Borealis Mining Receives U.S. Forest Service Approval for Permit Modification; Prepares for Mine Restart in Q1 2026

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Positive)
Tags

Borealis Mining (OTC: BORMF) received U.S. Forest Service approval for a Minor Modification to its Borealis Plan of Operations, signed October 16, 2025, clearing a final regulatory step toward a full mine restart.

The modification adds 68.3 acres of disturbance (total approved area 549.7 acres) and permits expanded pit work, new waste facility development, road construction, and relocation of infrastructure. Borealis is debt-free, says it is fully financed, and plans contractor mobilization in December 2025–January 2026 with drill and blast activities in early January 2026.

Ongoing stockpile crushing and heap leach operations continue, with the ADR plant producing gold and silver recoveries to generate near-term revenues.

Borealis Mining (OTC: BORMF) ha ottenuto l'approvazione dal Servizio Forestale degli Stati Uniti per una Modifica Minore al Piano delle Operazioni Borealis, firmata il 16 ottobre 2025, aprendo l'ultimo passo normativo verso un pieno riavvio della miniera.

La modifica aggiunge 68,3 acri di disturbo (area totale approvata 549,7 acri) e consente lavori di scavo ampliati, sviluppo di nuove strutture per i rifiuti, costruzione di strade e relocazione dell'infrastruttura. Borealis è senza debiti, afferma di essere completamente finanziata, e prevede la mobilitazione dei appaltatori tra dicembre 2025 e gennaio 2026 con attività di trivellazione e brillamento all'inizio di gennaio 2026.

Le operazioni correnti di frantumazione delle scorte e di heap leach proseguono, con lo stabilimento ADR che produce oro e argento per generare entrate a breve termine.

Borealis Mining (OTC: BORMF) obtuvo la aprobación del Servicio Forestal de EE. UU. para una Modificación Menor de su Plan de Operaciones Borealis, firmado el 16 de octubre de 2025, significando un último paso regulatorio hacia un reinicio total de la mina.

La modificación añade 68,3 acres de disturbio (área total aprobada 549,7 acres) y permite ampliar trabajos de mina, desarrollo de nuevas instalaciones de desechos, construcción de carreteras y reubicación de infraestructura. Borealis está libre de deudas, dice estar totalmente financiada, y planea la movilización de contratistas en diciembre de 2025–enero de 2026 con actividades de perforación y voladura a principios de 2026.

Las operaciones continuas de trituración de existencias y de lixiviación en montón siguen, con la planta ADR produciendo oro y plata para generar ingresos a corto plazo.

Borealis Mining (OTC: BORMF) 미국 산림청으로부터 Borealis 운영 계획의 Minor Modification 승인을 받아 2025년 10월 16일 서명된 수정이 최종 규제 단계를 통과하여 광산 재가동으로 이어집니다.

수정 사항은 68.3 에이커의 교란면을 추가하고(허용 총 면적 549.7 에이커), 확장된 구멍 작업, 새로운 폐기물 시설 개발, 도로 건설 및 인프라 재배치를 허용합니다. Borealis는 부채 제로이고 전액 조달 완료이라고 밝히며, 2025년 12월~2026년 1월에 하도급업체 mobilization을 계획하고 2026년 1월 초에 시추 및 폭파 활동을 시작할 예정입니다.

재고 자재의 파쇄 및 더미류 용출 작동은 계속되며, ADR 공장이 금과 은 회수를 통해 단기 수익을 창출합니다.

Borealis Mining (OTC: BORMF) a reçu l'approbation du Service forestier des États-Unis pour une Modification mineure de son Plan d'opérations Borealis, signé le 16 octobre 2025, ouvrant la dernière étape réglementaire vers une remise en service complète de la mine.

La modification ajoute 68,3 acres de perturbation (zone totale approuvée 549,7 acres) et autorise l'extension des travaux de puits, le développement de nouvelles installations de déchets, la construction de routes et la réinstallation des infrastructures. Borealis est à zéro dette, affirme être entièrement financée, et prévoit la mobilisation des entrepreneurs en décembre 2025–janvier 2026 avec des activités de forage et de dynamitage au début de janvier 2026.

Les opérations en cours de broyage des stocks et de lixiviation en tas se poursuivent, avec l'usine ADR produisant de l'or et de l'argent pour générer des revenus à court terme.

Borealis Mining (OTC: BORMF) erhielt die Genehmigung des US Forest Service für eine geringe Änderung (Minor Modification) am Borealis-Betriebsplan, unterzeichnet am 16. Oktober 2025, und ebnet damit einen letzten regulatorischen Schritt zu einem vollständigen Minen-Neustart.

