STOCK TITAN

Contango Announces S-K 1300 Technical Report Summary with Robust Economics and One Year Payback for its Johnson Tract Project

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags
Contango (NYSE: CTGO) has released a Technical Report Summary for its Johnson Tract Project in Alaska, revealing robust economic potential. The project shows a Post-Tax NPV5 of $225 million and IRR of 30% with a one-year payback period, based on a $2,200/oz gold price base case. The seven-year underground mining operation requires initial capital costs of $214 million with an all-in-sustaining cost of $860 per gold equivalent ounce. The project is expected to produce an annual average of 102,258 gold equivalent ounces at a grade of 7.58 g/t. At a higher gold price of $3,000/oz, the project's NPV5 increases to $400 million with 45% IRR. The company is currently focused on permitting an underground tunnel and conducting necessary studies for a feasibility study. The project has received support from federal agencies and may be selected for FAST-41 priority permitting under the National Energy Dominance Council.
Contango (NYSE: CTGO) ha pubblicato un Sommario del Rapporto Tecnico per il suo progetto Johnson Tract in Alaska, evidenziando un solido potenziale economico. Il progetto presenta un NPV post-tasse a un tasso del 5% di 225 milioni di dollari e un IRR del 30% con un periodo di recupero di un anno, basato su un prezzo dell'oro di 2.200 dollari per oncia come caso base. L'operazione mineraria sotterranea della durata di sette anni richiede costi di capitale iniziali di 214 milioni di dollari con un costo totale sostenibile di 860 dollari per oncia equivalente d'oro. Si prevede che il progetto produca una media annua di 102.258 once equivalenti d'oro con una gradazione di 7,58 g/t. A un prezzo dell'oro più elevato di 3.000 dollari per oncia, il NPV5 del progetto aumenta a 400 milioni di dollari con un IRR del 45%. Attualmente, l'azienda si concentra sull'ottenimento dei permessi per un tunnel sotterraneo e sulla conduzione degli studi necessari per una valutazione di fattibilità. Il progetto ha ottenuto il supporto delle agenzie federali e potrebbe essere selezionato per il permesso prioritario FAST-41 sotto il National Energy Dominance Council.
Contango (NYSE: CTGO) ha publicado un Resumen del Informe Técnico para su proyecto Johnson Tract en Alaska, revelando un sólido potencial económico. El proyecto muestra un VPN post-impuestos al 5% de $225 millones y una TIR del 30% con un período de recuperación de un año, basado en un precio base del oro de $2,200 por onza. La operación minera subterránea de siete años requiere costos iniciales de capital de $214 millones con un costo total sostenible de $860 por onza equivalente de oro. Se espera que el proyecto produzca un promedio anual de 102,258 onzas equivalentes de oro con una ley de 7.58 g/t. A un precio más alto del oro de $3,000 por onza, el VPN5 del proyecto aumenta a $400 millones con una TIR del 45%. Actualmente, la empresa está enfocada en obtener permisos para un túnel subterráneo y realizar los estudios necesarios para un estudio de factibilidad. El proyecto ha recibido apoyo de agencias federales y podría ser seleccionado para el permiso prioritario FAST-41 bajo el Consejo Nacional de Dominio Energético.
Contango(NYSE: CTGO)는 알래스카 Johnson Tract 프로젝트에 대한 기술 보고서 요약을 발표하며 강력한 경제적 잠재력을 공개했습니다. 이 프로젝트는 $2,200/온스 금 가격을 기준으로 세후 순현재가치(NPV5) 2억 2,500만 달러내부수익률(IRR) 30%을 보이며, 투자 회수 기간은 1년입니다. 7년간의 지하 광산 운영에는 초기 자본 비용 2억 1,400만 달러가 필요하며, 금 환산 온스당 총 유지비용은 860달러입니다. 프로젝트는 연평균 102,258 금 환산 온스를 7.58g/t 등급으로 생산할 것으로 예상됩니다. 금 가격이 온스당 3,000달러로 상승할 경우, 프로젝트의 NPV5는 4억 달러로 증가하며 IRR은 45%에 달합니다. 회사는 현재 지하 터널 허가 취득과 타당성 조사를 위한 필요한 연구 수행에 집중하고 있습니다. 이 프로젝트는 연방 기관들의 지원을 받았으며 National Energy Dominance Council 산하 FAST-41 우선 허가 대상에 선정될 가능성이 있습니다.
Contango (NYSE: CTGO) a publié un résumé du rapport technique pour son projet Johnson Tract en Alaska, révélant un fort potentiel économique. Le projet présente une VAN après impôts à 5% de 225 millions de dollars et un TRI de 30% avec un délai de récupération d'un an, basé sur un prix de l'or de 2 200 $/once en scénario de base. L'exploitation minière souterraine sur sept ans nécessite des coûts en capital initiaux de 214 millions de dollars avec un coût total de maintien de 860 $ par once équivalente d'or. Le projet devrait produire une moyenne annuelle de 102 258 onces équivalentes d'or à une teneur de 7,58 g/t. À un prix de l'or plus élevé de 3 000 $/once, la VAN5 du projet augmente à 400 millions de dollars avec un TRI de 45%. La société se concentre actuellement sur l'obtention des permis pour un tunnel souterrain et la réalisation des études nécessaires à une étude de faisabilité. Le projet a reçu le soutien des agences fédérales et pourrait être sélectionné pour une autorisation prioritaire FAST-41 dans le cadre du National Energy Dominance Council.
Contango (NYSE: CTGO) hat eine technische Berichtszusammenfassung für sein Johnson Tract-Projekt in Alaska veröffentlicht, die ein robustes wirtschaftliches Potenzial aufzeigt. Das Projekt weist einen Nachsteuer-NPV5 von 225 Millionen US-Dollar und einen IRR von 30% mit einer Amortisationszeit von einem Jahr auf, basierend auf einem Goldpreis von 2.200 US-Dollar pro Unze als Basisfall. Der siebenjährige Untertagebergbau erfordert anfängliche Investitionskosten von 214 Millionen US-Dollar bei Gesamtkosten von 860 US-Dollar pro Goldäquivalentunze. Das Projekt wird voraussichtlich eine durchschnittliche Jahresproduktion von 102.258 Goldäquivalentunzen mit einem Gehalt von 7,58 g/t erzielen. Bei einem höheren Goldpreis von 3.000 US-Dollar pro Unze steigt der NPV5 des Projekts auf 400 Millionen US-Dollar mit einem IRR von 45%. Das Unternehmen konzentriert sich derzeit auf die Genehmigung eines unterirdischen Tunnels und die Durchführung der erforderlichen Studien für eine Machbarkeitsstudie. Das Projekt hat die Unterstützung von Bundesbehörden erhalten und könnte für die FAST-41-Prioritätsgenehmigung unter dem National Energy Dominance Council ausgewählt werden.
Positive
  • Strong economics with Post-Tax NPV5 of $225M and IRR of 30.2%
  • Quick payback period of 1.3 years
  • Low AISC of $860 per gold equivalent ounce
  • High-grade resource with 7.58 g/t gold equivalent
  • Significant production of 102,258 GEO annually
  • Potential for resource expansion through underground drilling
  • Strong government support and potential fast-track permitting
Negative
  • High initial capital requirement of $213.6 million
  • Relatively short mine life of 7 years
  • Resource includes speculative Inferred category material
  • Additional permitting and studies still required

