Cerrado Gold Announces Q2 2025 Production Results at Its Minera Don Nicolas Mine in Argentina
Cerrado Gold (OTCQX:CRDOF) reported Q2 2025 production of 11,437 Gold Equivalent Ounces (GEO) from its Minera Don Nicolas Mine in Argentina, showing a slight increase from Q1's 11,163 GEO. The company maintains its 2025 production guidance of 55,000-60,000 GEO, with production weighted towards H2 2025.
Key developments include the commencement of underground mining at Paloma with three access portals, expanded heap leach crushing circuit capacity, and a 20,000m exploration program. The company is also progressing with feasibility studies for its Lagoa Salgada and Mont Sorcier projects, expected by Q3/2025 and Q1/2026 respectively.
The Mont Sorcier iron project's previous PEA indicated an NPV8% of US$1.6 Billion, with potential for high-purity DRI grade iron ore concentrate exceeding 67% iron. The company expects to receive future payments of US$25 million from asset sales through 2027.
Cerrado Gold (OTCQX:CRDOF) ha riportato una produzione nel secondo trimestre 2025 di 11.437 once equivalenti d'oro (GEO) dalla sua miniera Minera Don Nicolas in Argentina, mostrando un leggero aumento rispetto alle 11.163 GEO del primo trimestre. L'azienda conferma la previsione di produzione per il 2025 tra 55.000 e 60.000 GEO, con una produzione maggiormente concentrata nella seconda metà dell'anno.
Gli sviluppi principali includono l'avvio dell'estrazione sotterranea a Paloma con tre accessi, l'ampliamento della capacità del circuito di frantumazione per il heap leach e un programma di esplorazione di 20.000 metri. La società sta inoltre avanzando con gli studi di fattibilità per i progetti Lagoa Salgada e Mont Sorcier, attesi rispettivamente per il terzo trimestre 2025 e il primo trimestre 2026.
Il precedente studio preliminare di fattibilità (PEA) del progetto di ferro Mont Sorcier indicava un valore attuale netto (NPV) all'8% di 1,6 miliardi di dollari USA, con potenziale per un concentrato di minerale di ferro a elevata purezza DRI superiore al 67% di ferro. La società prevede di ricevere pagamenti futuri per 25 milioni di dollari derivanti dalla vendita di asset fino al 2027.
Cerrado Gold (OTCQX:CRDOF) reportó una producción en el segundo trimestre de 2025 de 11,437 onzas equivalentes de oro (GEO) de su mina Minera Don Nicolas en Argentina, mostrando un ligero aumento respecto al primer trimestre con 11,163 GEO. La compañía mantiene su pronóstico de producción para 2025 de 55,000 a 60,000 GEO, con la producción concentrada en la segunda mitad del año.
Los desarrollos clave incluyen el inicio de la minería subterránea en Paloma con tres accesos, la expansión de la capacidad del circuito de trituración para el heap leach y un programa de exploración de 20,000 metros. La empresa también avanza con estudios de factibilidad para sus proyectos Lagoa Salgada y Mont Sorcier, esperados para el tercer trimestre de 2025 y primer trimestre de 2026, respectivamente.
El estudio preliminar económico (PEA) previo del proyecto de hierro Mont Sorcier indicó un VPN8% de 1.600 millones de dólares, con potencial para un concentrado de mineral de hierro de alta pureza grado DRI que supera el 67% de hierro. La compañía espera recibir pagos futuros por 25 millones de dólares provenientes de ventas de activos hasta 2027.
Cerrado Gold (OTCQX:CRDOF)는 아르헨티나에 위치한 Minera Don Nicolas 광산에서 2025년 2분기 11,437 골드 등가 온스(GEO)를 생산했다고 보고했으며, 이는 1분기 11,163 GEO보다 약간 증가한 수치입니다. 회사는 2025년 생산 가이던스를 55,000~60,000 GEO로 유지하며, 생산은 2025년 하반기에 집중될 예정입니다.
주요 개발 사항으로는 세 개의 출입구를 가진 Paloma 지하 채굴 시작, 힙 리치 파쇄 회로 용량 확장, 그리고 20,000미터 탐사 프로그램이 포함됩니다. 또한 Lagoa Salgada와 Mont Sorcier 프로젝트의 타당성 조사가 각각 2025년 3분기와 2026년 1분기까지 진행 중입니다.
Mont Sorcier 철광석 프로젝트의 이전 예비 경제성 평가(PEA)는 8% 할인율 기준 순현재가치(NPV)가 16억 달러로 나타났으며, 67% 이상의 고순도 DRI 등급 철광석 농축물이 생산 가능할 것으로 예상됩니다. 회사는 2027년까지 자산 매각을 통해 2,500만 달러의 향후 지급금을 받을 것으로 기대하고 있습니다.
Cerrado Gold (OTCQX:CRDOF) a annoncé une production au deuxième trimestre 2025 de 11 437 onces équivalentes or (GEO) provenant de sa mine Minera Don Nicolas en Argentine, enregistrant une légère augmentation par rapport aux 11 163 GEO du premier trimestre. La société maintient ses prévisions de production pour 2025 entre 55 000 et 60 000 GEO, avec une production concentrée sur le second semestre 2025.
