Core Natural Resources (NYSE: CNR) provided an update on efforts to resume longwall operations at its Leer South mine following a January combustion event. After re-entering the mine on June 10th, the company conducted inspections and restored systems, confirming good condition of key components. However, on June 26th, elevated carbon monoxide levels forced temporary resealing of the affected area.

The company is working with regulatory officials on a recovery plan, expecting to complete the longwall equipment repositioning within four months. Despite the delayed restart, Core maintains its 2025 coking coal sales volume guidance and anticipates insurance recoveries exceeding $100 million related to the Leer South incident.

Core expects to resume longwall production during the fourth quarter and plans to provide a detailed update in its early August second quarter earnings release.

Core Natural Resources (NYSE: CNR) ha fornito un aggiornamento sugli sforzi per riprendere le operazioni di estrazione longwall nella miniera di Leer South dopo un evento di combustione avvenuto a gennaio. Dopo essere rientrata nella miniera il 10 giugno, l'azienda ha effettuato ispezioni e ripristinato i sistemi, confermando il buon stato dei componenti chiave. Tuttavia, il 26 giugno, livelli elevati di monossido di carbonio hanno costretto a una temporanea nuova sigillatura dell'area interessata.

L'azienda sta collaborando con le autorità regolatorie per un piano di recupero, prevedendo di completare il riposizionamento delle attrezzature longwall entro quattro mesi. Nonostante il ritardo nella ripresa, Core conferma la sua previsione di volume di vendite di carbone metallurgico per il 2025 e prevede recuperi assicurativi superiori a 100 milioni di dollari relativi all'incidente di Leer South.

Core prevede di riprendere la produzione longwall nel quarto trimestre e intende fornire un aggiornamento dettagliato nel comunicato sugli utili del secondo trimestre, previsto per i primi di agosto.

Core Natural Resources (NYSE: CNR) proporcionó una actualización sobre los esfuerzos para reanudar las operaciones de longwall en su mina Leer South tras un evento de combustión ocurrido en enero. Después de reingresar a la mina el 10 de junio, la compañía realizó inspecciones y restauró los sistemas, confirmando el buen estado de los componentes clave. Sin embargo, el 26 de junio, niveles elevados de monóxido de carbono obligaron a un sellado temporal del área afectada.

La empresa está trabajando con las autoridades regulatorias en un plan de recuperación, esperando completar el reposicionamiento del equipo longwall en un plazo de cuatro meses. A pesar del retraso en el reinicio, Core mantiene su pronóstico de volumen de ventas de carbón coquizable para 2025 y anticipa recuperaciones de seguros que superan los 100 millones de dólares relacionados con el incidente de Leer South.

Core espera reanudar la producción longwall durante el cuarto trimestre y planea proporcionar una actualización detallada en su reporte de ganancias del segundo trimestre a principios de agosto.

Core Natural Resources (NYSE: CNR)는 1월 연소 사건 이후 Leer South 광산에서 롱월 작업 재개를 위한 진행 상황을 업데이트했습니다. 6월 10일 광산에 재진입한 후 회사는 점검을 실시하고 시스템을 복구하여 주요 부품의 양호한 상태를 확인했습니다. 그러나 6월 26일 일산화탄소 농도 상승으로 인해 해당 구역을 일시적으로 재밀봉해야 했습니다.

회사는 규제 당국과 협력하여 복구 계획을 수립 중이며, 롱월 장비 재배치를 4개월 내에 완료할 것으로 예상합니다. 재가동 지연에도 불구하고 Core는 2025년 코킹 석탄 판매량 가이던스를 유지하며, Leer South 사건과 관련하여 1억 달러 이상의 보험금 회수를 기대하고 있습니다.

Core는 4분기에 롱월 생산을 재개할 것으로 예상하며, 8월 초 2분기 실적 발표에서 자세한 업데이트를 제공할 계획입니다.

Core Natural Resources (NYSE : CNR) a fourni une mise à jour sur les efforts visant à reprendre les opérations longwall dans sa mine de Leer South suite à un événement de combustion en janvier. Après être entrée à nouveau dans la mine le 10 juin, la société a effectué des inspections et restauré les systèmes, confirmant le bon état des composants clés. Cependant, le 26 juin, des niveaux élevés de monoxyde de carbone ont contraint à un resealing temporaire de la zone affectée.

