Bitdeer Announces September 2026 Production and Operations Update
AI Cloud backlog reached $2.9 billion as A201 commitments added more than $1.7 billion in expected five-year revenue.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Rhea-AI Summary
Bitdeer (NASDAQ: BTDR) reported September Bitcoin production of 1,355, up 200% year over year, alongside expanded AI Cloud commitments. AI Cloud revenue backlog reached $2.9 billion, versus $0.9 billion in August. Offtake commitments cover over 70% of its approximately 21.7MW A201 facility, with more than $1.7 billion in expected revenue over five years; full deployment and go-live are targeted for April 2027.
Malaysia capacity agreements secure 67MW at A901 and 60MW at A103, with delivery planned for Q2 2027 and Q1 2028, respectively. The AI Cloud pipeline totals 333.5MW. A 16-year Tydal lease with Volta represents approximately $4.7 billion in base-term contract value. Bitdeer also acquired 200 acres near Rockdale for AI infrastructure development. GPU utilization rose to 95% from 92% in August, while annualized revenue run-rate remained approximately $86 million. Self-mining computing capacity reached 82.3 EH/s; Bitcoin holdings fell to 47 from 61 in August.
How this balance works
Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.
It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.
Rhea-AI Sentiment measures something else, the tone of the wording.
Hollow bars mark forward-looking points. How the balance works
Positive
- Major point. Forward-looking: it has not happened yet and may not happen.A201 commitments cover over 70% of approximately 21.7MW, generating over $1.7 billion in expected five-year revenue. 81% of market cap
- Major pointTydal lease with Volta carries approximately $4.7 billion in contract value over its 16-year base term. 2.2× market cap
- Moderate pointBitcoin production rose 200% year over year to 1,355 in September, versus 1,310 in August.
- Moderate pointAI Cloud revenue backlog reached $2.9 billion in September, versus $0.9 billion in August.
- Moderate point. Forward-looking: it has not happened yet and may not happen.A901 capacity agreement secures 67MW in Malaysia, with full delivery planned for Q2 2027.
- Moderate point. Forward-looking: it has not happened yet and may not happen.A103 capacity agreement secures 60MW in Malaysia, with delivery planned for Q1 2028.
- Moderate pointGPU utilization increased to 95% in September from 92% in August.
- Moderate pointSelf-mining computing capacity rose to 82.3 EH/s from 79.9 in August and 35.0 a year earlier.
- Moderate pointCo-mining computing capacity rose to 28.7 EH/s in September from 21.6 EH/s in August.
- Moderate point. Forward-looking: it has not happened yet and may not happen.A102 has 100% signed cloud contracts for 9.5MW, with data center readiness scheduled for Q1 2027.
- Moderate point. Forward-looking: it has not happened yet and may not happen.A202 has a signed data center contract for 65.1MW, with readiness scheduled for Q3 2027.
6 minor points
- Minor point200 acres acquired near the existing 563MW Rockdale facility support planned AI infrastructure development.
- Minor pointExternally subscribed GPUs increased to 4,007 in September from 3,998 in August.
- Minor point. Forward-looking: it has not happened yet and may not happen.A201 deployment and go-live are targeted for April 2027; over 100 GB300 NVL72 racks were procured.
- Minor point. Forward-looking: it has not happened yet and may not happen.A401 in Norway adds a planned 42.7MW, with data center readiness scheduled for the second half of 2027.
- Minor point. Forward-looking: it has not happened yet and may not happen.A501 in Washington adds a planned 10MW, with data center readiness scheduled for December 2027.
- Minor point. Forward-looking: it has not happened yet and may not happen.A601 in Tennessee adds a planned 55MW, with data center readiness scheduled for October 2027.
Negative
- Moderate pointBitcoin holdings fell to 47 in September from 61 in August and 2,029 a year earlier.
- Minor point. Forward-looking: it has not happened yet and may not happen.Tydal's approximately $8.0 billion potential contract value depends on the tenant exercising a one-time eight-year extension.
- Minor pointOther proprietary computing capacity declined to 4.1 EH/s in September from 4.2 EH/s in August.
Details
Market move: BTDR +7.28% vs previous close. September 2026 production update
On Oct 19, the day this news came out, the latest delayed price for BTDR is 7.28% above the previous close. Our momentum scanner has recorded 27 alerts for this stock so far that day. The latest delayed price is $8.25.
