Amaroq (OTCQX: AMRQF) reported sequential operational improvements at the Nalunaq gold mine with gold production of ~5,000 oz to 7 Oct 2025, and processing running ahead of expectations. A double shift was implemented at the plant in late Q3 2025. A planned four-week commissioning shutdown is expected mid‑October 2025 to complete automation of the gravity circuit and major civil works for phase 1. Phase 2 (flotation circuit) construction will restart in December 2025 and continue to end of Q1 2026. The company targets 300 t/d nameplate throughput by year‑end 2025. Exploration: surface and underground drilling at Nalunaq and a 4,804 m programme at Nanoq completed; assays and a Mineral Resource Update are pending (Q4 2025 assays; MRE due Q1 2026).

Amaroq (OTCQX: AMRQF) ha riportato progressive migliorie operative presso la miniera d'oro Nalunaq con una produzione d'oro di ~5.000 oz al 7 ottobre 2025, e il processo sta avanzando oltre le aspettative. È stato implementato un doppio turno presso l'impianto alla fine del terzo trimestre 2025. È previsto un fermo di quattro settimane per la messa in servizio a metà ottobre 2025 per completare l'automazione del circuito di gravità e i principali lavori civili della fase 1. La fase 2 (circuito di flottazione) riprenderà a dicembre 2025 e continuerà fino alla fine del primo trimestre 2026. L'azienda punta a 300 t/d di capacità nominale entro la fine del 2025. Esplorazione: perforazioni superficiali e speleologiche a Nalunaq e un programma di 4.804 m a Nanoq completato; i risultati e un aggiornamento delle riserve minerarie sono in attesa (analisi Q4 2025; MRE previsto Q1 2026).

Amaroq (OTCQX: AMRQF) informó mejoras operativas secuenciales en la mina de oro Nalunaq con producción de oro de ~5,000 oz hasta el 7 de octubre de 2025, y el procesamiento avanzando por encima de las expectativas. Se implementó un segundo turno en la planta a finales del tercer trimestre de 2025. Se espera un cierre de puesta en marcha de cuatro semanas a mediados de octubre de 2025 para completar la automatización del circuito de gravedad y las obras civiles principales para la fase 1. La fase 2 (circuito de flotación) se reanudará en diciembre de 2025 y continuará hasta el final del primer trimestre de 2026. La empresa apunta a 300 t/d de capacidad nominal para finales de 2025. Exploración: perforación superficial y subterránea en Nalunaq y un programa de 4,804 m en Nanoq completado; se esperan ensayos y una Actualización de Recursos Minerales (MRE) para (ensayos Q4 2025; MRE previsto para Q1 2026).

Amaroq (OTCQX: AMRQF) Nalunaq 금광에서 순차적인 운용 개선을 보고했으며 2025년 10월 7일까지의 금 생산량 약 5,000 oz, 처리 공정은 예상을 상회하고 있습니다. 2025년 3분기 말에 플랜트에서 이중 교대를 도입했습니다. 네 주간의 시운전 중단이 2025년 10월 중순에 예정되어 있으며 중력 회로의 자동화 및 1단계의 주요 토목 공정을 완료합니다. 2단계(선광 회로) 건설은 2025년 12월에 재개되어 2026년 1분기 말까지 계속됩니다. 회사는 2025년 말까지 일일 300톤의 정격 처리량을 목표로 합니다. 탐사: Nalunaq의 표면 및 지하 드릴링과 Nanoq의 4,804 m 프로그램이 완료되었으며, 분석 및 광물 자원 업데이트가 보류 중입니다(Q4 2025 분석; MRE는 2026년 Q1 예정).

Amaroq (OTCQX: AMRQF) a rapporté des améliorations opérationnelles successives à la mine d'or Nalunaq avec une production d'or d'environ 5 000 oz au 7 octobre 2025, et un traitement qui évolue au-delà des attentes. Un double poste a été mis en place à l'usine à la fin du troisième trimestre 2025. Une fermeture de mise en service de quatre semaines est prévue à la mi-octobre 2025 pour finaliser l'automatisation du circuit de gravité et les principaux travaux civils de la phase 1. La phase 2 (circuit de flottation) reprendra en décembre 2025 et se poursuivra jusqu'à la fin du premier trimestre 2026. L'entreprise vise 300 t/j de capacité nominale d'ici la fin de 2025. Exploration : forage en surface et en underground à Nalunaq et un programme de 4 804 m à Nanoq achevé ; des essais et une Mise à jour des Ressources Minérales (MRE) sont en attente (essais du Q4 2025 ; MRE attendu au Q1 2026).