La société travaille avec les autorités réglementaires sur un plan de récupération, s'attendant à terminer le repositionnement de l'équipement longwall dans un délai de quatre mois. Malgré ce redémarrage retardé, Core maintient ses prévisions de volume de ventes de charbon à coke pour 2025 et anticipe des récupérations d'assurance dépassant 100 millions de dollars liées à l'incident de Leer South.

Core prévoit de reprendre la production longwall au cours du quatrième trimestre et envisage de fournir une mise à jour détaillée lors de la publication de ses résultats du deuxième trimestre début août.

Core Natural Resources (NYSE: CNR) gab ein Update zu den Bemühungen, den Longwall-Betrieb in seiner Leer South-Mine nach einem Brandereignis im Januar wieder aufzunehmen. Nach dem Wiedereintritt in die Mine am 10. Juni führte das Unternehmen Inspektionen durch und stellte Systeme wieder her, wobei der gute Zustand der wichtigsten Komponenten bestätigt wurde. Am 26. Juni zwangen jedoch erhöhte Kohlenmonoxidwerte zu einer vorübergehenden Wiederverplombung des betroffenen Bereichs.

Das Unternehmen arbeitet mit den Aufsichtsbehörden an einem Wiederherstellungsplan und erwartet, die Umpositionierung der Longwall-Ausrüstung innerhalb von vier Monaten abzuschließen. Trotz der verzögerten Wiederaufnahme hält Core an seiner Absatzmengenzielvorgabe für Kokskohle im Jahr 2025 fest und rechnet mit Versicherungserstattungen von über 100 Millionen US-Dollar im Zusammenhang mit dem Vorfall in Leer South.

Core erwartet, die Longwall-Produktion im vierten Quartal wieder aufzunehmen und plant, ein detailliertes Update in seinem Ergebnisbericht für das zweite Quartal Anfang August zu geben.

Positive
  • Insurance recovery expected to exceed $100 million
  • Longwall equipment and major components remain in good condition
  • Company maintains 2025 coking coal sales volume guidance despite delays
  • Regulatory officials actively engaged in recovery planning
Negative
  • Elevated carbon monoxide levels forced mine evacuation and resealing on June 26th
  • Longwall operations restart delayed by approximately four months
  • Production disruption continues since January combustion event

Insights

Core Natural Resources faces delays at Leer South mine due to carbon monoxide issues, but expects Q4 restart with $100M+ insurance recovery.

Core Natural Resources' update on the Leer South mine recovery efforts reveals a mixed operational picture. The company successfully re-entered the mine on June 10th following the January combustion event and found the longwall equipment largely intact—a significant positive finding given that longwall systems represent substantial capital investments, often exceeding $100 million. However, the detection of elevated carbon monoxide levels on June 26th necessitated mine evacuation and resealing, indicating that combustion-related issues remain unresolved.

This setback adds approximately four months to the recovery timeline, pushing the restart into Q4 2025. The need to reposition the longwall equipment suggests they'll likely need to abandon the current panel and set up in a new mining area, a complex undertaking requiring significant engineering work.

Despite these challenges, Core's maintenance of its 2025 coking coal sales volume guidance is noteworthy. This suggests they either have sufficient inventory, can increase production at other operations, or anticipate strong production rates once Leer South restarts. The expected insurance recovery exceeding $100 million will substantially offset financial impacts from the outage, though investors should note that such recoveries typically lag behind the actual events by several quarters.

The continued involvement of regulatory officials is standard protocol for mine recovery operations, but also indicates the complexity and safety-critical nature of the ongoing efforts. Overall, while the delay is unwelcome, the intact equipment and maintained guidance suggest the long-term operational impact will be contained.

