Austral Gold (OTCQB: AGLDF) reported significant progress in the refurbishment of its 100% owned Casposo Plant in Argentina. The company is targeting plant commissioning for August 2025, with commercial operations expected to begin in the second half of 2025.

Key completed activities include primary crusher refurbishment, SAG engine repair, and modifications to piping and ducts. Ongoing work includes SAG mill relining, installation of new hydrocyclones, and filter band refurbishment. The company has already hired 55 employees and plans to increase the workforce to 116 employees by August.

Austral Gold is preparing to commence toll processing in November 2025 under an agreement with Challenger Gold, while an independent consultant advances a technical report compliant with NI 43-101 and JORC 2012 standards to evaluate processing Casposo's own mineralized material.

Loading...
Loading translation...

Positive

  • Plant refurbishment is on schedule for August 2025 commissioning
  • Several key components already completed including primary crusher and SAG engine repair
  • Workforce expansion from 55 to 116 employees demonstrates operational readiness
  • Local community engagement through training programs for plant operators
  • Toll processing agreement with Challenger Gold secured for November 2025

Negative

  • Some critical components still pending completion including SAG mill relining and hydrocyclone installation
  • Technical report for processing own mineralized material still under development

News Market Reaction 1 Alert

-15.73% News Effect

On the day this news was published, AGLDF declined 15.73%, reflecting a significant negative market reaction.

Data tracked by StockTitan Argus on the day of publication.

  • Casposo Plant refurbishment steadily advancing and nearing completion

  • Commissioning targeted for August 2025

  • Commercial operations on track to commence during second half of 2025

Sydney, Australia--(Newsfile Corp. - July 29, 2025) - Austral Gold Limited (ASX: AGD) (TSXV: AGLD) (OTCQB: AGLDF) ("Austral" or the "Company"), an established gold producer, is pleased to provide an update on the refurbishment of its 100% owned Casposo Plant, following the previous update release on 30 April 2025.

Austral Gold's Chief Executive Officer, Stabro Kasaneva, said: "We are pleased with the progress on the refurbishment of the Casposo Plant in Argentina, with commissioning targeted for August 2025. In parallel, our independent consultant continues to advance a technical report prepared that complies with NI 43-101 and JORC 2012 standards to assess the feasibility of processing Casposo's own mineralised material. We remain on track to commence toll processing in November 2025 under the Toll Processing Agreement ("the Agreement") with ASX-listed Challenger Gold."

Refurbishment Plant Overview

Most of the key activities scheduled for Q2 2025 have been completed, with the remainder underway and expected to be finalised in the first half of August, ahead of commissioning.

Status of Q2 2025 planned activities:

  • Primary crusher refurbishment: Completed (Figure 1).
  • SAG mill relining: Underway; expected to be completed with recently arrived materials.
  • SAG engine repair: Completed (Figure 2).
  • Installation of new hydrocyclones: Underway; awaiting vendor's committed delivery date.
  • Engines and reducers for leaching tanks and CCD's repair: Completed (Figure 3).
  • Filter band refurbishment: Underway; all purchased materials received.
  • Modifications and improvement of piping and ducts: Completed.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_002.jpg

Figure 1: Primary Crusher (Area 100). The Primary Crusher has been completed and is ready for operation. Installation of a sampling tower is currently underway in this area to improve grade control of the material to be sourced from the Hualilán Project.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_002full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_003.jpg

Figure 2: SAG Mill (Area 200). The SAG mill engine, part of the Grinding Circuit, has been repaired, and the inching system was successfully tested.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_003full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_004.jpg

Figure 3: Leaching Tanks (Area 300). The engines and reducers for the leaching tanks and CCDs have been repaired.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_004full.jpg

Main works planned before Commissioning:

  • Finalise SAG mill relining and complete its full installation.

  • Complete Installation of new hydrocyclones.

  • Finalise Filter band refurbishment.

  • Complete testing of the Plant's electrical circuits.

