Blue Moon Metals Awards EPC Contract for Nussir Processing Plant and Receives Approval of Waste Management Plan, Final Mine Plan and Extended Discharge Permit

(Moderate)
(Positive)
Tags

Blue Moon Metals (NASDAQ:BMM) announced key milestones for its Nussir copper-silver-gold project in Norway. The company awarded an EPC contract for the processing plant to MOMEK Services, secured approval of its Mine Waste Management Plan and updated operating plan, and confirmed that all material permits for construction and operations are in place.

Underground development has exceeded 2,000m, key tunnels are complete, and Blue Moon is targeting production in late 2027.

Loading...
Loading translation...

Positive

  • EPC contract awarded to MOMEK Services for Nussir processing plant civil, structural, mechanical and piping
  • Mine Waste Management Plan approved and discharge permit amended, satisfying final condition to start operations
  • All material permits secured for Nussir construction and operation under Norwegian law
  • Underground development at Nussir exceeds 2,000m, including key conveyor and silo tunnels
  • Company targets full-scale construction and production at Nussir in Q4 2027

Negative

  • None.

News Market Reaction – BMM

+2.56%
3 alerts
+2.56% News Effect
-6.5% Trough Tracked
+$13M Valuation Impact
$523.95M Market Cap
0.1x Rel. Volume

On the day this news was published, BMM gained 2.56%, reflecting a moderate positive market reaction. Argus tracked a trough of -6.5% from its starting point during tracking. Our momentum scanner triggered 3 alerts that day, indicating moderate trading interest and price volatility. This price movement added approximately $13M to the company's valuation, bringing the market cap to $523.95M at that time.

Data tracked by StockTitan Argus on the day of publication.

Market Context

This announcement confirms Nussir’s permitting framework is complete and construction is advancing, ...
Analysis

This announcement confirms Nussir’s permitting framework is complete and construction is advancing, targeting production in Q4 2027. History shows mixed share reactions to growth updates, so investors may watch execution pace and future funding needs carefully.

Key Figures

Target production start: Q4 2027 MOMEK employees: over 600 employees MOMEK revenue: EUR 100 million annual revenue +5 more
8 metrics
Target production start Q4 2027 Planned start of full‑scale production at Nussir
MOMEK employees over 600 employees MOMEK Group workforce supporting EPC contract
MOMEK revenue EUR 100 million annual revenue Approximate annual revenue of MOMEK Group
Underground development 2,000m Total underground development exceeded at Nussir by early June 2026
2026 development advance over 1,000m Underground development added since January 2026 at Nussir
Original discharge permit date January 15, 2016 Initial grant date of Nussir discharge permit
Prior amendment date November 30, 2021 Previous amendment to Nussir discharge permit
Operating plan approval date June 18, 2026 Norwegian Directorate of Mines approved updated operating plan

Historical Context

5 past events · Latest: May 15 (Positive)
Pattern 5 events
Date Event Sentiment 24h Move Catalyst
May 15 Springer claims acquisition Positive +0.1% Closed acquisition of adjacent tungsten claims with cash, shares and royalty.
May 15 Strategic appointments Neutral -8.1% Announced five senior hires to support U.S. projects and Nussir delivery.
May 6 Bought‑deal financing Positive +6.8% Closed C$156M bought‑deal share offerings to fund Nussir and other projects.
Apr 28 Springer claims acquisition Positive -9.2% Agreed to acquire nine unpatented Springer claims with cash, shares and GRR.
Apr 27 Nussir FID and offerings Positive -9.2% Approved Nussir construction FID and concurrent C$150M equity offerings.

24h Move is the share-price change in the day after each event; other market factors may also have contributed.

Pattern Detected

Recent history shows mixed reactions, with notable selloffs on expansionary news like acquisitions and major financing decisions.

