STOCK TITAN

B2Gold Provides an Update on Goose Mine Commissioning, Confirms Consolidated 2025 Production Guidance Range, and Provides Operational Updates for the Fekola, Masbate, and Otjikoto Mines

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

B2Gold (NYSE AMERICAN: BTG) has provided comprehensive operational updates across its mining portfolio and confirmed its 2025 consolidated gold production guidance of 970,000 to 1,075,000 ounces. The company's new Goose Mine achieved first gold pour on June 30, 2025, and is nearing commercial production, though with revised 2025 guidance of 80,000-110,000 ounces due to crushing plant capacity issues.

The Fekola Complex maintains its 2025 guidance of 515,000-550,000 ounces, with underground operations now commenced. The Otjikoto Mine guidance has been increased to 185,000-205,000 ounces, and the company approved development of the Antelope underground deposit. The Masbate Mine guidance has been raised to 190,000-210,000 ounces due to strong mill throughput performance.

B2Gold (NYSE AMERICAN: BTG) ha fornito aggiornamenti operativi completi su tutto il proprio portafoglio di miniere e ha confermato la guida consolidata per la produzione di oro nel 2025 tra 970.000-1.075.000 once. La nuova Goose Mine ha ottenuto la prima fusione d'oro il 30 giugno 2025 ed è vicina alla produzione commerciale, sebbene con una guida 2025 rivista a 80.000-110.000 once a causa di problemi di capacità dell’impianto di frantumazione.

Il Fekola Complex mantiene la guida 2025 di 515.000-550.000 once, con operazioni sotterranee ora avviate. La guida della Otjikoto Mine è stata aumentata a 185.000-205.000 once, e la società ha approvato lo sviluppo del giacimento sotterraneo Antelope. La guida della Masbate Mine è stata innalzata a 190.000-210.000 once grazie alle robuste prestazioni del throughput della centrale di trattamento.

B2Gold (NYSE AMERICAN: BTG) ha proporcionado actualizaciones operativas integrales sobre su cartera minera y confirmó su guía de producción de oro consolidada para 2025 de 970,000 a 1,075,000 onzas. La nueva Goose Mine logró el primer vertido de oro el 30 de junio de 2025 y se encuentra cerca de la producción comercial, aunque con una guía 2025 revisada de 80,000-110,000 onzas debido a problemas de capacidad de la planta de trituración.

El Fekola Complex mantiene su guía para 2025 de 515,000-550,000 onzas, con operaciones subterráneas ya iniciadas. La guía de la Otjikoto Mine se ha incrementado a 185,000-205,000 onzas, y la compañía aprobó el desarrollo del yacimiento subterráneo Antelope. La guía de la Masbate Mine se ha elevado a 190,000-210,000 onzas gracias al fuerte rendimiento del molino de tratamiento.

B2Gold (NYSE AMERICAN: BTG)은 광산 포트폴리오 전반에 걸친 포괄적인 운영 업데이트를 제공했으며 2025년 합산 금 생산 가이던스를 970,000~1,075,000온스로 확인했습니다. 새로운 Goose Mine은 2025년 6월 30일에 첫 금 주조를 달성했고 상업 생산에 근접하고 있지만, 파쇄 시설 용량 문제로 2025년 가이던스가 80,000-110,000온스로 조정되었습니다.

또한 Fekola Complex은 2025년 가이던스를 515,000-550,000온스로 유지하며 지하 작업이 이제 시작되었습니다. Otjikoto Mine의 가이던스는 185,000-205,000온스로 상향되었고, 회사는 지하 매장 Antelope의 개발을 승인했습니다. Masbate Mine의 가이던스는 강력한 제선량 처리 성과로 190,000-210,000온스로 올랐습니다.

B2Gold (NYSE AMERICAN: BTG) a fourni des mises à jour opérationnelles complètes sur l’ensemble de son portefeuille minier et a confirmé ses prévisions consolidées de production d’or pour 2025 entre 970 000 et 1 075 000 onces. La nouvelle Goose Mine a connu sa première coulée d’or le 30 juin 2025 et se rapproche de la production commerciale, bien que les prévisions 2025 aient été révisées à 80 000-110 000 onces en raison de problèmes de capacité de l’usine de concassage.

