworks at the TSF are progressing well, supported by favourable weather throughout September. Notable progress includes the installation of underdrains and embankment foundation preparation.
- The GAP blue collar camp and mobilisation area have been completed on schedule, with temporary water heating installed to support resident occupancy and workforce mobilisation as major construction activities ramp up across the site.
- Excavation and foundation work in the fine grinding area are advancing, with TSF underdrain installation continuing in parallel.
- As of 30 September 2025, the project remains well within its scheduled milestones, with
58% of engineering design and draft,56% of procurement and27% of process plant construction completed. - The Sulphide Expansion Project remains on track to reach full commercial production by the end of H1 2026, enabling Gediktepe's transition into a long-life, low-cost copper producer.
Warrants
On 20 October 2025, the Company made various amendments to the terms of the (i) private placement warrant and public warrant instrument dated 2 September 2024 (the "First Warrant Instrument") and (ii) warrant instrument dated 6 October 2022 (as amended and restated on 2 September 2024 and as further amended and restated on 7 February 2025) (the "Second Warrant Instrument" and, together with the First Warrant Instrument, the "Warrant Instruments"); such that:
(A) the currency denomination of the Warrant Instruments has been changed from United States Dollars to Pounds Sterling, to reflect the change in trading currency of the Company's class A ordinary shares on the London Stock Exchange on 24 March 2025;
(B) the Exercise Price has been adjusted from
(C) the right of the Company to redeem the Warrants (herein as defined in the Warrant Instruments) if: (i) the Reference Value (herein as defined in the Warrant Instruments) equals or exceeds
(D) certain other consequential amendments have been made to give effect to the above,
(together, the "Amendments").
Save in respect of the Amendments, the Warrant Instruments remain otherwise unchanged and the Warrant terms and conditions remain as summarised in the prospectus dated 7 October 2022 and the announcement on 7 February 2025.
Pursuant to the Warrant T&Cs and the Warrant Instruments, the Company is permitted to amend the Warrant T&Cs without the consent of Warrant Holders (herein as defined in the Warrant Instruments) for the purpose of adding or changing any provisions as the Company may deem necessary or desirable and that the Company deems not to adversely affect the rights of Warrant Holders. The Company considers the Amendments to be necessary and, furthermore, the Company deems that such Amendments do not adversely affect the rights of the Warrant Holders. Accordingly, the consent of Warrant Holders was not sought in respect of the Amendments (nor was such consent required to be sought).
Copies of the updated Warrant Instruments will shortly be available on the Company's website at: https://acgmetals.com/regulatory-news/.
Inside information
The information contained within this announcement is considered by the Company to constitute inside information as stipulated under the Market Abuse Regulation (EU) No.596/2014 (as it forms part of
The person responsible for the release of this information on behalf of the Company is Artem Volynets, Chairman & Chief Executive Officer.
Forward looking statements
This announcement may contain certain "forward-looking information" and "forward-looking statements" (collectively, "forward-looking statements"). Forward-looking statements are identified by their use of terms and phrases such as "believe", "targets", "expects", "aim", "anticipate", "project", "would", "could", "envisage", "estimate", "intend", "may", "plan", "will" or the negative of those, variations or comparable expressions, including references to assumptions. The forward-looking statements in this announcement are based on current expectations and are subject to known and unknown risks and uncertainties that could cause actual results, performance and achievements to differ materially from any results, performance or achievements expressed or implied by such forward-looking statements. Factors that may cause actual results to differ materially from those expressed or implied by such forward looking statements. These forward-looking statements are based on numerous assumptions regarding the present and future business strategies of the Group and the environment in which it is and will operate in the future. All subsequent oral or written forward-looking statements attributed to the Company or any persons acting on its behalf are expressly qualified in their entirety by the cautionary statement above. Each forward-looking statement speaks only as of the date of this announcement. Except as required by applicable law, regulatory requirement, the
For further information please contact:
Palatine
Communications Advisor
Conal Walsh / James Gilheany/ Kelsey Traynor/ Richard Seed
acg@palatine-media.com
Berenberg
Research Analysts
William Dalby +44 (0) 20 3753 3243
Richard Hatch +44 (0) 20 3753 3070
Joint Broker
Jennifer Lee
+44 (0) 20 3207 7800
Canaccord
Research Analysts
Tim Huff +44 (0) 20 7523 8374
Alex Bedwany +44 (0) 20 7523 8387
Joint Broker
James Asensio / Charlie Hammond
+ 44 (0) 20 7523 80
Stifel
Joint Broker
Ashton Clanfield / Varun Talwar
+44 (0) 20 7710 7600
Cantor Fitzgerald
Research Analysts
Puneet Singh +1 (416) 350-8153
About the Company
ACG Metals is a company with a vision to consolidate the copper industry through a series of roll-up acquisitions, with best-in-class ESG and carbon footprint characteristics.
In September 2024, ACG successfully completed the acquisition of the Gediktepe Mine which is expected to transition to primary copper and zinc production from 2026 and will target annual steady-state copper equivalent production of 20-25 kt. Gediktepe sold 57koz of AuEq in 2024.
ACG's team has extensive M&A experience built through decades spent at blue-chip multinationals in the sector. The team brings a significant network as well as a commitment to ESG principles and strong corporate governance.
(LON: ACG) (OTCQX: ACGAF) (LON: ACGW) (Xetra: ACG) (Bond ISIN: NO0013414565)
For more information about ACG, please visit: www.acgmetals.com
View original content:https://www.prnewswire.com/news-releases/acg-metals-limited-q3-2025-ytd-operations-and-capital-structure-update-302588904.html
SOURCE ACG METALS LIMITED