Amaroq (OTCQX: AMRQF) meldete sequentielle operative Verbesserungen bei der Nalunaq-Goldmine mit Goldproduktion von ca. 5.000 Unzen bis zum 7. Oktober 2025, und die Verarbeitung läuft besser als erwartet. Im späten Q3 2025 wurde eine Doppelschicht in der Anlage eingeführt. Eine geplante vierwöchige Inbetriebnahmeunterbrechung wird voraussichtlich Mitte Oktober 2025 durchgeführt, um die Automatisierung des Gravity-Circuits und die größeren zivilen Arbeiten für Phase 1 abzuschließen. Phase 2 (Flotationskreis) Bau wird im Dezember 2025 wieder aufgenommen und bis Ende Q1 2026 fortgesetzt. Das Unternehmen strebt 300 t/d Nennleistung bis Ende 2025 an. Exploration: Oberflächen- und Untertagebohrungen bei Nalunaq und ein 4.804 mProgramm bei Nanoq abgeschlossen; Proben und eine Mineralressourcenschätzung (MRE) stehen aus (Q4 2025 Proben; MRE fällig Q1 2026).

Amaroq (OTCQX: AMRQF) أبلغت عن تحسن تشغيلي متتالٍ في منجم Nalunaq للذهب مع إنتاج ذهب نحو 5,000 أوقية حتى 7 أكتوبر 2025، والتجهيزات تعمل بشكل يتجاوز التوقعات. تم تنفيذ ورديتين في المحطة في أواخر الربع الثالث من 2025. من المتوقع إغلاق تشغيل لمدة أربعة أسابيع في منتصف أكتوبر 2025 لإكمال أتمتة دائرة الجاذبية وأعمال مدنية رئيسية للمرحلة 1. سيتم إعادة تشغيل البناء في المرحلة 2 (دائرة الفصل) في ديسمبر 2025 وسيستمر حتى نهاية الربع الأول من 2026. تستهدف الشركة سعة اسمية 300 طن/اليوم بحلول نهاية عام 2025. الاستكشاف: حفر سطحي وتحت الأرض في Nalunaq وبرنامج من 4,804 م في Nanoq مكتمل؛ النتائج وتحديث موارد المعادن (MRE) في انتظارها (نتائج Q4 2025؛ MRE مقرر Q1 2026).

Amaroq (OTCQX: AMRQF) 报告了 Nalunaq 金矿的连续运营改进,截至 2025 年 10 月 7 日的金产量约为 5,000 oz,加工进展超出预期。在 2025 年晚些时候第三季度末,工厂实施了双班制。计划在 2025 年 10 月中旬进行 为期四周的调试停工,以完成重力回路的自动化和第一阶段的主要土建工作。第二阶段(浮选回路)将于 2025 年 12 月重新启动,并将持续至 2026 年第一季度末。公司目标是在 2025 年底实现 每日产能 300 吨的额定吞吐量。勘探: Nalunaq 的地表和地下钻探,以及 Nanoq 的 4,804 m 计划已完成;分析与矿产资源更新待出炉(Q4 2025 的分析;MRE 预计在 Q1 2026)。

Positive
  • Gold production ~5,000 oz to 7 Oct 2025
  • Double shift at processing plant implemented ahead of schedule
  • Targeted 300 t/d nameplate throughput by year-end 2025
  • Completed 4,804 m drilling programme at Nanoq
Negative
  • Planned four-week shutdown for commissioning in third week October 2025
  • Phase 2 flotation work restarts in December and extends to end Q1 2026
  • Assay results and Mineral Resource Update remain pending (Q4 2025/Q1 2026)
  • Updated 2025 production guidance deferred until post‑shutdown (around 14 Nov 2025)

Reykjavík, Oct. 07, 2025 (GLOBE NEWSWIRE) -- Amaroq Ltd.(“Amaroq” or the “Company”)

Operational update

Sequential improvements at Nalunaq continue with production ahead of expectations

TORONTO, ONTARIO – 7 October 2025 – Amaroq Ltd. (AIM, TSX-V, NASDAQ Iceland: AMRQ, OTCQX: AMRQF), an independent mine development corporation focused on unlocking Greenland’s mineral potential, is pleased to provide an update on operations at its flagship Nalunaq gold mine and on its 2025 exploration programme.

Highlights

Operations – continued sequential improvement and production running ahead of expectations

  • Commissioning of the processing plant and ramp-up of mining operations at Nalunaq, continued to deliver steady improvements through Q3 2025.
  • A double shift pattern was implemented at the processing plant ahead of schedule in the latter half of Q3 2025.
  • Gold production to 7th October 2025, has reached approximately 5000 oz, in line with the Company’s revised full-year 2025 production guidance.
  • The planned shutdown for commissioning activities is expected to commence in the third week of October 2025, with an estimated four-week duration. Once complete, the gravity circuit of the processing facility will be fully automated and major civil works completed, marking the completion of the majority of phase 1 works.
  • Phase 2 construction comprises the installation of the flotation circuit, including civil works, piping and electrical fitting, as well as equipment installation. The main elements of the building erection and civil engineering are already complete, with construction for the remainder of the work expected to take place inside the plant and restart in December 2025, after the shutdown and continue until the end of Q1 2026.
  • The Company remains on track to achieve nameplate throughput of 300 t/d by year-end 2025.
  • With gold production running ahead of expectations, updated year end 2025 production guidance will be published once the period of shutdown is confirmed, around the time of the Q3 2025 results on 14th November 2025.