Le Fekola Complex maintient sa prévision 2025 de 515 000-550 000 onces, les opérations souterraines ayant désormais commencé. La prévision de la Otjikoto Mine est portée à 185 000-205 000 onces, et la société a approuvé le développement du dépôt souterrain Antelope. La prévision de la Masbate Mine est relevée à 190 000-210 000 onces grâce à de solides performances du moulin de traitement.

B2Gold (NYSE AMERICAN: BTG) hat umfassende Betriebsaktualisierungen über sein Bergbauportfolio bereitgestellt und bestätigt seine konsolidierte Goldproduktionsprognose für 2025 von 970.000 bis 1.075.000 Unzen. Die neue Goose Mine hat am 30. Juni 2025 die erste Goldschmelze erreicht und nähert sich der kommerziellen Produktion, jedoch mit einer überarbeiteten 2025-Prognose von 80.000-110.000 Unzen aufgrund von Kapazitätsproblemen der Zerkleinerungsanlage.

Der Fekola Complex hält seine 2025-Prognose von 515.000-550.000 Unzen bei, wobei die Untertagestellen nun begonnen wurden. Die Prognose für die Otjikoto Mine wurde auf 185.000-205.000 Unzen erhöht, und das Unternehmen genehmigte die Entwicklung des Untertagevorkommens Antelope. Die Prognose für die Masbate Mine wurde aufgrund einer starken Durchsatzleistung der Aufbereitungsanlage auf 190.000-210.000 Unzen angehoben.

B2Gold (NYSE AMERICAN: BTG) قدمت تحديثات تشغيلية شاملة عبر محفظة مناجمها وأكدت توجيه إنتاج الذهب الموحَّد لعام 2025 بواقع 970,000 إلى 1,075,000 أونصة. حققت منجم Goose الجديد أول صب ذهب في 30 يونيو 2025، وهو يقترب من الإنتاج التجاري، بالرغم من أن التوجيه لعام 2025 أُعيد حتّى إلى 80,000-110,000 أونصة بسبب مشاكل في قدرة مصنع التكسير.

يحافظ مجمع Fekola على توجيه 2025 بواقع 515,000-550,000 أونصة، مع بدء العمليات تحت الأرض الآن. تم رفع توجيه منجم Otjikoto إلى 185,000-205,000 أونصة، ووافقت الشركة على تطوير ترسب Antelope تحت الأرض. تمت زيادة توجيه منجم Masbate إلى 190,000-210,000 أونصة بسبب أداء الطحن القوي.

B2Gold (NYSE AMERICAN: BTG) 已对其矿业组合提供了全面的运营更新,并确认其2025年合并金产量指南为970,000到1,075,000盎司。新成立的Goose Mine于2025年6月30日实现了首铸金,接近商业化生产,尽管因碎矿厂产能问题,2025年的指导下调至80,000-110,000盎司

Fekola Complex维持其2025年指南为515,000-550,000盎司,地下作业现已启动。Otjikoto Mine的产量指引上调至185,000-205,000盎司,公司批准开发地下矿床AntelopeMasbate Mine的产量指引上调至190,000-210,000盎司,原因是选矿厂产量表现强劲。

Positive
  • Goose Mine achieved first gold pour and is operating at 75% of design capacity, above targeted 65% commercial production rate
  • Fekola underground mining commenced with positive grade reconciliations
  • Otjikoto Mine guidance increased by 20,000 ounces due to better-than-expected performance
  • Masbate Mine guidance increased by 20,000 ounces due to strong mill throughput
  • Antelope underground project capital cost reduced from $129M to $105M
  • Fekola Regional expected to produce 180,000 ounces annually from 2026-2030
Negative
  • Goose Mine 2025 production guidance reduced by 40,000 ounces due to crushing plant capacity shortfall
  • Fekola Regional exploitation permit delayed, with no gold production expected in 2025
  • Otjikoto open pit mining activities scheduled to conclude in near-term

Insights

B2Gold maintains overall production guidance despite Goose Mine delays, with other mines outperforming expectations and positive development decisions.

