STOCK TITAN

Collective Mining Provides an Exploration Update: Significant Visual Mineralization Intersected in Expansion Drilling at Both the Guayabales and San Antonio Projects

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Collective Mining (NYSE: CNL) reported visual mineralization from recent step-out drilling at its Guayabales Ramp Zone (Apollo system) and the San Antonio Pound target, with ten diamond rigs operating and a revised 2025 drill forecast of ~60,000 metres. The company holds approximately US$145 million in treasury and says this funds activities through at least the end of 2027. Notable historical and recent highlights include a greenfield Target X intercept of 12.85 m @ 503 g/t AgEq and prior Pound hole SAC-18: 172.40 m @ 1.88 g/t AuEq. Assay results for Ramp Zone holes are expected in 4–6 weeks and San Antonio assays are expected in November 2025.

The company contracted two additional deep-capacity rigs to begin in early Q1 2026 and plans further expansion drilling at both projects; numerous drill holes remain outstanding and will be reported when compiled.

Collective Mining (NYSE: CNL) ha riportato mineralizzazione visiva dai recenti step-out drilling nel suo Guayabales Ramp Zone (sistema Apollo) e nel target San Antonio Pound, con dieci trivelle diamantate in attività e una previsione di trivellazione 2025 rivista di circa 60.000 metri. L'azienda detiene circa US$145 milioni in tesoreria e afferma che questi fondi sosterranno le attività almeno fino alla fine del 2027. Evidenze storiche e recenti notevoli includono un intercetto di Target X greenfield di 12,85 m @ 503 g/t AgEq e il precedente Pound foro SAC-18: 172,40 m @ 1,88 g/t AuEq. I risultati delle analisi per i fori Ramp Zone sono attesi entro 4–6 settimane e le analisi di San Antonio sono previste per novembre 2025.

L'azienda ha contrattualizzato due ulteriori trivelle di ampia capacità che inizieranno all'inizio del Q1 2026 e pianifica ulteriori trivellazioni di espansione su entrambi i progetti; numerosi fori di trivellazione rimangono da riportare una volta assemblati.

Collective Mining (NYSE: CNL) informó mineralización visual a partir de recientes perforaciones de expansión en su zona de Ramp de Guayabales (sistema Apollo) y en el objetivo San Antonio Pound, con diez equipos de diamante operando y una previsión revisada de perforación para 2025 de ~60.000 metros. La empresa posee aproximadamente US$145 millones en caja y dice que estos fondos sostendrán las actividades al menos hasta finales de 2027. Destacan históricos y recientes: un intercepto greenfield Target X de 12.85 m @ 503 g/t AgEq y el agujero Pound anterior SAC-18: 172.40 m @ 1.88 g/t AuEq. Se esperan resultados de las pruebas para los agujeros Ramp Zone en 4–6 semanas y las pruebas de San Antonio están previstas para noviembre de 2025.

La compañía contrató dos perforadoras de mayor capacidad adicionales para empezar a principios del Q1 2026 y planea más perforaciones de expansión en ambos proyectos; quedan numerosos agujeros por reportar cuando se compilen.

Collective Mining (NYSE: CNL)은 최근의 확장 드릴링에서 시각적 광물화가 보고되었으며 Guayabales Ramp Zone (아폴로 시스템) 및 San Antonio Pound 목표에서 두고, 다이아몬드 로편 10대를 운영 중이고 2025년 드릴링 전망치를 약 60,000 미터로 수정했습니다. 이 회사는 약 미화 1,4500만 달러를 현금 보유하고 있으며 이 자금으로 2027년 말까지 활동을 뒷받침한다고 밝힙니다. 주목할 만한 과거 및 최근 하이라이트로는 12.85 m @ 503 g/t AgEq의 그린필드 Target X 인터셉트와 이전 Pound 구멍 SAC-18: 172.40 m @ 1.88 g/t AuEq가 있습니다. Ramp Zone 구멍의 분석 결과는 4–6주 후에 기대되며 San Antonio의 분석은 2025년 11월에 예상됩니다.

회사는 2026년 1분기 초에 시작할 두 대의 심층용 로드리를 추가로 계약했고 양 프로젝트에서 추가 확장 드릴링을 계획하고 있으며, 보고될 예정인 다수의 드릴 홀들이 남아 있습니다.