Data tracked by StockTitan Argus (15 min delayed). Upgrade to Gold for real-time data.
Key Figures
- A201 commitments
- More than 70%
- Share of the Malaysia facility covered by offtake commitments
- A201 expected revenue
- >$1.7 billion
- Over 5 years
- AI Cloud revenue backlog
- ~$2.9 billion
- Reported September 2026
- BTC mined
- 1,355 Bitcoins
- September 2026
- BTC production change
- 200% Y/Y increase
- September 2026
- Tydal lease contract value
- Approximately $4.7 billion
- 16-year initial base term
- Tydal lease extension value
- Approximately $8.0 billion total contract value
- If the tenant exercises its one-time 8-year extension
- GPU utilization rate
- 95%
- September 2026; 92% in August 2026
Previous Crypto Reports
-
BTC production rose to 1,310, alongside AI cloud growth and a new long-term data-center lease.
-
Reported 1,190 BTC mined, up 322% year over year, plus AI infrastructure contracts.
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Key Terms
offtake commitments financial
pue technical
arr financial
hash rate technical
AI-generated analysis. How Rhea-AI works. Not financial advice.
Monthly Highlights
- AI Cloud:
- Capacity Expansion in Malaysia: Bitdeer AI recently announced data services agreements securing 67MW of capacity at A901 data center with full delivery planned for Q2 2027 and an additional 60MW of capacity at A103 data center with delivery planned for Q1 2028.
- Contracting of A201 Facility in Malaysia: Bitdeer AI announced offtake commitments covering more than
70% of our ~21.7MW A201 data center in Johor Bahru, generating >$1.7 billion in expected revenue over 5 years and boosting total AI Cloud revenue backlog to ~$2.9 billion .
- Colocation: Bitdeer recently acquired 200 acres near existing 563 MW Rockdale facility to support AI/HPC infrastructure development.
- Bitcoin: Production increased
200% Y/Y to 1,355 Bitcoins.
| Key Metrics Summary | ||||||||
| AI Cloud Pipeline (IT MW) | AI Cloud Revenue Backlog | AI Cloud ARR1 | Colocation AI Data Center | Self-Mining Hash Rate2 | Co-Mining Hash Rate3 | BTC Mined | ||
| 333.5 MW | ~ | ~ | at Tydal, Norway | 82.3 (EH/s) | 28.7 (EH/s) | 1,355 | ||
SINGAPORE, Oct. 19, 2026 (GLOBE NEWSWIRE) -- Bitdeer Technologies Group (NASDAQ: BTDR) (“Bitdeer” or the “Company”), a world-leading technology company for AI neocloud services and Bitcoin mining infrastructure, today announced its unaudited operations updates for September 2026.
Management Commentary
“September demonstrated our ability to convert owned power into contracted AI Cloud revenue. Offtake commitments covering more than
Bitdeer AI Update:
Colocation AI Data Center:
- Bitdeer recently acquired 200 acres near existing 563 MW Rockdale facility to support AI/HPC infrastructure development. Outright ownership provides the long-term site control required to develop and finance AI/HPC data center infrastructure. Bitdeer believes its Rockdale site, with its existing large-load interconnection and established transmission infrastructure, is well positioned to receive additional power allocations over the coming years.
- Bitdeer announced a 16-Year AI/HPC Data Center Lease for its Tydal, Norway Campus, representing approximately
$4.7 billion of total contract value over the initial base term, with the potential to reach a total contract value of approximately$8.0 billion if the tenant exercises its one-time 8-year lease extension. - Tydal, Norway AI Data Center expected to be among Norway's largest and most efficient AI data centers upon completion. With a PUE of approximately 1.1 and running on
100% renewable energy, it sets a compelling standard for data center performance, at scale.
