STOCK TITAN

Aduro Clean Technologies Provides Update on NGP Pilot Plant Commissioning

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Positive)
Tags

Aduro Clean Technologies (Nasdaq: ADUR) provided an update on commissioning of its Next Generation Process (NGP) Pilot Plant in London, Ontario on Oct. 30, 2025. The plant advanced from Phase 1 into Phase 2 commissioning, with major modules—extruder, Zeton-fabricated process skids, and Siemens automation—installed and progressing through staged commissioning.

Key milestones include extruder SAT completion, Zeton skids FAT passed and delivered, Siemens integration of automation, and planned wet runs and process tuning through mid-December 2025. Data will inform an 8,000 ton/year demonstration plant design.

Aduro Clean Technologies (Nasdaq: ADUR) ha fornito un aggiornamento sulla messa in servizio del suo Next Generation Process (NGP) Pilot Plant a London, Ontario, il 30 ottobre 2025. L'impianto è passato dalla Fase 1 alla Fase 2 della messa in servizio, con i moduli principali — estrusore, skid di processo fabbricati da Zeton e automazione Siemens — installati e in avanzamento con una messa in servizio a fasi.

Principali traguardi includono il completamento SAT dell'estrusore, il FAT dei skid Zeton superato e fornito, l'integrazione dell'automazione Siemens, e i wet runs pianificati e la messa a punto del processo fino a metà dicembre 2025. I dati informeranno il design di un impianto dimostrativo da 8.000 tonnellate/anno.

Aduro Clean Technologies (Nasdaq: ADUR) proporcionó una actualización sobre la puesta en marcha de su Planta Piloto de Proceso de Nueva Generación (NGP) en London, Ontario, el 30 de octubre de 2025. La planta avanzó de la Fase 1 a la Fase 2 de la puesta en marcha, con los módulos principales — extrusora, skids de proceso fabricados por Zeton y automatización Siemens — instalados y avanzando en una puesta en marcha por etapas.

Los hitos clave incluyen la finalización SAT de la extrusora, el FAT de los skids Zeton aprobado y entregado, la integración de la automatización de Siemens, y las pruebas en húmedo planificadas y el ajuste del proceso hasta mediados de diciembre de 2025. Los datos informarán el diseño de una planta de demostración de 8.000 toneladas/año.

Aduro Clean Technologies (나스닥: ADUR)는 런던, 온타리오에서 열린 차세대 공정(NGP) 파일럿 플랜트의 커미셔닝 업데이트를 2025년 10월 30일에 제공했습니다. 이 공장은 Fase 1에서 Fase 2의 커미셔닝으로 진행되었으며, 주요 모듈인 압출기, Zeton 제작 프로세스 스키드, 및 Siemens 자동화가 설치되어 계단식 커미셔닝이 진행 중입니다.

주요 이정표로는 압출기의 SAT 완료, Zeton 스키드FAT 합격 및 납품, Siemens 자동화의 통합, 2025년 12월 중순까지의 습식 운전 및 공정 조정이 포함되며, 데이터는 연간 8,000톤 규모의 데모 플랜트 설계에 정보를 제공할 것입니다.

Aduro Clean Technologies (Nasdaq: ADUR) a fourni une mise à jour sur la mise en service de sa Pilote de Processus de Nouvelle Génération (NGP) à London, Ontario, le 30 octobre 2025. L'usine est passée de la Phase 1 à la Phase 2 de la mise en service, avec les principaux modules — extrudeuse, skid de procédé fabriqué par Zeton et automatisation Siemens — installés et en progression dans une mise en service par étapes.

Les jalons clés comprennent l'achèvement SAT de l'extrudeuse, le FAT des skid Zeton passé et livré, l'intégration de l'automatisation Siemens, et des essais humides planifiés et l'ajustement du procédé jusqu'à mi-décembre 2025. Les données guideront la conception d'une usine de démonstration de 8.000 tonnes/an.

Aduro Clean Technologies (Nasdaq: ADUR) hat am 30. Oktober 2025 ein Update zur Inbetriebnahme seiner Next Generation Process (NGP) Pilotanlage in London, Ontario gegeben. Die Anlage schreitet von Phase 1 zu Phase 2 der Inbetriebnahme voran, mit installierten Hauptmodulen — Extruder, Zeton-gefertigte Prozess-Skids und Siemens-Automatisierung — und läuft mit gestaffelter Inbetriebnahme.

Zu den wichtigsten Meilensteinen gehören der SAT-Abschluss des Extruders, der FAT der Zeton-Skids bestanden und geliefert, die Integration der Siemens-Automatisierung sowie geplante Nassläufe und Prozessabstimmung bis Mitte Dezember 2025. Die Daten werden das Design einer Demonstrationsanlage mit 8.000 Tonnen pro Jahr informieren.

