TSF1 Geotechnical Drilling Completed at Central Gawler Mill
Barton Gold (ASX:BGD, OTCQB:BGDFF) completed TSF1 geotechnical drilling at the Central Gawler Mill on November 3, 2025 to support the Stage 1 Definitive Feasibility Study (DFS) for the Challenger Gold Project.
The program comprised 5 sonic holes for material recovery, 24 CPTu holes, and 3 VST and 3 bulk density holes. Samples will be used for fine grinding testwork and to inform detailed mine design, equipment selection, and operating cost estimates for tailings recovery and processing.
Barton Gold (ASX:BGD, OTCQB:BGDFF) ha completato le trivellazioni geotecniche TSF1 presso il Central Gawler Mill il 3 novembre 2025 per supportare lo Studio di Fattibilità Definitiva della Stage 1 (DFS) per il Challenger Gold Project.
Il programma comprendeva 5 pozzi sonici per il recupero del materiale, 24 pozzi CPTu, e 3 sonde di densità bulk e 3 pozzi VST. I campioni saranno utilizzati per prove di macinazione fine e per informare la progettazione dettagliata della miniera, la selezione delle attrezzature e le stime dei costi operativi per il recupero e l'elaborazione dei fanghi di scarto.
Barton Gold (ASX:BGD, OTCQB:BGDFF) completó la perforación geotécnica TSF1 en Central Gawler Mill el 3 de noviembre de 2025 para respaldar el Estudio de Factibilidad Definitiva de la Fase 1 (DFS) para el Proyecto de Oro Challenger.
El programa comprendió 5 pozos sónicos para recuperación de material, 24 pozos CPTu y 3 pozos VST y 3 pozos de densidad a granel. Las muestras se utilizarán para pruebas de molienda fina y para informar el diseño detallado de la mina, la selección de equipos y las estimaciones de costos operativos para la recuperación y procesamiento de relaves.
Barton Gold (ASX:BGD, OTCQB:BGDFF)는 Central Gawler Mill에서 2025년 11월 3일에 TSF1 지질기술 시추를 완료하여 Challenger Gold Project를 위한 1단계 최종타당성조사(DFS)를 지원했습니다.
프로그램은 재료 회수를 위한 5개의 음향 구멍, 24 CPTu 구멍, 3 VST 및 3 벌크 밀도 구멍으로 구성되었습니다. 샘플은 미세 분쇄 시험에 사용되며 광산 설계의 세부 사항, 설비 선택 및 배수 처리 회수에 대한 운영비 추정치를 결정하는 데 활용됩니다.
Barton Gold (ASX:BGD, OTCQB:BGDFF) a terminé le forage géotechnique TSF1 au Central Gawler Mill le 3 novembre 2025 pour soutenir l’étude de faisabilité définitive de la phase 1 (DFS) pour le Challenger Gold Project.
Le programme comprenait 5 forages soniques pour la récupération du matériel, 24 forages CPTu et 3 forages VST et 3 forages de densité en vrac. Les échantillons seront utilisés pour les essais de broyage fin et pour éclairer la conception détaillée de la mine, la sélection des équipements et les estimations des coûts d’exploitation pour la récupération et le traitement des tailings.
Barton Gold (ASX:BGD, OTCQB:BGDFF) hat das geotechnische Bohrprogramm TSF1 am Central Gawler Mill am 3. November 2025 abgeschlossen, um die Stage-1-Definitive-Feasibility-Study (DFS) für das Challenger Gold Project zu unterstützen.
Das Programm umfasste 5 Sonic-Bohrungen zur Materialgewinnung, 24 CPTu-Bohrungen und 3 VST sowie 3 Bohrungen zur Bulk-Dichte. Proben werden für Feinmahltests verwendet und dazu genutzt, das detaillierte Minendesign, die Ausrüstungsauswahl und die Betriebskostenkalkulationen für die Rückgewinnung und Verarbeitung der Tailings zu informieren.
Barton Gold (ASX:BGD, OTCQB:BGDFF) أكملت حفر دراسية جيولوجية-هندسية TSF1 في Central Gawler Mill في 3 نوفمبر 2025 لدعم دراسة جدوى نهائية للمرحلة الأولى (DFS) لمشروع Challenger Gold.
اشتمل البرنامج على 5 آبار صوتية لاسترداد المادة، و24b آبار CPTu، و3 آبار VST و3 آبار كثافة إجمالية. ستُستخدم العينات في اختبارات الطحن الدقيق ولإبلاغ التصميم التفصيلي للمَناجم، واختيار المعدات، وتقديرات تكاليف التشغيل لاسترداد ومعالجة مخلفات الخام.
- None.
- None.
Samples collected for fine grinding testwork, mine design & costing
ADELAIDE, AU / ACCESS Newswire / November 3, 2025 / Barton Gold Holdings Limited (ASX:BGD)(OTCQB:BGDFF)(FRA:BGD3) (Barton or the Company) has completed TSF1 geotechnical drilling in support of a recently launched Definitive Feasibility Study for 'Stage 1' production (Stage 1 DFS) at the Company's South Australian Challenger Gold Project (Challenger). 1
The program included 5 sonic drill holes to recover TSF1 materials for lab testing, 24 holes for Cone Penetration Testing ( CPTu ) and further laboratory testing, and 3 holes each for vein shear testing (VST) and bulk density (BD) testing. Results will inform TSF1 detailed mine design, equipment selection, and operating cost estimates.