AI Cloud Key Metrics: (as of 9/30/2026):
| Metric | September 2026 | August 2026 |
| GPU Amount Deployed | 4,328 | 4,328 |
| GPU Types | H100, H200, B200, B300, GB200, GB300 | H100, H200, B200, B300, GB200, GB300 |
| Utilization Rate8 | ||
| GPUs Under External Subscription | 4,007 | 3,998 |
| ARR1 | ~ | ~ |
| Revenue Backlog |
AI Cloud Pipeline Update:
| Data Center | Location | IT Load (MW) | GPU Platform | DC RFS | Cloud Contract Status | Long Term Contract Coverage, % | DC Contract |
| A101 | Malaysia | 2.5 | GB200 and GB300 | Live | Live | Signed | |
| A102 | Malaysia | 9.5 | GB300 | Q1 2027 | Signed | ||
| A103 | Malaysia | 60 | Vera Rubin | Q1 2028 | Signed | ||
| A201 | Malaysia | 21.7 | GB300 and Vera Rubin | Jan 2027 | Over | Over | Signed |
| A202 | Malaysia | 65.1 | GB300 and/or Vera Rubin | Q3 2027 | Signed | ||
| A401 | Norway | 42.7 | Vera Rubin | 2H 2027 | Self-Owned | ||
| A501 | WA, USA | 10 | Vera Rubin | Dec 2027 | Self-Owned | ||
| A601 | TN, USA | 55 | Vera Rubin | Oct 2027 | Self-Owned | ||
| A901 | Malaysia | 67 | GB300 | Q2 2027 | Signed | ||
| Total | 333.5 | ||||||
- Capacity Expansion in Malaysia: Bitdeer AI recently announced data services agreements securing 67MW of capacity at A901 data center with full delivery planned for Q2 2027 and an additional 60MW of capacity at A103 data center with delivery planned for Q1 2028.
- Contracting of A201 Facility in Malaysia: Bitdeer AI announced offtake commitments covering more than
70% of our ~21.7MW A201 data center in Johor Bahru, generating >$1.7 billion in expected revenue over 5 years and boosting total AI Cloud revenue backlog to ~$2.9 billion . The liquid-cooled facility supports NVIDIA GB300 NVL72 systems and next-generation Vera Rubin architectures. Over 100 GB300 NVL72 racks were procured ahead of energization, with full deployment and go-live targeted for April 2027. - NVIDIA Collaboration on Agent Safety: Bitdeer AI announced collaboration with NVIDIA on the NVIDIA Open Agent Safety Platform, which combines NVIDIA OpenShell software controls and the NVIDIA Sentry reference system design. The collaboration focuses on infrastructure-level policy enforcement, sandboxing and auditability for enterprise AI agents. We plan to integrate NVIDIA’s AI safety technology stack to strengthen software- and hardware-based protection for production-grade agentic workflows.
- Industry Engagement: Bitdeer AI enhanced its global market presence by sponsoring AI Infra Summit 2026 (Santa Clara), serving as Gold Sponsor at Tech Week Singapore, and participating in the World AI Show Malaysia. To foster ecosystem adoption and showcase its full-stack AI cloud capabilities, the team also took part in the NVIDIA Inception Grand Challenge and hosted two hands-on community workshops.
Crypto Mining Update:
CRYPTO Mining, R&D, Manufacturing:
- Mined 1,355 Bitcoins4, an increase of
200% Y/Y; we continue to expect momentum in our mining results over the coming months. - Self-mining hash rate reached ~82.3 EH/s.
- Co-mining hashrate of 28.7 EH/s driven by Co-Mining collaboration, using Bitdeer’s mining rigs operated by 3rd party datacenters.
Key Crypto Metrics:
| Metric | September 2026 | August 2026 | September 2025 |
| Hash Rate Metrics: | |||
| Self-Mining (Operated in self-owned datacenters) | 82.3 | 79.9 | 35.0 |
| Other Proprietary Hash Rate5 | 4.1 | 4.2 | - |
| Total Proprietary Hash Rate6 (EH/s) | 86.4 | 84.1 | 35.0 |
| Co-Mining (Operated by 3rd party datacenters) | 28.7 | 21.6 | - |
| BTC Mined4 | 1,355 | 1,310 | 452 |
| BTC Held7 | 47 | 61 | 2,029 |
Infrastructure Summary:
Bitdeer will transition its infrastructure updates from a monthly reporting cadence to quarterly disclosures issued concurrently with its financial earnings releases, providing a more meaningful and integrated perspective on the Company’s development progress. The Company's most recent infrastructure update was disclosed alongside its Q2 2026 financial results on August 10, 2026.