B2Gold's operational update reveals a mixed picture across its mining portfolio, though the overall consolidated guidance of 970,000-1,075,000 ounces for 2025 remains unchanged. The newly commissioned Goose Mine in Canada faces early challenges, with production guidance reduced to 80,000-110,000 ounces (down from 120,000-150,000) due to crushing plant capacity limitations. However, the company is implementing mobile crushing solutions that should enable the mill to reach its 4,000 tpd design capacity while permanent optimizations are completed. Despite this setback, Goose is still expected to deliver approximately 70,000 ounces in Q4 2025, and long-term production projections remain intact at 250,000 ounces in 2026 and 330,000 ounces in 2027.

Offsetting the Goose Mine's reduced guidance, both the Otjikoto Mine in Namibia and Masbate Mine in the Philippines are outperforming expectations, leading to increased production guidance at both operations. Otjikoto's 2025 forecast has been raised to 185,000-205,000 ounces (from 165,000-185,000), while Masbate's guidance increases to 190,000-210,000 ounces (from 170,000-190,000). The Fekola Complex in Mali continues to perform strongly, with production tracking ahead of budget and maintaining its guidance of 515,000-550,000 ounces for 2025.

A significant positive development is the approval of the Antelope underground project at Otjikoto, with reduced pre-production capital costs of $105 million (down from $129 million). This project has the potential to sustain Otjikoto's annual production at approximately 110,000 ounces over the life of the underground mine. Additionally, the underground operations at Fekola have commenced following regulatory approval, with initial gold grade reconciliations exceeding resource model estimates.

VANCOUVER, British Columbia, Sept. 15, 2025 (GLOBE NEWSWIRE) -- B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX: B2G) (“B2Gold” or the “Company”) is announcing an update on operational performance year-to-date in 2025 at each of its four mines. B2Gold confirms 2025 total annual gold production of between 970,000 and 1,075,000 ounces.

Goose Mine - Canada

The Goose Mine achieved first gold pour on June 30, 2025

The mine remains on track for commercial production in the coming weeks, and estimates strong gold production in Q4 2025

Project commissioning activities are nearing completion at the Goose Mine. Since first gold production in late June 2025, the Goose mill is achieving consistent performance and daily throughput is increasing. Current daily throughput is approximately 75% of the 4,000 tonnes per day (“tpd”) design capacity (above the Company’s targeted average commercial production rate of 65% of the design capacity) and will increase to full design capacity in the near term as described below.

B2Gold anticipates achieving commercial production at the Goose Mine in the coming weeks. The Goose Mine is currently operating, and plans to achieve commercial production, with the use of supplemental mobile crushing capacity to ensure a consistent feed of crushed ore to the mill, as crushing plant capacity has been limited during the third quarter of 2025. B2Gold believes that with this supplemental mobile crushing capacity the Goose mill can operate at design capacity of 4,000 tpd following the throughput ramp-up. Permanent optimizations to the primary crushing and secondary grinding circuits and the installation of surge bin capacity have been engineered, designed, and are being implemented. Use of the mobile crusher is expected to allow the mill to run at design throughput while these modifications are implemented.

Due to the crushing plant capacity shortfall in the third quarter of 2025, B2Gold is modifying its 2025 gold production guidance for the Goose Mine to 80,000 to 110,000 ounces (original guidance range of 120,000 to 150,000 ounces). B2Gold anticipates gold production in the fourth quarter of 2025 to be in line with original estimates of approximately 70,000 ounces. The Company reiterates the near-term and long-term gold production estimates at the Goose Mine, which included gold production forecasts of approximately 250,000 ounces of gold production in 2026, approximately 330,000 ounces of gold production in 2027, and average annual gold production for the initial full six years of operations (2026 to 2031 inclusive) of approximately 300,000 ounces per year, based only on existing Mineral Reserves.

In addition, work continues on the multiple optimization studies for the Goose Mine as previously announced in March 2025, including the evaluation of a flotation / concentrate leach process and the potential installation of a SAG mill to be paired in conjunction with the existing 4,000 tpd ball mill, which could expand mill throughput capacity up to 6,000 tpd. The results of these studies are expected to be finalized in late 2025, and will also reflect two additional value drivers for the Goose Mine related to the potential reduction in carbon taxes paid over the life of the mine, and a reduction in the annual amount of fuel consumed as a result of equipment optimizations.