Key Terms

epc contract, discharge permit, operating license, feasibility study
4 terms
epc contract technical
"Blue Moon has awarded MOMEK Services AS... an EPC contract for the civil, structural, mechanical"
An EPC contract is a single agreement where one firm is hired to design, buy the materials for, and build a large project — often delivering it ready to operate. For investors it matters because these contracts usually fix the price and schedule and shift most construction and performance risk to the contractor, much like hiring a general contractor to build a house for a set price and completion date.
discharge permit regulatory
"issued an Amendment to the Discharge Permit (originally granted January 15, 2016, previously amended"
A discharge permit is an official license that lets a company release water, air emissions, or other wastes into the environment under specific limits and conditions. For investors, it matters because having, losing, or needing to modify such a permit affects a business’s ability to operate, comply with rules, and control cleanup costs and fines—think of it like a traffic permit that dictates how, when and how much a company can “pour” into public spaces.
operating license regulatory
"an Operating License under the Minerals Act."
An operating license is an official permit from a government or regulatory body that allows a company to carry out specific business activities, such as selling products, running a facility, or providing services. For investors it matters because the license is often required for a company to earn revenue; losing, not obtaining, or facing restrictions on the license can stop operations or add costs, much like a business losing its driver’s license would be unable to legally drive its core activity.
feasibility study technical
"execution plan set out in the April 2026 Feasibility Study on the Project"
A feasibility study is an assessment that evaluates whether a proposed project or idea is practical and likely to succeed before investing significant time and resources. It considers factors like costs, potential benefits, and challenges, helping stakeholders decide if moving forward makes sense. Think of it as a detailed plan that gauges if a new venture is worth pursuing.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

TORONTO, June 24, 2026 /PRNewswire/ - Blue Moon Metals Inc. ("Blue Moon" or the "Company") (TSXV: MOON) (NASDAQ: BMM) is pleased to announce several significant milestones towards advancing its Nussir copper-silver-gold project ("Nussir" or the "Project") in the Hammerfest Municipality, Norway: a) the award of an engineering, procurement, and construction ("EPC") contract for the Project's processing plant, b) the approval of the Waste Management Plan by the Norwegian Environment Agency, together with a corresponding update to the Project's discharge permit c) the approval of the Project's updated mine operating plan from the Norwegian Directorate of Mines.

EPC CONTRACT – NUSSIR PROCESSING PLANT

Blue Moon has awarded MOMEK Services AS, a company within MOMEK Group, an EPC contract for the civil, structural, mechanical, and piping scope of the Nussir processing plant. The contract scope includes detailed design, construction of buildings, equipment foundations, structural steel, piping and pipe supports, and the balance of mechanical equipment not directly procured by Blue Moon, and installation of the Company supplied equipment. The award is consistent with the execution plan set out in the April 2026 Feasibility Study on the Project (the "Feasibility Study") and advances the Project towards full-scale construction and production in Q4 2027.

MOMEK Group is a leading Norwegian industrial group established in 1998, headquartered in Mo i Rana, with over 600 employees and annual revenue of approximately EUR 100 million. The group provides engineering, construction, mechanical installation, and fabrication services across the mining industry, oil and gas, renewable energy, and defense sectors, and holds ISO 9001, ISO 14001, and ISO 45001 certifications.

MINE WASTE MANAGEMENT PLAN APPROVAL AND UPDATED DISCHARGE PERMIT

In Q2-2026 the Norwegian Environment Agency approved the Mine Waste Management Plan for the Nussir project, which included a public comment period, and issued an Amendment to the Discharge Permit (originally granted January 15, 2016, previously amended November 30, 2021) incorporating the latest Mine Waste Management Plan. The approval satisfies the last outstanding regulatory condition precedent to the commencement of mine operations of the Nussir mine.

The Project holds all material permits for construction and operation, including an Extraction Permit under the Minerals Act, an approved Zoning Plan under the Planning and Building Act, a Discharge Permit under the Pollution Control Act, and an Operating License under the Minerals Act.

MINE OPERATING PLAN APPROVAL

On June 18, 2026, the Norwegian Directorate of Mines approved the updated operating plan for Nussir mine as part of the Operating license awarded previously under the Minerals Act. The operating plan provides the technical details for operation and closure of the mine. In early June, underground development at Nussir exceeded the 2,000m mark (over 1,000m since January 2026).  Additionally, the conveyor tunnel linking the decline to the orebody and the silo tunnel to feed the mill was completed, allowing construction of the ore conveyor system between the orebody and the silo to commence.

Christian Kargl-Simard, CEO of Blue Moon, stated: "The award of the EPC contract and the approval of our Waste Management Plan and updated operating plan represent three key milestones for the advancement of the Nussir Project. With our permitting framework now complete, our long-lead equipment on order, our mine decline advancing to the orebody, and our key construction contracts in place, we are on track to deliver production later in 2027."