Collective Mining (NYSE: CNL) a rapporté une minéralisation visuelle à partir des forages de démarrage récents dans sa zone de ramp Guayabales (système Apollo) et la cible San Antonio Pound, avec dix foreuses diamant et une prévision de forage 2025 révisée à environ 60 000 mètres. L'entreprise détient environ US$145 millions en trésorerie et affirme que ces fonds soutiendront les activités jusqu'au moins la fin de 2027. Des faits saillants historiques et récents incluent une interception greenfield Target X de 12,85 m @ 503 g/t AgEq et le forage Pound précédent SAC-18: 172,40 m @ 1,88 g/t AuEq. Les résultats des forages Ramp Zone sont attendus dans 4–6 semaines et les analyses de San Antonio sont prévues pour novembre 2025.

La société a mandaté deux foreuses supplémentaires de grande capacité pour débuter au début du Q1 2026 et prévoit d'autres forages d'expansion sur les deux projets; de nombreux forages restent à être rapportés une fois compilés.

Collective Mining (NYSE: CNL) berichtete visuelle Mineralisierung aus jüngsten Step-out-Bohrungen in seiner Ramp Zone Guayabales (Apollo-System) und dem Ziel San Antonio Pound, wobei zehn Diamantbohrgeräte im Einsatz sind und eine überarbeitete Bohrvorhersage für 2025 von ca. 60.000 Metern vorliegt. Das Unternehmen hält etwa US$145 Millionen im Treasury und sagt, dass diese Mittel die Aktivitäten bis mindestens Ende 2027 finanzieren. Bemerkenswerte historische und aktuelle Highlights umfassen einen grüne Gelände-Intercept Target X von 12,85 m @ 503 g/t AgEq und den vorherigen Pound-Bohrloch SAC-18: 172,40 m @ 1,88 g/t AuEq. Die Ergebnisse der Ramp Zone-Bohrlöcher werden in 4–6 Wochen erwartet, und die Analysen für San Antonio sind für November 2025 vorgesehen.

Das Unternehmen hat zwei weitere Bohrgeräte mit tiefer Kapazität verpflichtet, die Anfang des Q1 2026 beginnen sollen, und plant weitere Erweiterungsbohrungen an beiden Projekten; zahlreiche Bohrlöcher stehen noch aus und werden gemeldet, sobald sie zusammengestellt sind.

Collective Mining (NYSE: CNL) أبلغت عن تَلْوِينٍ مَعدني بصري من حَفرٍ توسيعية حديثة في منطقة الانسياق Guayabales (نظام Apollo) وهدف San Antonio Pound، مع وجود عشرة حِرَف حُفْرَة ماسية قيد التشغيل وتوقع حَفر مُراجَع لسنة 2025 بــ حوالي 60,000 متر. تمتلك الشركة نحو US$145 مليون في الخزينة وتقول إنها تموّل الأنشطة حتى على الأقل نهاية 2027. من أبرز المعالم التاريخية والحديثة وجود اعتراض Target X greenfield بمقدار 12.85 م @ 503 g/t AgEq ونقطة Pound السابقة SAC-18: 172.40 م @ 1.88 g/t AuEq. سيتم تقديم نتائج التحاليل لحنفيات Ramp Zone خلال 4–6 أسابيع ومتوقع نتائج San Antonio في نوفمبر 2025.

وقعت الشركة عقداً مع اثنين من حَفّارات سِمَاكَة إضافية للبدء في أوائل الربع الأول من 2026 وتخطط لمزيد من حفر التوسع في كلا المشروعين؛ ما زال هناك العديـد من حُفَرات الخامِ التي لم تُبلَّغ بعد عند تجميعها.

Collective Mining (NYSE: CNL) 报告在其 Guayabales Ramp Zone(阿波罗系统)和 San Antonio Pound 目标的最近扩展钻探中观察到肉眼可见的矿化,十台金刚钻钻机在运作,2025 年钻探预测修订为 约60,000 米。公司手头现金约为 1.45亿美元,表示这些资金将至少支撑到 2027 年底。历史与近期的值得注意亮点包括绿色田野 Target X 的截距 12.85 m @ 503 g/t AgEq,以及此前 Pound 钻孔 SAC-18: 172.40 m @ 1.88 g/t AuEq。Ramp Zone 针孔的化验结果预计在 4–6 周内,San Antonio 的化验结果预计在 2025 年 11 月公布。

公司已签约另外两台深容量钻机,计划于 2026 年第一季度初开始,并在两个项目上进行更多扩张钻探;还有大量钻孔待汇总后公布。

Positive
  • US$145M in treasury funds operations through end-2027
  • Revised ~60,000 metres drilling program for 2025
  • 10 diamond rigs operating across projects
  • 12.85 m @ 503 g/t AgEq at Target X (greenfield discovery)
  • SAC-18: 172.40 m @ 1.88 g/t AuEq previously reported
  • Two additional deep rigs contracted to start in Q1 2026
Negative
  • Numerous drill holes outstanding; assay results pending
  • Ramp Zone results currently based on visual logging only
  • San Antonio assay results not expected until November 2025

Insights

Visual mineralization seen at two nearby projects; assays pending and treasury shows runway through 2027.

