Besra Gold Announces Significant Strides in Jugan Project BFS H1 2025 Jugan Project Update

(Very Positive)
Tags

Besra Gold Inc (ASX: BEZ) has reported significant progress in their Jugan Project's Bankable Feasibility Study (BFS) during H1 2025 in Sarawak, Malaysia. The company completed three metallurgical drillholes totaling 715 meters and advanced various technical studies including alternative processing assessments and geotechnical drilling.

Key developments include 9 out of 11 planned geotechnical drillholes completed, hydrogeological assessment planning, and preparations for Pilot Plant construction. The company is evaluating an innovative pyrolysis-based processing technology through Dundee Technologies as an alternative to conventional Pressure Oxidation (POX). The Pilot Plant project awaits only the renewal of Mining Lease ML 05/2012/1D to commence construction, with an expected four-month earthworks phase followed by seven months of construction.

Loading...
Loading translation...

Positive

  • Completion of 9 out of 11 planned geotechnical drillholes, strengthening mine planning confidence
  • Evaluation of alternative processing technology that could provide environmental and social benefits
  • Secured most local and departmental approvals for Pilot Plant construction
  • Strategic drilling approach providing validation of resource tonnage and grade estimates

Negative

  • Pilot Plant construction delayed pending Mining Lease ML 05/2012/1D renewal
  • Alternative processing technology still unproven for this specific application
  • Significant construction timeline ahead with 11 months total for earthworks and plant construction

News Market Reaction – BESAF

-60.00%
-60.00% Session move

In the trading session that priced this news, BESAF declined 60.00%, reflecting a significant negative market reaction.

Data tracked by StockTitan Argus on the day of publication.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

Highlights

H1 2025 has seen significant strides in derisking key Bankable Feasibility Study (BFS) workstreams for the Jugan Project during H1 2025 including:

  • Metallurgical test work.
  • Trialling alternative processing techniques.
  • Geotechnical assessment and tailings management studies.
  • Hydrogeological groundwater studies.
  • Mineral Resource Estimate update for Jugan, incorporating open-cut & underground, and
  • Pilot Plant construction commencement awaits approvals.

Melbourne, Victoria--(Newsfile Corp. - June 25, 2025) - Besra Gold Inc (ASX: BEZ) (Besra or the Company) is pleased to provide an update on the activities undertaken during H1 2025 at its flagship Jugan Project, located within the Bau Gold Field in Sarawak, Malaysia. These activities reflect an increasing pace of de-risking the Project and building the technical foundations of the key disciplines required to complete the Jugan BFS in the shortest practical timeframe. Specifically, these activities include:

Metallurgical Test Work and Alternative Processing Assessment

As part of further derisking and strengthening the basis for the Jugan BFS assumptions, three fully cored metallurgical drillholes have been completed, totalling 715 metres. Core from the two 300-metre down-dip holes have been dispatched to ALS Laboratories in Perth for advanced metallurgical test work. The third hole, drilled to 115 metres, has been sent to Minefill Services in Newcastle, New South Wales, for tailings characterisation, including paste fill trials to support design considerations for potential underground mining operations.

In parallel, selected core intervals are being sent to Dundee Technologies in Canada to evaluate an alternative, patented processing route to conventional Pressure Oxidation (POX). This pyrolysis-based technology targets beneficiation of concentrate in order to produce on-site doré, while simultaneously converting arsenic-bearing tailings into a stable, vitrified (glass-based) form. If proven viable, this process could provide additional, meaningful environmental and social benefits, further de-risking the development pathway at Jugan.

These three metallurgical drillholes were angled to follow the dip of the mineralised zone, allowing for continuous sampling through most of the ore body. This approach was chosen to ensure the core collected is representative within the main mineable depth range and so provide validation of both the resource tonnage and grade estimates. In addition to the studies outlined above, all 715 metres of core are currently undergoing elemental analysis to further validate the updated Jugan Resource Model (ASX release dated 31 March 2025). This "proofing" will enhance confidence in the continuity of mineralisation and future mine development planning. Final assay results from all three holes are expected shortly, with release to the market anticipated in July 2025.