Re-enters the mine on June 10th, consistent with previously provided timeline

Re-establishes ventilation, conducts a full inspection of the mine, restores hydraulic pressure along the longwall face, and confirms that key longwall components are in good condition

Decides to temporarily reseal the affected area of the mine on June 26th due to elevated carbon monoxide levels

Engages regulatory officials on a plan that is expected to facilitate the repositioning and restart of the longwall system within the next four months

Reiterates 2025 coking coal sales volume guidance for metallurgical segment despite delayed restart

Expects Leer South-related insurance recoveries in excess of $100 million 

CANONSBURG, Pa., June 30, 2025 /PRNewswire/ -- Today, Core Natural Resources, Inc. (NYSE: CNR) ("Core") provided an update on its ongoing efforts to resume longwall operations at its Leer South mine following a combustion-related event at the mine in mid-January. Consistent with the previously provided timeline, Core personnel and regulatory officials re-entered the sealed area of the mine on June 10th, and thereafter re-established ventilation to the full mine, restored hydraulic pressure along the longwall face, and conducted an extensive evaluation of the major equipment and infrastructure. As expected, the longwall was largely unaffected by the combustion event and major components and systems remain in good condition.

On June 26th, after more than two weeks in the mine, the operating team found it necessary to evacuate the mine and begin restoring pumpable seals to the affected area in the wake of an increase in carbon monoxide levels. The Core team is working closely with federal and state officials on a plan to recover and reposition the longwall equipment in an effort that is expected to be completed within four months.

"The Core team continues to do an admirable job of addressing the situation at Leer South in a safe and efficient manner, and we want to again thank federal and state regulatory officials for their invaluable assistance," said George J. Schuller Jr., Core's senior vice president and chief operating officer. "While recent developments are expected to delay the restart of the longwall, we are encouraged by the condition of the mine and related infrastructure, and optimistic about the prospects of resuming longwall production during the fourth quarter."

"Core maintains a property damage / business interruption insurance program and placed insurance carriers on notice immediately after the Leer South event occurred earlier this year," said Mitesh Thakkar, Core's president and chief financial officer. "Core has kept the carriers updated on developments to date and anticipates an insurance recovery in excess of $100 million."

Core is reiterating its 2025 coking coal sales volume guidance despite the delayed restart of the Leer South mine and expects to provide a more detailed update on ongoing efforts at Leer South in its second quarter earnings release in early August.

About Core Natural Resources, Inc.

Core Natural Resources, Inc. (NYSE: CNR) is a world-class producer and exporter of high-quality, low-cost coals, including metallurgical and high calorific value thermal coals. The company operates a best-in-sector portfolio, including the Pennsylvania Mining Complex, Leer, Leer South, and West Elk mines. With a focus on seaborne markets, Core plays an essential role in meeting the world's growing need for steel, infrastructure, and energy, and has ownership interests in two marine export terminals. The company was created in January 2025 via the merger of long-time industry leaders CONSOL Energy and Arch Resources and is based in Canonsburg, Pennsylvania.