Fekola Complex - Mali

Fekola has continued the strong operational performance exhibited in the first half of the year into the third quarter of 2025. As of early September 2025, Fekola Complex gold production remains ahead of budgeted levels year-to-date. On July 30, 2025, the State of Mali granted approval for the Company to commence underground operations, including stope ore production, at the Fekola Mine. Subsequent to receipt of the underground mining approval, the Company commenced stope ore production at Fekola underground, and Fekola underground ore is currently being processed through the Fekola mill. Initial underground gold grade reconciliations have been positive compared to the resource model.

The Company continues to expect to receive the Fekola Regional exploitation permit by the end of the third quarter of 2025. Upon receipt of the exploitation permit for Fekola Regional, mining pre-stripping activities will commence immediately for a period of three months, followed by initial gold production expected to commence in early 2026. Importantly, the haul road from Fekola Regional to the Fekola Mine is operational as construction of the haul roads and mining infrastructure (warehouse, workshop, fuel depot and offices) was completed on schedule in 2023. Fekola Regional gold production is expected to begin in early 2026 and will ramp up to average approximately 180,000 ounces per year over its first five years of production from 2026 through 2030, with a mine life expected to extend well into the 2030’s.

B2Gold reiterates its 2025 gold production guidance for the Fekola Complex of 515,000 to 550,000 ounces. The Company is modifying the components of how the Fekola Complex gold production guidance will be achieved to optimize the production profile. Based on the timing of the Fekola Regional exploitation permit by end of the third quarter of 2025, no gold production from Fekola Regional is anticipated in 2025. Fekola underground performance has exceeded expectations since receipt of the underground mining approval in late July 2025, and is now anticipated to contribute between 30,000 and 40,000 ounces of gold production this year (original guidance range of 25,000 to 35,000 ounces). Mining activities at the Fekola and Cardinal open pits are anticipated to contribute between 485,000 and 510,000 ounces of gold production in 2025 (original guidance range of 470,000 to 490,000 ounces).

Otjikoto Mine - Namibia

The Otjikoto Mine has continued to outperform expectations into the third quarter of 2025. As previously disclosed, open pit mining activities at Otjikoto are scheduled to conclude in the near-term. During mining of the final phases of the Otjikoto pit, ore tonnes and average gold grade mined have exceeded expectations providing more robust ore stockpiles than previously anticipated.

Due to the positive ore tonne and grade reconciliations described above, the Company is increasing its 2025 gold production guidance for the Otjikoto Mine to 185,000 to 205,000 ounces (original guidance range of 165,000 to 185,000 ounces).

B2Gold is pleased to announce it has approved a development decision on the Antelope underground deposit at the Otjikoto Mine. Subsequent to the release of the Preliminary Economic Assessment results for the Antelope deposit on February 4, 2025, the Company has completed further optimization work on a small-scale, low-cost, underground gold mine at Antelope, and believe that the estimated pre-production capital cost can be reduced from $129 million to $105 million. The majority of pre-production capital is estimated to be spent in 2026 and 2027, with production from Antelope having the potential to increase Otjikoto Mine gold production to approximately 110,000 ounces per year over the life of the Antelope underground mine.

Masbate Mine – The Philippines

The Masbate Mine has also outperformed expectations in the third quarter of 2025, a continuation of the outperformance experienced in the first half of 2025. At the beginning of 2025, Masbate was projected to process 8.0 million tonnes of ore at an average grade of 0.88 grams per tonne gold with a process gold recovery of 79.9%. Throughout the first half of 2025, mill throughput exceeded expectations while mill feed grade and gold recoveries have been in line with expectations.

Based on the strong mill throughput rates experienced in the first half of 2025 that are expected to continue into the second half of the year, B2Gold is increasing its 2025 gold production guidance for the Masbate Mine to 190,000 to 210,000 ounces (original guidance range of 170,000 to 190,000 ounces).

About B2Gold Corp.

B2Gold is a responsible international senior gold producer headquartered in Vancouver, Canada. Founded in 2007, today, B2Gold has operating gold mines in Canada, Mali, Namibia and the Philippines, and numerous development and exploration projects in various countries. B2Gold forecasts gold production of between 970,000 and 1,075,000 ounces in 2025.