The update describes ongoing step-out and infill drilling at **Guayabales** (Apollo and Ramp Zone) and **San Antonio** (Pound) that has produced encouraging visual mineralization in multiple holes. The company reports ten rigs active, contracted additional deep rigs for Q1, 2026, and a recently closed financing leaving approximately US$145 million in treasury, which management says funds operations at least until the end of 2027.

The near-term technical case rests on third-party assay confirmation; the release repeatedly cautions visual observations are only indicative. Key dependencies include assay results for Ramp Zone holes expected in the next 4-6 weeks and San Antonio assays expected in November 2025. Operational risks include typical drilling conversion risk (visual ≠ grade), timing of assays, and the need to convert discovery intercepts into continuous, mineable zones. The company also notes expanded rig capacity for deeper testing in Q1, 2026.

Concrete near-term items to watch are assay releases for Ramp Zone holes in ~4-6 weeks, San Antonio assay results in November 2025, and the mobilization of two additional deep capacity rigs in early Q1, 2026. These milestones will materially change the technical picture once assays are published and should be monitored on that cadence.

TORONTO, Oct. 20, 2025 /PRNewswire/ - Collective Mining Ltd. (NYSE: CNL) (TSX: CNL) ("Collective" or the "Company") is pleased to provide an exploration update and announce that visual inspection of new drill core from step-out drilling at the Guayabales Project's Ramp Zone (located at the bottom of the Apollo system) and the San Antonio Project's Pound target indicates that potentially significant mineralization has been intersected. The Company has ten diamond drill rigs operating and remains on track to complete its recently revised forecast of approximately 60,000 metres of drilling in 2025. The Guayabales and San Antonio Projects are located approximately 3 kilometers apart on either side of the Pan American Highway in Caldas, Colombia and benefit from significant nearby infrastructure including hydropower access, skilled labor and roads.

As a result of the recently closed financing, the Company is in a strong financial position with approximately US$145 million in its treasury and will be able to carry out all activities to advance its business plan, at least until the end of 2027.

Ari Sussman, Executive Chairman commented: "This is the first time in my career that I have been involved in an exploration program which appears to be intersecting potentially exciting mineralization at two projects simultaneously. Visual inspection of new hole APC143-D1 into the Ramp Zone is particularly pleasing as this is the deepest hole drilled to date at the Apollo system and helps to validate our theory that only the top of the Ramp Zone system has been drilled. The Ramp Zone is a reduced intrusion related system and as such, has the potential to extend for 1,000 metres or more vertically. If correct, we may have only intersected the tip of the iceberg of the Ramp Zone thus far."

"Although its early days for the Pound target at the San Antonio Project, it is exciting to find visual mineralization for the first time beginning at a shallow depth in hole SAC-24. We look forward to receiving assay results in the short term and are happy that two additional deep capacity rigs have been secured so we can expedite the drilling in 2026 at both the Ramp Zone and the San Antonio Project."

Exploration Update Highlights (see Figures 1-4)

*The reader should take caution that references below to positive visual mineralization is for indicative purposes only and should not be relied upon. Only official assay results from a third-party laboratory should be relied upon for an actual determination of the metal content in a specific drill hole*

Guayabales Project (see Figure 1 and 4)

  • Six rigs are operating at the Guayabales Project. One rig is being mobilized to conduct expansion drilling at the outcropping zone of high-grade tungsten, gold, silver and copper; two rigs are conducting infill drilling of the Apollo system at elevations ranging between 1,500MASL to 1,000MASL and two deep capacity rigs are focused on expanding both the strike and vertical dimensions of the high-grade Ramp Zone at depth (below Apollo).

  • Of note is the recently completed drill hole APC143-D1, which cut potentially significant Ramp Zone style mineralization at the deepest elevation (~1,370m depth) drilled to date within the Apollo system. Assay results for holes drilled into the Ramp Zone are expected in the next 4-6 weeks.