Exploration – 2025 programme completed with resource upside identified and assay results underway

  • Surface drilling at Nalunaq’s South Deep Zone, ~250 m down-dip of the current Resource, has been completed providing growth potential. Results will feed into the next Mineral Resource Update, scheduled for Q1 2026.
  • Underground drilling at Nalunaq between the 725 and 790 levels has been completed, with continuous definition drilling programmes being planned from the 800 level upwards.
  • Both surface and underground campaigns are targeting the high-grade Main Vein and the parallel 75 Vein.
  • At Nanoq, the 4,804 m drilling programme was completed on schedule. Core is being logged and sampled for assay, with initial results expected during Q4 2025. Winterisation of the camp and equipment is underway, facilitating earlier start to a drilling programme next year.
  • Satellite gold exploration around Nalunaq, along with copper and critical metals programmes, has been completed, with assays pending.
  • The team has completed strategic site visits to the Black Angel and Kangerluarsuk projects, to assess logistics and development pathways, alongside a re-sampling programme. Market updates will follow in due course.

Eldur Olafsson, Chief Executive commented:
“I am pleased with the progress the team and our commissioning crews and contractors have delivered to date. We are ahead of schedule across all key workstreams, a clear testament to the strength and capability of Amaroq’s people. I look forward to providing a full update on operations and outlook at our Q3 2025 results on 14th November 2025.”

Enquiries:
Amaroq Ltd.        
Eldur Olafsson, Executive Director and CEO         

Ed Westropp, Head of BD and Corporate Affairs                         
+44 (0)7385 755711
ewe@amaroqminerals.com

Eddie Wyvill, Corporate Development                         
+44 (0)7713 126727
ew@amaroqminerals.com

Panmure Liberum Limited (Nominated Adviser and Corporate Broker)
Scott Mathieson
Freddie Wooding
+44 (0) 20 7886 2500

Canaccord Genuity Limited (Corporate Broker)
James Asensio
Harry Rees
+44 (0) 20 7523 8000

Camarco (Financial PR)
Billy Clegg
Elfie Kent
Fergus Young
+44 (0) 20 3757 4980

Further Information:
About Amaroq

Amaroq’s principal business objectives are the identification, acquisition, exploration, and development of gold and strategic metal properties in South Greenland. The Company’s principal asset is a 100% interest in the Nalunaq Gold mine. The Company has a portfolio of gold and strategic metal assets in Southern Greenland covering the two known gold belts in the region as well as advanced exploration projects at Stendalen and the Sava Copper Belt exploring for Strategic metals such as Copper, Nickel, Rare Earths and other minerals. Amaroq is continued under the Business Corporations Act (Ontario) and wholly owns Nalunaq A/S, incorporated under the Greenland Companies Act.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Inside Information

This announcement contains inside information for the purposes of Article 7 of the UK version of Regulation (EU) No. 596/2014 on Market Abuse ("UK MAR"), as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018, and Regulation (EU) No. 596/2014 on Market Abuse ("EU MAR").

Qualified Person Statement

The technical information presented in this press release has been approved by James Gilbertson CGeol, VP Exploration for Amaroq Ltd. and a Chartered Geologist with the Geological Society of London, and as such a Qualified Person as defined by NI 43-101.


FAQ

How much gold has Amaroq (AMRQF) produced at Nalunaq through 7 Oct 2025?

Amaroq reported approximately 5,000 oz of gold production to 7 Oct 2025.

When will Amaroq complete the Nalunaq processing shutdown and automated gravity circuit?

A planned four-week shutdown begins in the third week of Oct 2025 to finish gravity automation.

What is Amaroq's throughput target for Nalunaq by year‑end 2025 (AMRQF)?

The company remains on track to achieve 300 t/d nameplate throughput by year‑end 2025.

When will Amaroq (AMRQF) publish updated 2025 production guidance?

Updated year‑end 2025 production guidance is expected around the Q3 results on 14 Nov 2025.

What exploration results are pending for Amaroq's 2025 programmes?

Assays from Nalunaq surface/underground drilling and Nanoq core are pending, with initial Nanoq results expected in Q4 2025.

When is the next Mineral Resource Update for Nalunaq expected for AMRQF?

The next Mineral Resource Update is scheduled for Q1 2026 and will incorporate recent drilling.

What timeline is given for completion of Nalunaq phase 2 construction?

Phase 2 construction (flotation circuit) restarts in Dec 2025 and continues until end of Q1 2026.