In addition, the Company is progressing well with its recruitment efforts, with 55 employees currently on board. During August, the workforce is expected to increase by approximately 61 employees, bringing the total headcount to 116. As part of its commitment to local engagement, the Company delivered a targeted three-day training program in the Calingasta Village, aimed at identifying potential candidates and supporting the development of a skilled local workforce for plant operator roles.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_005.jpg

Figure 4: Training Course in Calingasta Village to recruit local plant operators.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/690/260627_69c56723644c4846_005full.jpg

About Austral Gold

Austral Gold is a growing gold and silver mining producer building a portfolio of quality assets in the Americas based on three strategic pillars: production, exploration and equity investments. Austral continues to lay the foundation for its growth strategy by advancing its attractive portfolio of producing and exploration assets.

For more information, please visit the Company's website at www.australgold.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Release approved by the Company's Chief Executive Officer of Austral Gold, Stabro Kasaneva.

For additional information, please contact:

David HwangJose Bordogna
Joint Company SecretaryChief Financial Officer and Joint Company Secretary
Austral Gold LimitedAustral Gold Limited
david@confidantpartners.comjose.bordogna@australgold.com
+61 433 292 290 +61 466 892 307

 

Forward-Looking Statements

Statements in this announcement that are not historical facts are forward-looking statements. Forward-looking statements are statements that are not historical, and consist primarily of projections - statements regarding future plans, expectations and developments. Words such as "expects", "intends", "plans", "may", "could", "potential", "should", "anticipates", "likely", "believes" and words of similar import tend to identify forward-looking statements. Forward-looking statements in this announcement include statements regarding our expectations for the refurbishment of the Casposo Plant in Argentina, our independent consultant continues to advance a technical report prepared that complies with NI 43-101 and JORC 2012 standards to assess the feasibility of processing Casposo's own mineralised material, the projected increase of approximately 61 employees at Casposo during August 2025, and our expectation that we can continue to lay the foundation for our growth strategy by advancing our attractive portfolio of producing and exploration assets.

All of these forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those expressed or implied, including, without limitation, uncertainty of exploration programs, development plans and cost estimates, commodity price fluctuations; political or economic instability and regulatory changes; currency fluctuations, the state of the capital markets, uncertainty in the measurement of mineral resources and reserves and other risks and hazards related to the exploration of a mineral property, and the availability of capital and a skilled workforce. You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. Austral cannot assure you that actual events, performance or results will be consistent with these forward-looking statements, and management's assumptions may prove to be incorrect. Austral's forward-looking statements reflect current expectations regarding future events and operating performance and speak only as of the date hereof and Austral does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, you should not place undue reliance on forward-looking statements.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/260627

FAQ

When will Austral Gold's Casposo Plant begin operations in 2025?

The Casposo Plant is scheduled for commissioning in August 2025, with commercial operations expected to begin in the second half of 2025 and toll processing starting in November 2025.

What is the current status of AGLDF's Casposo Plant refurbishment?

The plant refurbishment has completed several key components including primary crusher refurbishment and SAG engine repair, with remaining work on SAG mill relining, hydrocyclones installation, and filter band refurbishment to be completed by August 2025.

How many employees will Austral Gold hire for the Casposo Plant?

Austral Gold currently has 55 employees and plans to increase the workforce to 116 employees by August 2025, including locally trained plant operators from Calingasta Village.

What is the agreement between Austral Gold and Challenger Gold for the Casposo Plant?

Austral Gold has a Toll Processing Agreement with Challenger Gold, scheduled to commence toll processing operations in November 2025.

What technical standards is Austral Gold following for the Casposo project?

Austral Gold is working with an independent consultant to prepare a technical report that complies with both NI 43-101 and JORC 2012 standards for processing Casposo's mineralized material.
Austral Gold

OTC:AGLDF

AGLDF Rankings

AGLDF Latest News

AGLDF Stock Data

25.72M
101.63M
83.34%
0.07%
Other Precious Metals & Mining
Basic Materials
Link
Australia
Sydney