  • The sixth and final rig operating at the Guayabales Project is expected to start drilling this week at Target X, where the Company recently announced a new greenfield silver discovery highlighted by hole XTC-1 which cut multiple silver rich sets of veins including a best intercept of 12.85 metres @ 503 g/t AgEq. (see press release dated September 3, 2025) The Company believes that potential exists at Target X to find a bulk style mineralized system deeper and along strike from the discovery hole, which remains open in all directions.

  • Two additional deep capacity rigs capable of testing the Ramp Zone have been contracted and are expected to begin operating at site in early Q1, 2026 which would bringing the total number of deep capacity rigs to four.

San Antonio Project (see Figures 2-4)

  • Exploration at the Pound target, the first of three targets to be tested at the San Antonio Project, continues to expand in dimensions with four drill rigs now operating in this area. As drilling continues at the Pound target, a potentially large mineralized system is taking shape and can best be described as a shallow porphyry-related, intermediate sulphidation, sheeted veinlet system sitting above a gold-copper porphyry system. The Pound target covers more than 500 metres of strike length and has been drill tested for more than 1,000 metres from surface. The system remains open in all directions for expansion.

  • In particular, recently completed drill hole SAC-24, which is a follow up hole to previously reported hole SAC-18 (172.40 metres at 1.88 g/t gold equivalent 1.40 g/t Au, 0.16% Cu, 17 g/t Ag, 68 ppm Mo and bottomed in strong mineralization; see press release dated August 25, 2025) highlights strong visual mineralization. Review of SAC-24 indicates that a first zone of intermediate sulphidation sheeted veinlet mineralization was intersected beginning at approximately 75 metres downhole which continued for up to 225 metres in length. A second, albeit narrower zone of similar style sheeted veinlet mineralization has been logged from approximately 430 metres to 500 metres downhole. Finally, porphyry style mineralization was encountered beginning at around 725 metres downhole and has been logged with various degrees of intensity until the end of the hole at 1,072 metres. The hole bottomed in mineralization as the Company decided that it makes more sense to wait for assay results from this hole before making the decision to continue to deeper depths. Assay results for drill holes completed at the San Antonio Project are expected in November 2025.

  • In continuance of its aggressive exploration strategy at the San Antonio Project, the Company plans to move one of its rigs shortly to the COP target, where large and coincidental magnetic inversion and chargeability anomalies align with favorable geochemistry from surface soil sampling.

Approximately 140,000 metres of diamond drilling has been completed to date at the Guayabales Project, including 100,000 metres at Apollo. For the San Antonio Project, approximately 13,000 metres of diamond drilling has been completed to date, including 9,500 metres at the Pound target. Numerous drill holes from both projects are outstanding and will be reported once received and compiled by the Company.

About Collective Mining Ltd.

To see our latest corporate presentation and related information, please visit www.collectivemining.com.

Founded by the team that developed and sold Continental Gold Inc. to Zijin Mining for approximately $2 billion in enterprise value, Collective is a gold, silver, copper and tungsten exploration company with projects in Caldas, Colombia. The Company has options to acquire 100% interest in two projects located directly within an established mining camp with ten fully permitted and operating mines.

The Company's flagship project, Guayabales, is anchored by the Apollo system, which hosts the large-scale, bulk-tonnage and high-grade gold-silver-copper-tungsten Apollo system. The Company's objectives at the Guayabales Project are to expand the newly discovered high-grade Ramp Zone along strike and to depth and drill a series of greenfield generated targets on the property. 

Additionally, the Company has launched its largest drilling campaign in history at the San Antonio Project as it hunts for new discoveries and looks to expand upon the newly discovered porphyry system at the Pound target. The San Antonio Project is located between two to five kilometers east-northeast of the Guayabales Project and could potentially share infrastructure given their proximity to each other.

Management, insiders, a strategic investor and close family and friends own 45.3% of the outstanding shares of the Company and as a result, are fully aligned with shareholders. The Company is listed on both the NYSE American and TSX under the trading symbol "CNL".

Qualified Person (QP) and NI43-101 Disclosure

David J Reading is the designated Qualified Person for this news release within the meaning of National Instrument 43-101 ("NI 43-101") and has reviewed and verified that the technical information contained herein is accurate and approves of the written disclosure of same. Mr. Reading has an MSc in Economic Geology and is a Fellow of the Institute of Materials, Minerals and Mining and of the Society of Economic Geology (SEG).