Figure 1 - TSF1 with completed CPT (red), sonic (green stars), VST / BD (orange) & AC / RC drill holes
Commenting on the TSF1 geotechnical drilling, Barton Managing Director Alexander Scanlon said:
"This drilling is the first of several production-related work programs completed for our 'Stage 1' production DFS at the Central Gawler Mill. The samples collected will be used for fine grinding testwork, and to inform key elements of mine design, equipment selection and operating costs for tailings recovery and processing."
Authorised by the Managing Director of Barton Gold Holdings Limited.
For further information, please contact:
Alexander Scanlon | Jade Cook |
About Barton Gold
Barton Gold is an ASX, OTCQB and Frankfurt Stock Exchange listed Australian gold developer targeting future gold production of 150,000ozpa with 2.2Moz Au & 3.1Moz Ag JORC Mineral Resources (79.9Mt @ 0.87g/t Au), brownfield mines, and
Competent Persons Statement & Previously Reported Information
The information in this announcement that relates to the historic Exploration Results and Mineral Resources as listed in the table below is based on, and fairly represents, information and supporting documentation prepared by the Competent Person whose name appears in the same row, who is an employee of or independent consultant to the Company and is a Member or Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM), Australian Institute of Geoscientists (AIG) or a Recognised Professional Organisation (RPO). Each person named in the table below has sufficient experience which is relevant to the style of mineralisation and types of deposits under consideration and to the activity which he has undertaken to quality as a Competent Person as defined in the JORC Code 2012 ( JORC ).
Activity | Competent Person | Membership | Status |
Tarcoola Mineral Resource (Stockpiles) | Dr Andrew Fowler (Consultant) | AusIMM | Member |
Tarcoola Mineral Resource (Perseverance Mine) | Mr Ian Taylor (Consultant) | AusIMM | Fellow |
Tarcoola Exploration Results (until 15 Nov 2021) | Mr Colin Skidmore (Consultant) | AIG | Member |
Tarcoola Exploration Results (after 15 Nov 2021) | Mr Marc Twining (Employee) | AusIMM | Member |
Tunkillia Exploration Results (until 15 Nov 2021) | Mr Colin Skidmore (Consultant) | AIG | Member |
Tunkillia Exploration Results (after 15 Nov 2021) | Mr Marc Twining (Employee) | AusIMM | Member |
Tunkillia Mineral Resource | Mr Ian Taylor (Consultant) | AusIMM | Fellow |
Challenger Mineral Resource (above 215mRL) | Mr Ian Taylor (Consultant) | AusIMM | Fellow |
Challenger Mineral Resource (below 90mRL) | Mr Dale Sims | AusIMM / AIG | Fellow / Member |
Wudinna Mineral Resource (Clarke Deposit) | Ms Justine Tracey | AusIMM | Member |
Wudinna Mineral Resource (all other Deposits) | Mrs Christine Standing | AusIMM / AIG | Member / Member |
The information relating to historic Exploration Results and Mineral Resources in this announcement is extracted from the Company's Prospectus dated 14 May 2021 or as otherwise noted, available from the Company's website at www.bartongold.com.au or on the ASX website www.asx.com.au. The Company confirms that it is not aware of any new information or data that materially affects the Exploration Results and Mineral Resource information included in previous announcements and, in the case of estimates of Mineral Resources, that all material assumptions and technical parameters underpinning the estimates, and any production targets and forecast financial information derived from the production targets, continue to apply and have not materially changed. In accordance with ASX Listing Rule 5.19.2, the Company further confirms that the material assumptions underpinning any production targets and the forecast financial information derived therefrom continue to apply and have not materially changed. The Company confirms that the form and context in which the applicable Competent Persons' findings are presented have not been materially modified from the previous announcements.
Cautionary Statement Regarding Forward-Looking Information
This document may contain forward-looking statements. Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "expect", "target" and "intend" and statements than an event or result "may", "will", "should", "would", "could", or "might" occur or be achieved and other similar expressions. Forward-looking information is subject to business, legal and economic risks and uncertainties and other factors that could cause actual results to differ materially from those contained in forward-looking statements. Such factors include, among other things, risks relating to property interests, the global economic climate, commodity prices, sovereign and legal risks, and environmental risks. Forward-looking statements are based upon estimates and opinions at the date the statements are made. Barton undertakes no obligation to update these forward-looking statements for events or circumstances that occur subsequent to such dates or to update or keep current any of the information contained herein. Any estimates or projections as to events that may occur in the future (including projections of revenue, expense, net income and performance) are based upon the best judgment of Barton from information available as of the date of this document. There is no guarantee that any of these estimates or projections will be achieved. Actual results will vary from the projections and such variations may be material. Nothing contained herein is, or shall be relied upon as, a promise or representation as to the past or future. Any reliance placed by the reader on this document, or on any forward-looking statement contained in or referred to in this document will be solely at the readers own risk, and readers are cautioned not to place undue reliance on forward-looking statements due to the inherent uncertainty thereof.
1 Refer to ASX announcements dated 29 September and 23 October 2025
* Refer to Barton Prospectus dated 14 May 2021 and ASX announcement dated 8 September 2025. Total Barton JORC (2012) Mineral Resources include 1,049koz Au (39.7Mt @ 0.82 g/t Au) in Indicated category and 1,186koz Au (40.2Mt @ 0.92 g/t Au) in Inferred category, and 3,070koz Ag (34.5Mt @ 2.80 g/t Ag) in Inferred category as a subset of Tunkillia gold JORC (2012) Mineral Resources.
SOURCE: Barton Gold Holdings Limited
View the original press release on ACCESS Newswire