Die Änderung fügt 68,3 Hektar Störung hinzu (insgesamt genehmigte Fläche 549,7 Hektar) und erlaubt erweiterte Abbauarbeiten, die Entwicklung neuer Abfallanlagen, den Straßenbau und die Verlagerung der Infrastruktur. Borealis ist SCHULDENFREI, sagt, es sei voll finanziert, und plant die Mobilisierung von Auftragnehmern im Dezember 2025–Januar 2026 mit Bohr- und Sprengarbeiten Anfang Januar 2026.

Der laufende Betrieb der Lagerstufenzerkleinerung und des Heap-Leach-Verfahrens geht weiter, und das ADR-Werk produziert Gold und Silber, um kurzfristige Umsätze zu erzielen.

Borealis Mining (OTC: BORMF) حصلت على موافقة خدمة الغابات الأمريكية على تعديل minor للخطّة التشغيلية لبوراليس، الموقع في 16 أكتوبر 2025، ويمثل خطوة تنظيمية أخيرة نحو إعادة تشغيل كاملة للمنجم.

الإجراء يضيف 68.3 فداناً من الإضرار (المساحة المعتمدة الإجمالية 549.7 فداناً) ويسمح بتوسيع أعمال الحفر، وتطوير مرافق نفايات جديدة، وبناء طرق، وإعادة توزيع للبنية التحتية. تقول بوراليس إنها خالصة الديون، ومتمول بالكامل، وتخطط تعبئة المقاولين في ديسمبر 2025–يناير 2026 مع أنشطة الحفر والانفجار في مطلع يناير 2026.

تستمر عمليات سحق المخزون وعمليات امتصاص الرواسب في التشكيل، مع وجود مصنع ADR الذي ينتج الذهب والفضة ليحقق إيرادات على المدى القريب.

Borealis Mining (OTC: BORMF) 已获得美国林务局批准对 Borealis 作业计划的 Minor Modification,该修改于 2025 年 10 月 16 日签署,为全面矿山重启铺平了最后一个监管步骤。

该修改新增 68.3 亩扰动面积(总批准区域 549.7 亩),并允许扩展矿坑作业、开发新的废物处理设施、修建道路以及基础设施的重新分配。Borealis 无债务,声称已全额融资,计划于 2025 年 12 月至 2026 年 1 月之间动员承包商,并在 2026 年 1 月初进行钻探与爆破活动

现有的库存碎矿和堆浸作业将继续,ADR 工厂将生产黄金和白银以产生短期收入。

Positive
  • USFS Minor Modification approved (signed Oct 16, 2025)
  • Added 68.3 acres, total project area 549.7 acres
  • Full restart targeted in Q1 2026 with contractor mobilization Dec 2025–Jan 2026
  • Company reported debt-free status and says it is fully financed for restart
  • Active stockpile crushing and leaching producing near-term revenues
Negative
  • New activities contingent on posting updated financial assurance bond per USFS approval

Toronto, Ontario--(Newsfile Corp. - October 21, 2025) - Borealis Mining Company Limited (TSXV: BOGO) (OTC Pink: BORMF) (FSE: L4B0) (the "Company" or "Borealis") is pleased to announce that the U.S. Forest Service (USFS), Bridgeport Ranger District, has approved the Company's Minor Modification to the Borealis Plan of Operations (#02-04-08). The approval marks a significant milestone in the restart of the fully permitted Borealis Gold Mine in Mineral County, Nevada.

The Minor Modification allows for expanded mining activities in the Freedom Flats, Borealis, and Deep Ore/Polaris pits, the development of Waste Rock Facility 9, reconfiguration of existing waste facilities, construction of new haul and light vehicle roads, and relocation of key mine infrastructure including fuel storage, power lines, and process water routing. The modification adds approximately 68.3 acres of new disturbance, bringing the total approved project area to 549.7 acres.

The Company is preparing for a full mine re-start in Q1 of 2026. Borealis anticipates contractor mobilization beginning in December and through to early January, with drill and blast activities beginning in early January. Additional preparatory works include slope angle adjustments on portions of the heap leach pad, hiring of additional personnel, and geotechnical works.

"Receipt of this approval represents the final major regulatory step required to restart operations at Borealis," said Kelly Malcolm, President and CEO of Borealis. "The project is fully permitted, fully financed, and construction-ready. The Company is debt-free, cashed-up, and about to begin generating meaningful revenues for our shareholders. Our team is now shifting focus toward execution - mobilizing equipment, contractors, and personnel to begin pre-production work in preparation for full resumption of mining at Borealis."