Cautionary Statement Regarding Forward-Looking Statements

This communication contains certain "forward-looking statements" within the meaning of federal securities laws. Forward-looking statements may be identified by words such as "anticipate," "believe," "could," "continue," "estimate," "expect," "intend," "will," "should," "may," "plan," "predict," "project," "would" and similar expressions. Forward-looking statements are not statements of historical fact and reflect Core's current views about future events. No assurances can be given that the forward-looking statements contained in this communication will occur as projected, and actual results may differ materially from those projected. Forward-looking statements are based on current expectations, estimates and assumptions that involve a number of risks and uncertainties that could cause actual results to differ materially from those projected. These risks and uncertainties include, without limitation, risks related to the prior occurrence of combustion-related activity at Core's Leer South mine and the risk of future occurrences; the increase in combustion-related gases at Core's Leer South mine; Core's ability to resume development work at Leer South with continuous miners and longwall development in accordance with its expected timing; deterioration in economic conditions (including continued inflation) or changes in consumption patterns of our customers may decrease demand for our products, impair our ability to collect customer receivables and impair our ability to access capital; volatility and wide fluctuation in coal prices based upon a number of factors beyond our control; an extended decline in the prices we receive for our coal affecting our operating results and cash flows; significant downtime of our equipment or inability to obtain equipment, parts or raw materials; decreases in the availability of, or increases in the price of, commodities or capital equipment used in our coal mining operations; our reliance on major customers, our ability to collect payment from our customers and uncertainty in connection with our customer contracts; our inability to acquire additional coal reserves or resources that are economically recoverable; alternative steel production technologies that may reduce demand for our coal; the availability and reliability of transportation facilities and other systems that deliver our coal to market and fluctuations in transportation costs; a loss of our competitive position; foreign currency fluctuations that could adversely affect the competitiveness of our coal abroad; the risks related to the fact that a significant portion of our production is sold in international markets (and may grow) and our compliance with export control and anti-corruption laws; coal users switching to other fuels in order to comply with various environmental standards related to coal combustion emissions; the impact of current and future regulations to address climate change, the discharge, disposal and clean-up of hazardous substances and wastes and employee health and safety on our operating costs as well as on the market for coal; the risks inherent in coal operations, including being subject to unexpected disruptions caused by adverse geological conditions, equipment failure, delays in moving out longwall equipment, railroad derailments, security breaches or terroristic acts and other hazards, delays in the completion of significant construction or repair of equipment, fires, explosions, seismic activities, accidents and weather conditions; failure to obtain or renew surety bonds or insurance coverages on acceptable terms; the effects of coordinating our operations with oil and natural gas drillers and distributors operating on our land; our inability to obtain financing for capital expenditures on satisfactory terms; the effects of our securities being excluded from certain investment funds as a result of environmental, social and corporate governance practices; the effects of global conflicts on commodity prices and supply chains; the effect of new or existing laws or regulations or tariffs and other trade measures; our inability to find suitable joint venture partners or acquisition targets or integrating the operations of future acquisitions into our operations; obtaining, maintaining and renewing governmental permits and approvals for our coal operations; the effects of asset retirement obligations, employee-related long-term liabilities and certain other liabilities; uncertainties in estimating our economically recoverable coal reserves; defects in our chain of title for our undeveloped reserves or failure to acquire additional property to perfect our title to coal rights; the outcomes of various legal proceedings; the risk of our debt agreements, our debt and changes in interest rates affecting our operating results and cash flows; information theft, data corruption, operational disruption and/or financial loss resulting from a terrorist attack or cyber incident; the potential failure to retain and attract qualified personnel of Core; failure to maintain effective internal controls over financial reporting; uncertainty with respect to Core's common stock, potential stock price volatility and future dilution; uncertainty regarding the timing and value of any dividends we may declare; uncertainty as to whether we will repurchase shares of our common stock; inability of stockholders to bring legal action against us in any forum other than the state courts of Delaware; the risk that the businesses of Core and Arch Resources, Inc. will not be integrated successfully; the risk that the anticipated benefits of the merger may not be realized or may take longer to realize than expected; and other unforeseen factors.

All such factors are difficult to predict, are beyond Core's control, and are subject to additional risks and uncertainties, including those detailed in Core's annual report on Form 10-K for the year ended December 31, 2024, quarterly reports on Form 10-Q, and current reports on Form 8-K that are available on Core's website at www.corenaturalresources.com and on the SEC's website at http://www.sec.gov.

Forward-looking statements are based on the estimates and opinions of management at the time the statements are made. Core does not undertake any obligation to publicly update any forward-looking statement, whether as a result of new information, future events or otherwise, except as required by law. Readers are cautioned not to place undue reliance on these forward-looking statements that speak only as of the date hereof.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/core-natural-resources-provides-update-on-ongoing-efforts-to-resume-longwall-operations-at-leer-south-302494040.html

SOURCE Core Natural Resources

FAQ

When will Core Natural Resources (CNR) resume longwall operations at Leer South mine?

Core expects to resume longwall production during the fourth quarter of 2025, following a four-month equipment repositioning plan.

How much insurance recovery does CNR expect from the Leer South mine incident?

Core Natural Resources anticipates insurance recoveries exceeding $100 million from its property damage and business interruption insurance program.

What caused the latest delay in CNR's Leer South mine reopening?

Elevated carbon monoxide levels discovered on June 26th forced the evacuation and temporary resealing of the affected area of the mine.

Will the Leer South mine delay affect CNR's 2025 coking coal sales guidance?

No, Core Natural Resources is maintaining its 2025 coking coal sales volume guidance despite the delayed restart of the Leer South mine.

What is the current condition of CNR's Leer South mine equipment?

The longwall was reportedly largely unaffected by the combustion event, with major components and systems remaining in good condition.
Core Natural

NYSE:CNR

CNR Rankings

CNR Latest News

CNR Latest SEC Filings

CNR Stock Data

3.67B
51.67M
2.53%
58.91%
5.84%
Thermal Coal
Bituminous Coal & Lignite Mining
Link
United States
CANONSBURG