Technical Information

Samples were cut by Company personnel at Collective Mining's core facility in Caldas, Colombia. Diamond drill core was sawed and then sampled in maximum 2 metres intervals, stopping at geological boundaries. Drill hole core diameter is a mix of PQ, HQ and NQ depending on the depth of the drill hole.

Core samples have been prepared and analyzed at ALS laboratory facilities in Medellin, Colombia and Lima, Peru. Blanks, duplicates, and certified reference standards are inserted into the sample stream to monitor laboratory performance. Crush rejects and pulps are kept and stored in a secured storage facility for future assay verification. No capping has been applied to sample composites. The Company utilizes a rigorous, industry-standard QA/QC program.

Information Contact:

Follow Executive Chairman Ari Sussman (@Ariski73) on X

Follow Collective Mining ( @CollectiveMini1 ) on X,  (Collective Mining)  on LinkedIn, and  (@collectivemining) on Instagram

FORWARD-LOOKING STATEMENTS

This news release contains "forward-looking statements" and "forward-looking information" within the meaning of applicable securities legislation (collectively, "forward-looking statements"). All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that involves discussion with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often, but not always using phrases such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "believes" or variations (including negative variations) of such words and phrases, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved) are not statements of historical fact and may be forward-looking statements. In this news release, forward-looking statements relate, among other things, to the anticipated advancement of mineral properties or programs; future operations; future recovery metal recovery rates; future growth potential of Collective; and future development plans.

These forward-looking statements, and any assumptions upon which they are based, are made in good faith and reflect our current judgment regarding future events including the direction of our business. Management believes that these assumptions are reasonable. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: risks related to the speculative nature of the Company's business; the Company's formative stage of development; the Company's financial position; possible variations in mineralization, grade or recovery rates; actual results of current exploration activities; conclusions of future economic evaluations; fluctuations in general macroeconomic conditions; fluctuations in securities markets; fluctuations in spot and forward prices of gold, precious and base metals or certain other commodities; fluctuations in currency markets; change in national and local government, legislation, taxation, controls regulations and political or economic developments; risks and hazards associated with the business of mineral exploration, development and mining (including environmental hazards, industrial accidents, unusual or unexpected formation pressures, cave-ins and flooding); inability to obtain adequate insurance to cover risks and hazards; the presence of laws and regulations that may impose restrictions on mining; employee relations; relationships with and claims by local communities and indigenous populations; availability of increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development (including the risks of obtaining necessary licenses, permits and approvals from government authorities); and title to properties, as well as those risk factors discussed or referred to in the annual information form of the Company dated March 24, 2025. Forward-looking statements contained herein are made as of the date of this news release and the Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results, except as may be required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements and there may be other factors that cause results not to be anticipated, estimated or intended. Accordingly, readers should not place undue reliance on forward-looking statements.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/collective-mining-provides-an-exploration-update-significant-visual-mineralization-intersected-in-expansion-drilling-at-both-the-guayabales-and-san-antonio-projects-302588466.html

SOURCE Collective Mining Ltd.

FAQ

What did Collective Mining announce about drilling at Guayabales and San Antonio on October 20, 2025?

Visual mineralization was reported from step-out drilling at Guayabales Ramp Zone and San Antonio Pound; assays are pending.

How much cash does Collective Mining (CNL) have after the recent financing?

The company reported approximately US$145 million in its treasury.

How many metres of drilling does Collective Mining plan for 2025 (CNL)?

The company revised its 2025 drilling forecast to about 60,000 metres.

When are assay results expected for Guayabales Ramp Zone holes (CNL)?

Assay results for Ramp Zone holes are expected in about 4–6 weeks from October 20, 2025.

When will Collective Mining report San Antonio Project assay results (CNL)?

Assay results for San Antonio drill holes are expected in November 2025.

What notable drill intercepts did Collective Mining reference in the October 20, 2025 update?

They referenced a Target X intercept of 12.85 m @ 503 g/t AgEq and prior hole SAC-18: 172.40 m @ 1.88 g/t AuEq.

How many drill rigs are operating at Collective Mining sites and are more being added (CNL)?

Ten diamond drill rigs are operating; two additional deep-capacity rigs were contracted to start in early Q1 2026.
Collective Mng

NYSE:CNL

CNL Rankings

CNL Latest News

CNL Latest SEC Filings

CNL Stock Data

1.00B
51.97M
46.5%
28.02%
3.2%
Gold
Basic Materials
Link
Canada
Toronto