Ongoing Stockpile and Leaching Program

The Company's crushing, stacking, and leaching of existing stockpiles is continuing as planned. The ADR plant remains fully operational, with gold and silver recoveries occurring continuously through this pre-restart phase. This active leaching program is designed to generate near-term revenues and ensure a smooth transition to steady-state operations once new mining begins in Q1.

Operational Readiness and Financing

Borealis confirms it is fully financed for the restart through existing working capital and future revenues from its stockpile crushing program.

The USFS approval letter, signed by District Ranger Aaron Coogan on October 16, 2025, emphasizes continued compliance with all environmental protection measures outlined in the 2006 Environmental Assessment and Decision Notice/FONSI, and confirms that new activities may begin upon posting of the updated financial assurance bond.

Borealis Mine

The Borealis mine property, located close to the town of Hawthorne, NV, is fully permitted and equipped for present mine operations and future expansion, with existing open pits, heap leach pads, modern infrastructure, and a functional ADR facility which produces doré bars. The project has historically produced over 600,0001 ounces of gold from an open pit heap leach operation. It is an under-explored property and has not been drilled since 2011, aside from Borealis' efforts in 2024 and 2025. The property possesses high grade expansion potential with excellent historical drilling results, along with a number of untested regional targets. 1Please see the Borealis Mine technical report entitled "NI 43-101 Technical Report, Project Status Report, Borealis Mine, Nevada, U.S.A." authored by Douglas Reid, P.Eng. of SRK Consulting, dated February 16, 2024. The report can be found on SEDAR+ or the Borealis website.

About Borealis

Borealis is a gold mining and exploration company focused on exploration and resumption of production of the Borealis Mine in Nevada and the advancement of its Sandman project also in Nevada. The Borealis Mine is a fully permitted mine site, equipped with active heap leach pads, an ADR facility, and all necessary infrastructure to support a heap leach gold mining operation. In addition to the mine, the property, comprised of 815 unpatented mining claims of approximately 20 acres each totaling approximately 16,300 acres and one unpatented mill site claim of about five acres located in western Nevada, is highly prospective for additional high-sulfidation gold mineralization. The Sandman project, recently acquired through the acquisition of Gold Bull Resources Inc., is an advanced exploration project with a recently completed (2021) NI 43-101 compliant resource and a recent (2023) Preliminary Economic Assessment which indicates compelling economics, particularly in light of the increase in commodity prices since publication of the study. Borealis is led by a strong board and management team, many of whom have founded, managed, and sold highly successful mining and exploration companies.

For further information, please contact:

Kelly Malcolm
President and Chief Executive Officer
info@BorealisMining.com
Office: (289) 371-3371

This news release may contain certain "forward-looking information" within the meaning of applicable securities law. Forward-looking information is frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "may", "will", "would", "potential", "proposed" and other similar words, or statements that certain events or conditions "may" or "will" occur. These statements are only predictions. Forward-looking information is based on the opinions and estimates of management at the date the information is provided, and is subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking information. For a description of the risks and uncertainties facing the Company and its business and affairs, readers should refer to the Company's Management's Discussion and Analysis. The Company undertakes no obligation to update forward-looking information if circumstances or management's estimates or opinions should change, unless required by law. The reader is cautioned not to place undue reliance on forward-looking information.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/271121

FAQ

When did Borealis Mining (BORMF) receive USFS approval to modify the Borealis Plan of Operations?

The USFS approval letter was signed on October 16, 2025 and allows the Minor Modification to proceed.

What does the USFS permit change mean for Borealis Mining (BORMF) operations and acreage?

The modification adds 68.3 acres of new disturbance, increasing the total approved project area to 549.7 acres and permits expanded pit and infrastructure work.

When is Borealis Mining (BORMF) planning to restart the Borealis mine?

Borealis is preparing for a full restart in Q1 2026, with contractor mobilization starting December 2025 and drill and blast in early January 2026.

Is Borealis Mining (BORMF) financed for the mine restart?

The company states it is fully financed for the restart, is debt-free, and expects additional revenue from ongoing stockpile leaching.

Will Borealis Mining (BORMF) generate revenue before full restart?

Yes. The company is crushing, stacking, and leaching existing stockpiles and operating an ADR plant to produce continuous gold and silver recoveries for near-term revenue.

Are there any conditions before Borealis Mining (BORMF) can begin new activities under the USFS approval?

Yes. The USFS letter requires posting the updated financial assurance bond before new activities may begin.