Les développements clés incluent le début de l'exploitation souterraine à Paloma avec trois accès, l'expansion de la capacité du circuit de concassage pour le lixiviation en tas, et un programme d'exploration de 20 000 mètres. La société progresse également dans les études de faisabilité pour ses projets Lagoa Salgada et Mont Sorcier, attendues respectivement au troisième trimestre 2025 et au premier trimestre 2026.
L'étude économique préliminaire (PEA) précédente du projet de fer Mont Sorcier indiquait une valeur actuelle nette (VAN) à 8 % de 1,6 milliard de dollars US, avec un potentiel pour un concentré de minerai de fer de haute pureté de qualité DRI dépassant 67 % de fer. La société prévoit de recevoir des paiements futurs de 25 millions de dollars issus de la vente d'actifs jusqu'en 2027.
Cerrado Gold (OTCQX:CRDOF) meldete für das zweite Quartal 2025 eine Produktion von 11.437 Goldäquivalent-Unzen (GEO) aus seiner Minera Don Nicolas Mine in Argentinien, was einen leichten Anstieg gegenüber den 11.163 GEO im ersten Quartal darstellt. Das Unternehmen hält an seiner Produktionsprognose für 2025 von 55.000 bis 60.000 GEO fest, wobei die Produktion auf das zweite Halbjahr 2025 konzentriert ist.
Zu den wichtigsten Entwicklungen zählen der Beginn des Untertageabbaus bei Paloma mit drei Zugangspunkten, die Erweiterung der Kapazität der Heap-Leach-Brechanlage und ein 20.000-Meter-Explorationsprogramm. Das Unternehmen arbeitet außerdem an Machbarkeitsstudien für die Projekte Lagoa Salgada und Mont Sorcier, die voraussichtlich im dritten Quartal 2025 bzw. ersten Quartal 2026 abgeschlossen werden.
Die vorherige vorläufige Wirtschaftlichkeitsstudie (PEA) für das Mont Sorcier Eisenprojekt ergab einen Barwert (NPV) bei 8 % von 1,6 Milliarden US-Dollar mit Potenzial für ein hochreines DRI-Eisenerzkonzentrat mit über 67 % Eisenanteil. Das Unternehmen erwartet, zukünftige Zahlungen in Höhe von 25 Millionen US-Dollar aus dem Verkauf von Vermögenswerten bis 2027 zu erhalten.
- Q2 GEO production increased to 11,437 from 11,163 in Q1 2025
- Underground development commenced at Paloma with three access portals
- Expanded crushing and heap leach capacity to improve production in H2 2025
- Mont Sorcier project shows potential NPV8% of US$1.6 Billion
- Future payments of US$25 million expected from asset sales through 2027
- Balance sheet expected to strengthen with increased production and strong gold prices
- Heap leach recovery rates impacted by larger amount of primary ore with lower recovery rates
- Crushing circuit was offline for approximately 15 days in Q2
- Q2 results were modestly lower than company expectations
- CIL plant production declined due to lower grades
Gold Equivalent Ounce ("GEO") Production of 11,437 GEO for the 2nd Quarter 2025
Underground Development has commenced and production set to ramp up in H2/2025
Expanded crushing and agglomeration capacity should expand tonnages to the leach pads and improve recoveries at the Heap Leach operation
2025 Production Guidance of 55,000 - 60,000 GEO remains in place, production weighted to H2 2025 as underground ramps up
20,000m Exploration Program underway at MDN targeting potential significant resource growth opportunities
Development activities continue to progress both the Lagoa Salgada and Mont Sorcier projects
TORONTO, ONTARIO / ACCESS Newswire / July 17, 2025 / Cerrado Gold Inc. (TSXV:CERT)(OTCQX:CRDOF) ("Cerrado" or the "Company") announces production results for the second quarter ended June 2025 ("Q2 2025") from the Minera Don Nicolas Mine in Santa Cruz Province, Argentina ("MDN"). Full quarterly financial results are expected to be released prior to August 30, 2025.
Q2 Operating Highlights
Q2 Production of 11,437 GEO vs 11,163 in Q1
Heap leach production steadily ramping up to expanded capacity for H2/25
Underground development at Paloma commencing as planned with three access portals started
CIL plant starting to receive initial contribution from underground development, production expected to ramp up over H2/2025
Operational results for Q2 2025 showed a slight increase in production over the previous quarter, driven by modestly higher production from the heap leach operations. The heap leach operational performance remained steady over the quarter, however, recovery rates were impacted by a larger amount of primary ore placed on the pad during the quarter due to mine sequencing. This primary material has lower recovery rates and longer retention times as compared to oxide material. Heap leach production is expected to improve in H2/25 as more oxide ore is mined, the addition of an agglomerator to reduce fines and the ongoing upgrades to the crushing circuit are completed. In addition, during the quarter the crushing circuit was offline for approximately 15 days early in the quarter as upgrades were put in place to support higher throughput rates moving forward. Production from stockpiled material via the CIL plant declined somewhat due to lower grades, however, underground operations at Paloma are expected to begin to contribute meaningfully to production in Q3 2025 and beyond as development rates increase and more ore becomes available.