أدو رو كلين تكنولوجيز (ناسداك: ADUR) قدمت تحديثاً حول التشغيل التجريبي لعملية الجيل التالي (NGP) لمصنعها التجريبي في لندن، أونتاريو في 30 أكتوبر 2025. تقدمت المنشأة من المرحلة 1 إلى المرحلة 2 من التشغيل، مع تثبيت الوحدات الرئيسية — آلة البثق، وحدات عملية مصنعة من Zeton، وأتمتة سيمنز — وتتبّع التشغيل على مراحل.

تشمل المعالم الرئيسية إكمال SAT لآلة البثق، اجتياز وتوريد FAT للوحدات المصغرة من Zeton، دمج أتمتة سيمنز، وتجارب مبللة مخطط لها وتعديل العملية حتى منتصف ديسمبر 2025. ستُستخدم البيانات لتوجيه تصميم مصنع عرض بسعة 8,000 طن/سنة.

Positive
  • Moved from Phase 1 into Phase 2 commissioning (Oct 2025)
  • Extruder completed Site Acceptance Testing (SAT)
  • Zeton modular skids passed Factory Acceptance Testing (FAT) and delivered
  • Siemens completed automation configuration and system integration
  • Pilot data to inform 8,000 tons/year Demonstration Plant design
Negative
  • None.

Insights

NGP pilot plant moved into Phase 2 commissioning; core systems installed and key acceptance tests completed, preparing for integrated operations.

The update describes progression from assembly to system integration, with the extruder completing Site Acceptance Testing and Zeton skids having passed Factory Acceptance Testing. Siemens has configured the automation network and integrated the extruder and utilities, enabling staged commissioning activities such as sequential testing, wet runs, and process tuning that aim to validate continuous operation of the Hydrochemolytic™ process.

Progress depends on successful integrated runs, reliable data acquisition, and operator readiness; risks include potential delays during wet runs, unresolved control tuning, or integration issues that would push timelines. The company plans operator training and procedure development during commissioning, which supports readiness for extended operation campaigns and the design basis for the announced demonstration plant with initial capacity of 8,000 tons per year.

Watch for completion of Phase 2 activities through November into mid-December 2025, successful extended operation campaigns, and published mass/energy balance and yield data that will inform the Demonstration Plant design; these milestones will materially clarify technical validation and next-stage project timing.

LONDON, Ontario, Oct. 30, 2025 (GLOBE NEWSWIRE) -- Aduro Clean Technologies Inc. (“Aduro” or the “Company”) (Nasdaq: ADUR) (CSE: ACT) (FSE: 9D5), a clean technology company using the power of chemistry to transform lower value feedstocks, like waste plastics, heavy bitumen, and renewable oils, into resources for the 21st century, today provides an update on the progress of the Next Generation Process (NGP) Pilot Plant.

Highlights of Ongoing Commissioning Progress

  • On-schedule progression: The NGP Pilot Plant remains on schedule, having advanced from Phase 1 to Phase 2 commissioning as planned.
  • Commissioning of core systems underway: All major modules, including the extruder, Zeton-fabricated process skids, and Siemens automation network, are now installed at the London, Ontario facility and are progressing through staged commissioning.
  • System validation milestones achieved: The extruder successfully completed Site Acceptance Testing (SAT); Zeton skids passed Factory Acceptance Testing (FAT); and Siemens is continuing work on automation system commissioning alongside physical equipment.
  • Phase 2 commissioning focus: Current activities include sequential testing, subsystem verification, wet runs, and process tuning through November and into mid-December 2025, preparing the plant for integrated operation.
  • Operator training and procedures: Commissioning activities also include planned operator training and development of standardized operating procedures, ensuring readiness for continuous plant operation and future scale-up phases.

The NGP Pilot Plant is a key step in the Company’s scale-up pathway, designed to validate Hydrochemolytic™ Technology in continuous operation, establish operating parameters across target feedstocks, and produce product samples and quality data for customer evaluation. It will confirm mass and energy balances, yields, and controllability, supply data to support environmental assessments and lifecycle analyses, support operator training and procedures, and generate the key data to inform the design basis and integration approach for the previously announced demonstration plant with an initial capacity of 8,000 tons per year.

All three main systems are now onsite at the recently expanded Aduro laboratory facilities in London, Ontario, and commissioning has advanced into its next phase. Since the last project update, the NGP Pilot Plant moved from Phase 1 into Phase 2 commissioning. Phase 1, which began in September 2025, focused on assembly and installation of major systems, mechanical completion, and verification of utilities and communications. During this period, the extruder system was installed, commissioned, and successfully completed its Site Acceptance Test (SAT). The modular process skids fabricated by Zeton Inc. also completed Factory Acceptance Testing (FAT) prior to shipment and have since been delivered to site. Siemens Canada completed configuration of the automation, control, and communication systems, and integrated the extruder systems, utilities, and ancillary systems into an integrated control network. Additional work included connection of plant utilities, electrical systems, and safety interlocks, ensuring full readiness for process commissioning. Assembly and integration activities continue as the plant progresses through Phase 2 commissioning.