Qualified Persons

Bill Lytle, Senior Vice President and Chief Operating Officer, a qualified person under NI 43-101, has approved the scientific and technical information related to operations matters contained in this news release.

ON BEHALF OF B2GOLD CORP.
“Clive T. Johnson”
President & Chief Executive Officer

The Toronto Stock Exchange and NYSE American LLC neither approve nor disapprove the information contained in this news release.

Production guidance presented in this news release reflect total production at the mines B2Gold operates on a 100% project basis. Please see our Annual Information Form dated March 28, 2025, for a discussion of our ownership interest in the mines B2Gold operates.

This news release includes certain "forward-looking information" and "forward-looking statements" ("collectively forward-looking statements") within the meaning of applicable Canadian and United States securities legislation, including: projections; outlook; guidance; forecasts; estimates; and other statements regarding future or estimated financial and operational performance, gold production and sales, revenues and cash flows, and capital costs (sustaining and non-sustaining) and operating costs, including projected cash operating costs and AISC, and budgets on a consolidated and mine by mine basis; future or estimated mine life, metal price assumptions, ore grades or sources, gold recovery rates, stripping ratios, throughput, ore processing; statements regarding anticipated exploration, drilling, development, construction, permitting and other activities or achievements of B2Gold; and including, without limitation: total consolidated gold production of between 970,000 and 1,075,000 ounces in 2025; the Goose Mine achieving commercial production in the next few weeks, and achieving strong production in Q4 2025; the Goose mill being able to operate at 4,000 tpd throughput; 2025 gold production at the Goose Mine of 80,000 to 110,000 ounces; Q4 2025 gold production at the Goose Mine of 70,000 ounces; 2026 gold production at the Goose Mine of approximately 250,000 ounces; 2027 gold production at the Goose Mine of approximately 330,000 ounces; average annual gold production of approximately 300,000 ounces from 2026 to 2031 at the Goose Mine; receiving the Fekola Regional exploitation permit in Q3 2025; initial gold production from Fekola Regional in early 2026; average annual gold production of approximately 180,000 ounces from 2026 through 2030 at Fekola Regional; the mine life of Fekola Regional extending well into the 2030’s; 2025 gold production at the Fekola Complex of 515,000 to 550,000 ounces; Fekola underground gold production of 30,000 to 40,000 ounces in 2025; Open pit gold production at Fekola and Cardinal of 485,000 to 510,000 ounces in 2025; 2025 gold production at the Otjikoto Mine of 185,000 to 205,000 ounces; pre-production capital cost of $105 million to develop the Antelope deposit; the Otjikoto Mine producing approximately 110,000 ounces of gold per year over the life of the Antelope underground mine; 2025 gold production at the Masbate Mine of 190,000 to 210,000 ounces. All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as "expect", "plan", "anticipate", "project", "target", "potential", "schedule", "forecast", "budget", "estimate", "intend" or "believe" and similar expressions or their negative connotations, or that events or conditions "will", "would", "may", "could", "should" or "might" occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made.

Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond B2Gold's control, including risks associated with or related to: the volatility of metal prices and B2Gold's common shares; changes in tax laws; the dangers inherent in exploration, development and mining activities; the uncertainty of reserve and resource estimates; not achieving production, cost or other estimates; actual production, development plans and costs differing materially from the estimates in B2Gold's feasibility and other studies; the ability to obtain and maintain any necessary permits, consents or authorizations required for mining activities; environmental regulations or hazards and compliance with complex regulations associated with mining activities; climate change and climate change regulations; the ability to replace mineral reserves and identify acquisition opportunities; the unknown liabilities of companies acquired by B2Gold; the ability to successfully integrate new acquisitions; fluctuations in exchange rates; the availability of financing; financing and debt activities, including potential restrictions imposed on B2Gold's operations as a result thereof and the ability to generate sufficient cash flows; operations in foreign and developing countries and the compliance with foreign laws, including those associated with operations in Mali, Namibia, the Philippines, Canada, and Colombia and including risks related to changes in foreign laws and changing policies related to mining and local ownership requirements or resource nationalization generally; remote operations and the availability of adequate infrastructure; fluctuations in price and availability of energy and other inputs necessary for mining operations; shortages or cost increases in necessary equipment, supplies and labour; regulatory, political and country risks, including local instability or acts of terrorism and the effects thereof; the reliance upon contractors, third parties and joint venture partners; the lack of sole decision-making authority related to Filminera Resources Corporation, which owns the Masbate Project; challenges to title or surface rights; the dependence on key personnel and the ability to attract and retain skilled personnel; the risk of an uninsurable or uninsured loss; adverse climate and weather conditions; litigation risk; competition with other mining companies; community support for B2Gold's operations, including risks related to strikes and the halting of such operations from time to time; conflicts with small scale miners; failures of information systems or information security threats; the ability to maintain adequate internal controls over financial reporting as required by law, including Section 404 of the Sarbanes-Oxley Act; compliance with anti-corruption laws, and sanctions or other similar measures; social media and B2Gold's reputation; as well as other factors identified and as described in more detail under the heading "Risk Factors" in B2Gold's most recent Annual Information Form, B2Gold's current Form 40-F Annual Report and B2Gold's other filings with Canadian securities regulators and the U.S. Securities and Exchange Commission (the "SEC"), which may be viewed at www.sedar.com and www.sec.gov, respectively (the "Websites"). The list is not exhaustive of the factors that may affect B2Gold's forward-looking statements.

B2Gold's forward-looking statements are based on the applicable assumptions and factors management considers reasonable as of the date hereof, based on the information available to management at such time. These assumptions and factors include, but are not limited to, assumptions and factors related to B2Gold's ability to carry on current and future operations, including: development and exploration activities; the timing, extent, duration and economic viability of such operations, including any mineral resources or reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and assessments; B2Gold's ability to meet or achieve estimates, projections and forecasts; the availability and cost of inputs; the price and market for outputs, including gold; foreign exchange rates; taxation levels; the timely receipt of necessary approvals or permits; the ability to meet current and future obligations; the ability to obtain timely financing on reasonable terms when required; the current and future social, economic and political conditions; and other assumptions and factors generally associated with the mining industry.

B2Gold's forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date hereof. B2Gold does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, no assurance can be given that any events anticipated by the forward-looking statements will transpire or occur, or if any of them do, what benefits or liabilities B2Gold will derive therefrom. For the reasons set forth above, undue reliance should not be placed on forward-looking statements.



For more information on B2Gold, please visit the Company’s website at www.b2gold.com or contact:

Michael McDonald
VP, Investor Relations, Corporate Development & Treasury
+1 604-681-8371        
investor@b2gold.com

FAQ

What is B2Gold's (BTG) total gold production guidance for 2025?

B2Gold confirms its 2025 total gold production guidance of 970,000 to 1,075,000 ounces across all its mining operations.

Why did B2Gold reduce the Goose Mine's 2025 production guidance?

B2Gold reduced Goose Mine's 2025 guidance from 120,000-150,000 to 80,000-110,000 ounces due to crushing plant capacity shortfall in Q3 2025, though Q4 production is expected to meet original estimates of 70,000 ounces.

What is the status of B2Gold's Fekola underground operations?

Fekola underground operations commenced after receiving approval on July 30, 2025, with positive grade reconciliations and expected production of 30,000-40,000 ounces in 2025.

How much will the Antelope underground project at Otjikoto cost?

The pre-production capital cost for the Antelope underground project has been reduced to $105 million from the original estimate of $129 million, with majority of spending planned for 2026-2027.

What is the production outlook for B2Gold's Fekola Regional project?

Fekola Regional is expected to begin production in early 2026 and produce an average of 180,000 ounces per year over its first five years (2026-2030), with mine life extending into the 2030s.

How has B2Gold's Masbate Mine performed in 2025?

Masbate Mine has outperformed expectations with strong mill throughput rates, leading to increased 2025 guidance of 190,000-210,000 ounces from the original 170,000-190,000 ounces.
B2Gold

NYSE:BTG

BTG Rankings

BTG Latest News

BTG Latest SEC Filings

BTG Stock Data

5.73B
1.25B
0.46%
68.52%
4.26%
Gold
Basic Materials
Link
Canada
Vancouver