The second phase of the expansion of the heap leach crushing circuit is now operational, which will increase feed stability in order to deliver steady ore to the pad. While supporting higher production rates, additional crushing facilities are also expected to reduce the feed size to the pad and result in increased recoveries. The final updates to the crusher circuit, including final installation of the agglomerator and additional conveyors, are set to be completed in Q3/25
As previously announced, the company commenced underground mining in June, opening up three portals for underground mining beneath the Paloma pit. Ore production is expected to ramp up over the coming months and is set to make a material contribution to production rates as the year progresses. While initial production expectations are relatively modest given the current known underground resource, underground access is expected to provide a platform for major exploration activities at lower costs than drilling from surface. Underground exploration aims to materially expand resources at MDN, leveraging the underground development for a potential expansion in production and/or mine life.
On the exploration front, the Company commenced an approximate 20,000 metre drill program late in the quarter and is set to drill numerous targets in the coming months with the aim to potentially define new resources to provide mill feed to the CIL plant at MDN. Drilling commenced with a single DDH rig north of the Paloma pit, where several new veins have been intersected. Results are pending and further drilling will be required to confirm any new resources.
Mark Brennan, CEO and Chairman commented, "While Q2 results were modestly lower than our expectations as the heap leach continues to ramp up to its fully expanded capacity, we continue to be confident in our full year expectations as the underground operations ramp-up in H2/25. Cerrado also continued to progress both the Lagoa Salgada project and the Mont Sorcier projects towards completion of feasibility studies by Q3/2025 and Q1/2026 respectively, which we believe should demonstrate substantial value being unlocked by Cerrado's development projects."
Mont Sorcier Project Update
At the Mont Sorcier high-purity iron project, detailed metallurgical test work and flow sheet design continued during the quarter. All key workstreams are now engaged and the Company has commenced an infill drill program to update sufficient resources to the Proven and Probable categories as required to support the ongoing feasibility. Assay results remain pending at this time.
The Bankable Feasibility Study will look to provide greater detail of the potential for the project that was highlighted in the previous 2022 NI 43-101 Preliminary Economic Assessment ("PEA") that delivered a project NPV
Lagoa Salgada Project Update
At the Lagoa Salgada polymetallic VMS project, detailed metallurgical test work is scheduled to be completed by the end of July, with results targeting improvements across recoveries and grades for the various concentrate products. An updated Mineral Resource and Reserve Estimate is planned to be completed in Q3/25 incorporating the results of the metallurgical test work as well as using updated long term commodity price expectations. This updated resource will be used as part of the Optimized Feasibility Study that is well underway and expected to be completed around the end of Q3/25.
Corporate Activities
In addition to funding development programs at Lagoa Salgada and Mont Sorcier Cerrado continued to pay down debt during the quarter. The Company anticipates its balance sheet to strengthen over the remainder of the year as cash flow increases from higher production rates and strong gold prices. In the medium term the Company is also set to receive future payments from the sale of the Brazilian Monte do Carmo asset sale totaling US
Table 1. Key Operating Information
Review of Technical Information
The scientific and technical information in this press release has been reviewed and approved by Andrew Croal, P.Eng., Chief Technical Officer for Cerrado Gold, who is a Qualified Person as defined in National Instrument 43-101.
About Cerrado
Cerrado Gold is a Toronto-based gold production, development, and exploration company. The Company is the
In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas ("MDN") operation through continued operational optimization and is growing production through its operations at the Las Calandrias heap leach project. An extensive campaign of exploration is ongoing to further unlock potential resources in our highly prospective land package in the heart of the Deseado Masiff.
In Portugal, Cerrado is focused on the development and exploration of the highly prospective Lagoa Salgada VMS project located on the prolific Iberian Pyrite Belt in Portugal. The Lagoa Salgada project is a high-grade polymetallic project, demonstrating a typical mineralization endowment of zinc, copper, lead, tin, silver, and gold. Extensive exploration upside potential lies both near deposit and at prospective step-out targets across the large 7,209-hectare property concession. Located just 80km from Lisbon and surrounded by exceptional infrastructure, Lagoa Salgada offers a low-cost entry to a significant development and exploration opportunity, already showing its mineable scale and cashflow generation potential.
In Canada, Cerrado holds a
For more information about Cerrado please visit our website at: www.cerradogold.com.
Mark Brennan
CEO and Chairman
Mike McAllister
Vice President, Investor Relations
Tel: +1-647-805-5662
mmcallister@cerradogold.com
Disclaimer
NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.
This press release contains statements that constitute "forward-looking information" (collectively, "forward-looking statements") within the meaning of the applicable Canadian securities legislation. All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements.
Forward-looking statements contained in this press release include, without limitation, statements regarding the business and operations of Cerrado, production forecasts and estimated AISC for 2025 and beyond, the potential for additional crushing capacity that may be added and the performance of the heap leach pad, the production potential of MDN' underground mining operations, the potential to produce iron concentrate grading in excess of
SOURCE: Cerrado Gold Inc.
View the original press release on ACCESS Newswire