Geotechnical Drilling and Analysis

Geotechnical drilling, a key input for the BFS mine planning, has advanced significantly during H1 2025, following the deployment of a second drill rig. Of the 11 diamond drillholes (totalling ~2,700 metres) planned in late 2024, nine have been completed, with the remaining two expected by end-June 2025. This program is fundamental to obtaining representative core samples to determine geotechnical design parameters for both open-pit and underground mine plan configurations.

Minegeotech Services, a Perth-based specialist mining engineering consultancy, has been engaged to lead the analytical geotechnical workstream. Its output will provide parameters for modelling slope stability, underground access development and stope design, as well as rock mass classification—all key elements for de-risking the Jugan development strategy.

Hydrogeological Assessment

Planning has commenced for hydrogeological investigations at Jugan to estimate water inflows associated with the proposed open-pit and underground mine developments. The program is expected to include surface-based geophysical surveys—specifically electromagnetic (EM) and resistivity methods—to delineate subsurface water-bearing structures. Based on the results, the Company plans to install up to three test dewatering bores and three monitoring bores at strategically selected locations.

This work is aimed at quantifying the dewatering requirements for future mining operations and developing a robust understanding of the potential impacts on the local aquifer system for both the open-pit and underground components.

Pilot Plant Approvals and Site Readiness

The Company has secured nearly all required local and departmental approvals to commence construction of the Jugan Pilot Plant. These include environmental and civil works clearances, with only the renewal of Mining Lease ML 05/2012/1D remaining as the final outstanding item before mobilisation can occur.

To prepare the site, five civil earthworks geotechnical drillholes were completed in June 2025 beneath the proposed ore stockpile zones. The results will inform ground preparation requirements and ensure slope stability, enabling efficient and compliant earthworks execution once lease renewal is confirmed. This proactive approach underscores Besra's commitment to project readiness and minimising lead time to construction.

Managing Director (North Borneo Gold Sdn Bhd - NBG) Matthew Antill said:

"We have made excellent progress with our drilling program to source core specifically required by the key technical disciplines that underpin our Jugan BFS critical-path workstreams.

The Pilot Plant is essentially construction-ready, with commencement of earthworks contingent only on the renewal of ML 05/2012/1D. Once granted, we anticipate a rapid mobilisation and completion of earthworks within four months, followed by a seven-month construction phase."

Importantly, our in-country operations have been supported throughout the recent changes in Board composition which have been seamless in respect of NBG's operational activities."

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3448/256807_1r.jpg

Rig 76 and Rig 38 on their final 300 metre holes for the 1,720 metre geotechnical drilling programme.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3448/256807_1.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3448/256807_2r.jpg

Civils Geotechnical holes completed this month to finalise Pilot Plant stockpile surface stability requirements (lower right).

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3448/256807_2.jpg

This announcement was authorised for release by David Potter, Chair of Besra Gold Inc.

Michael Higginson,
Company Secretary

N. America Contact:
James Hamilton
M +1-416-471-4494

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/256807

FAQ

What progress has Besra Gold made in the Jugan Project during H1 2025?

Besra completed three metallurgical drillholes (715 meters), advanced 9 of 11 geotechnical drillholes, and secured most approvals for Pilot Plant construction. They're also evaluating alternative processing technologies and conducting hydrogeological studies.

What is the timeline for Besra Gold's Pilot Plant construction at Jugan?

Once Mining Lease ML 05/2012/1D is renewed, the company expects 4 months for earthworks completion followed by 7 months of construction.

What new processing technology is Besra Gold (BEZ) evaluating for the Jugan Project?

Besra is evaluating a pyrolysis-based technology through Dundee Technologies as an alternative to conventional Pressure Oxidation (POX). This technology aims to produce on-site doré while converting arsenic-bearing tailings into a stable, vitrified form.

How many metallurgical drillholes has Besra Gold completed at Jugan in H1 2025?

Besra completed three fully cored metallurgical drillholes totaling 715 meters, with two 300-meter down-dip holes sent to ALS Laboratories and one 115-meter hole sent to Minefill Services.

What is the current status of Besra Gold's geotechnical drilling program at Jugan?

The company has completed 9 out of 11 planned diamond drillholes (approximately 2,700 meters total), with the remaining two holes expected to be completed by end-June 2025.