The commissioning roadmap continues to follow a structured progression. Phase 2 commissioning, which began in October 2025, focuses on integrated operations, wet runs, and process tuning. These activities will continue through November and into mid-December, after which the Pilot Plant will move toward final preparation for extended operation campaigns.

Key partners of Aduro continue to play a central role in supporting the commissioning phase. Zeton Inc., the engineering, and fabrication partner that completed and delivered the modular process skids, remains actively engaged during integration and commissioning. Siemens Canada installed the plant’s automation and control systems and is supporting calibration and validation to ensure reliable process performance and proper data acquisition. These coordinated efforts provide the framework for a safe and efficient start-up.

“This milestone underscores the progress of Team Aduro,” said Ofer Vicus, Chief Executive Officer of Aduro. “The NGP Pilot Plant represents the first-in-kind implementation of our Hydrochemolytic™ Technology, and seeing it move from construction into commissioning is deeply rewarding for everyone involved. This milestone reflects the dedication and collaboration across our operations, research, and senior leadership teams, people who have worked with relentless focus to bring us to this point. The data and experience gained during this process will provide critical insight into system performance, feedstock segregation, environmental footprint, and continuous improvement, all of which will inform the design, fabrication, and commissioning of our Demonstration Plant and bring us closer to commercialization. We are also grateful to our partners, Zeton and Siemens, whose expertise and collaboration have been instrumental in achieving this progress.”

“The Pilot Plant represents a complex integration of equipment and process systems, and I am very pleased with the coordinated effort across engineering, operations, and safety teams,” added David Weizenbach, Chief Operating Officer of Aduro. “As we progress through phase 2 commissioning, our focus remains on verifying performance, ensuring reliability, and completing operator training so that we enter the next stage of operation with confidence.”

About Aduro Clean Technologies

Aduro Clean Technologies is a developer of patented water-based technologies to chemically recycle waste plastics; convert heavy crude and bitumen into lighter, more valuable oil; and transform renewable oils into higher-value fuels or renewable chemicals. The Company’s Hydrochemolytic™ technology relies on water as a critical agent in a chemistry platform that operates at relatively low temperatures and cost, a game-changing approach that converts low-value feedstocks into resources for the 21st century.

For further information, please contact:

Abe Dyck, Head of Corporate Development / Investor Relations
ir@adurocleantech.com
+1 226 784 8889

KCSA Strategic Communications
Jack Perkins, Senior Vice President
aduro@kcsa.com

Forward-Looking Statements

This news release contains forward-looking statements within the meaning of applicable securities laws. All statements other than statements of historical fact may be forward-looking statements. Forward-looking statements are often, but not always, identified by words such as “expects,” “anticipates,” “believes,” “intends,” “estimates,” “potential,” “plans,” “projects,” “targets,” “forecasts,” “may,” “will,” “should,” or similar expressions.

In this news release, forward-looking statements include, but are not limited to, statements relating to the progress, timing, and objectives of the Pilot Plant Program, the advancement of Phase 2 commissioning and subsequent validation activities, anticipated outcomes from extended operation campaigns, and the expected development, design, and timing of the Demonstration Plant.

These forward-looking statements are based on assumptions and estimates made by the Company in light of its experience and its perception of historical trends, current conditions, and expected future developments. Such statements are subject to a number of known and unknown risks, uncertainties, and other factors that could cause actual results or events to differ materially from those expressed or implied by such forward-looking statements. These factors include, but are not limited to, risks related to technology development, operational execution, supply chain logistics, regulatory approvals, financing availability, and other risks as described in the Company’s filings with Canadian securities regulators and the U.S. Securities and Exchange Commission.

Readers are cautioned not to place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statements, except as required by applicable securities laws.

PR170 Aduro Pilot Plant Commissioning Update

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/c9d915d2-99b6-44db-ac3f-a73da989e142


FAQ

What did Aduro (ADUR) announce about the NGP Pilot Plant on October 30, 2025?

Aduro said the NGP Pilot Plant advanced to Phase 2 commissioning, with major modules installed and system commissioning underway.

What are the commissioning timelines for Aduro's NGP Pilot Plant (ADUR)?

Phase 2 activities include sequential testing, wet runs, and process tuning through November and mid-December 2025 before extended operations.

Which partners supported Aduro's NGP Pilot Plant commissioning (ADUR)?

Aduro named Zeton (modular process skids) and Siemens Canada (automation and integration) as primary partners.

What commissioning milestones has Aduro (ADUR) achieved so far?

The extruder completed SAT, Zeton skids passed FAT and were delivered, and Siemens completed automation configuration and integration.

How will Aduro use data from the NGP Pilot Plant (ADUR)?

The company will use pilot data to validate operations, confirm mass and energy balances, and inform the 8,000 ton/year Demonstration Plant design.
Aduro Clean Tech

OTC:ACTHF

ACTHF Rankings

ACTHF Latest News

ACTHF Stock Data

12.03M
Bituminous Coal and Lignite Surface Mining
Mining, Quarrying, and Oil and Gas Extraction
CA