Footnotes
1 ARR as of the last day of the respective month is calculated by multiplying the daily revenue generated from all contractually obligated GPU orders on that specific day by 365. This metric provides an annualized view of the revenue run-rate based on active contracts at the end of the reporting period.
2 Self-Mining (Operated in self-owned datacenters) refers to cryptocurrency mining for Bitdeer’s own account, whereby its mining rigs are operated in self-owned datacenters.
3 Co-mining (Operated by 3rd party datacenters) refers to cryptocurrency mining for Bitdeer’s own account, whereby its mining rigs are operated by third-party datacenters.
4 Includes BTC from self-mining operations and BTC from co-mining operations.
5 Other Proprietary Hash Rate includes the hashrate from Bitdeer’s cloud hashrate business, mining rigs delivered in the crypto mining datacenters but not deployed and the mining rigs temporarily offline due to limited economic benefit.
6 Total Proprietary Hash Rate as of September 30, 2026 includes Self-Mining Hash Rate and Other Proprietary Hash Rate.
7 Bitcoins held does not include Bitcoins from customer deposits but does include Bitcoins that are pledged as collateral by us.
8 Utilization Rate as of the last day of the respective month is calculated as the total number of GPUs under internal and external orders divided by the total number of deployed GPUs.
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company for AI neocloud services and Bitcoin mining infrastructure. Bitdeer is committed to providing comprehensive Bitcoin mining solutions for its customers and building AI computational infrastructure to support the AI revolution. Bitdeer handles complex processes involved in computing such as equipment procurement, transport logistics, data center design and construction, equipment management, and daily operations. Bitdeer also offers advanced cloud capabilities to customers with high demand for artificial intelligence. Headquartered in Singapore, Bitdeer has deployed data centers across multiple countries, including the United States, Norway, Bhutan, Ethiopia, and Malaysia. To learn more, visit https://ir.bitdeer.com/ or follow Bitdeer on X@Bitdeer and LinkedIn @Bitdeer.
Investors and others should note that Bitdeer may announce material information using its website and/or on its accounts on social media platforms, including X, formerly known as Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages investors and others to review the information it posts on social media and other communication channels listed on its website.
Forward-Looking Statements
Statements in this press release about future expectations, plans, and prospects, as well as any other statements regarding matters that are not historical facts, may constitute “forward-looking statements” within the meaning of The Private Securities Litigation Reform Act of 1995. The words “anticipate,” “look forward to,” “believe,” “continue,” “could,” “estimate,” “expect,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “should,” “target,” “will,” “would” and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain these identifying words. Forward-looking statements in this press release include, among others, statements regarding: the expected DC RFS dates and the expected IT capacity of each data center identified above, and the aggregate AI Cloud capacity figures presented in this press release; the GPU platforms expected to be deployed at each facility and the availability and timing of delivery of that equipment; the off-take commitments covering more than
For investor and media inquiries, please contact:
Investor Relations
Tesh Dahya, Head of Investor Relations
tesh.dahya@bitdeer.com
Media
Eunice Hwangbo, Director, Corporate Communications
eunice.hwangbo@bitdeer.com
FAQ
AI-generated questions and answers. How Rhea-AI works. Not financial advice.
How much Bitcoin did Bitdeer mine in September 2026?
Bitdeer mined 1,355 Bitcoins in September 2026, an increase of 200% year over year. Production includes both self-mining operations in company-owned data centers and co-mining operations using Bitdeer rigs operated by third-party data centers.
How much revenue does Bitdeer expect from its A201 AI data center commitments?
Bitdeer expects more than $1.7 billion over five years from offtake commitments covering more than 70% of its approximately 21.7MW A201 facility in Johor Bahru. Full deployment and go-live are targeted for April 2027.
How does Bitdeer calculate AI Cloud annualized revenue run-rate?
Bitdeer calculates annualized revenue run-rate by multiplying daily revenue from all contractually obligated GPU orders on the month's final day by 365. This measures the annualized pace of revenue from active contracts at that date, rather than revenue earned over a full year.
How will Bitdeer report infrastructure development updates going forward?
Bitdeer will replace monthly infrastructure updates with quarterly disclosures alongside financial earnings releases. Its most recent infrastructure update accompanied its Q2 2026 financial results on August 10, 2026.