Qualified Person

The technical and scientific information of this news release has also been reviewed and approved by Mr. Reza Ehsani, P.Eng., a Blue Moon Officer, and a non-Independent Qualified Person, as defined by NI 43-101.

About Blue Moon

Blue Moon is advancing 5 brownfield polymetallic projects, including the Nussir copper-silver-gold project in Norway, the NSG copper-zinc-gold-silver project in Norway, the Blue Moon zinc-gold-silver-copper project in the United States, the Springer tungsten-molybdenum project in the United States and the Apex germanium-gallium-copper project in the United States. All 5 projects are well located with existing local infrastructure including roads, power and historical infrastructure. Zinc, copper and tungsten are currently on the USGS and EU lists of metals critical to the global economy and national security, and germanium and gallium are also on the USGS list of critical metals. Major shareholders include Teck Resources Limited, funds managed by Oaktree Capital Management, Hartree Partners, LP, Wheaton Precious Metals, Altius Minerals Corporation, Baker Steel Resources Trust, LNS and Monial. More information is available on the Company's website (www.bluemoonmetals.com). 

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

CAUTIONARY DISCLAIMER - FORWARD LOOKING STATEMENTS

This news release includes "forward-looking statements" and "forward-looking information" within the meaning of applicable Canadian and U.S. securities laws. All statements included herein that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.

We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information and that it would be unreasonable to rely on such statements as creating legal rights regarding our future results or plans. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represents management's current expectations and are based on information currently available to management, and are subject to change after the date of this news release. We are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein.                                                                                                     

Forward-looking information is provided herein for the purpose of giving information about the Project and its expected impact. Readers are cautioned that such information may not be appropriate for other purposes.

A comprehensive discussion of other risks that impact Blue Moon can also be found in its public reports and filings which are available at www.sedarplus.ca.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/blue-moon-metals-awards-epc-contract-for-nussir-processing-plant-and-receives-approval-of-waste-management-plan-final-mine-plan-and-extended-discharge-permit-302809873.html

SOURCE Blue Moon Metals

FAQ

What did Blue Moon Metals (NASDAQ:BMM) announce about the Nussir EPC contract on June 24, 2026?

Blue Moon Metals awarded the Nussir processing plant EPC contract to MOMEK Services AS. According to Blue Moon, the scope covers detailed design, buildings, foundations, structural steel, piping, and installation of company-supplied equipment, aligning with the April 2026 feasibility study execution plan.

Which permits and approvals has Blue Moon Metals obtained for the Nussir project (BMM)?

Blue Moon Metals reports holding all material permits needed for Nussir construction and operations. According to Blue Moon, these include an Extraction Permit, approved Zoning Plan, Discharge Permit with amended Mine Waste Management Plan, and an Operating License with an updated mine operating plan in Norway.

How does the waste management plan approval affect Blue Moon Metals’ Nussir mine startup?

Approval of the Mine Waste Management Plan removes the last regulatory condition before Nussir operations. According to Blue Moon, the Norwegian Environment Agency approved the plan and amended the discharge permit, following a public comment period, enabling progression toward mine start-up activities.

How advanced is underground development at Blue Moon Metals’ Nussir project as of mid-2026?

Underground development at Nussir has surpassed 2,000 meters in early June 2026. According to Blue Moon, more than 1,000 meters were added since January 2026, and both the conveyor tunnel to the orebody and the silo tunnel feeding the mill are now completed.

When is Blue Moon Metals targeting first production from the Nussir copper project (BMM)?

Blue Moon Metals is targeting production from Nussir in late 2027. According to Blue Moon, the EPC award, completed permitting framework, advancing decline toward the orebody, and key construction contracts support the execution plan for full-scale construction and production in the fourth quarter of 2027.

Who is MOMEK Services AS, the EPC contractor for Blue Moon Metals’ Nussir plant?

MOMEK Services AS, part of MOMEK Group, is the EPC contractor for Nussir’s processing plant. According to Blue Moon, MOMEK Group is a Norwegian industrial firm with over 600 employees, around EUR 100 million in revenue, and ISO 9001, 14001, and 45001 certifications.