Insights

Contango's Johnson Tract shows strong economics with $224.5M NPV, 30.2% IRR, quick payback, and competitive $860/oz AISC using DSO approach.

Contango's Technical Report Summary for its Johnson Tract polymetallic project demonstrates compelling economics at current gold prices. The post-tax NPV5 of $224.5 million with a 30.2% IRR and 1.3-year payback period represents strong potential returns for a mid-tier mining project. The sensitivity analysis is particularly noteworthy - at $3,000/oz gold, NPV5 increases to $398.2 million with a 45% IRR.

The direct ship ore (DSO) approach mirrors the successful Manh Choh mine, reducing upfront capital requirements by avoiding construction of on-site processing facilities. This strategy helps explain the modest initial capital expenditure of $213.6 million, which is relatively low for an underground operation of this scale.

The all-in sustaining cost (AISC) of $860 per gold equivalent ounce is competitive and would generate healthy margins at current gold prices. This cost structure positions Johnson Tract in the lower half of the global cost curve for gold producers. The average grade of 7.58 g/t gold equivalent is substantially above industry averages, contributing to the favorable economics.

The resource estimate of 598,000 ounces of gold in the Indicated category provides a solid foundation, though the seven-year mine life is relatively short. However, management's expectation of resource expansion through additional underground drilling is reasonable given that polymetallic deposits often extend beyond initial boundaries.

While the Initial Assessment is preliminary in nature, the project's economics appear robust even under conservative assumptions. The polymetallic nature of the deposit provides valuable revenue diversification, with zinc contributing significantly to the project's value alongside gold and copper.

Johnson Tract's one-year payback period and favorable economics in various gold price scenarios present significant value creation potential for Contango.

The Johnson Tract Initial Assessment demonstrates uncommonly robust economics for a development-stage mining project. The quick payback period of 1.3 years (discounted) significantly reduces capital recovery risk compared to typical mining projects that often require 3-5 years to recoup initial investment. This accelerated capital return profile substantially improves the project's risk-adjusted value proposition.

Examining the capital intensity metrics reveals Johnson Tract's efficiency - with $213.6 million initial capital to produce an average of 90,692 payable gold equivalent ounces annually, the project requires approximately $2,350 per annual ounce of production capacity. This compares favorably to industry averages for underground operations that typically range from $2,500-4,000 per annual ounce.

The project's polymetallic nature provides important economic resilience against single-commodity price volatility. While gold represents the primary value driver at $1,014 million in potential revenue, the $274.2 million from zinc and $120.2 million from copper create significant by-product credits that strengthen the overall economics.

The sensitivity analysis demonstrating NPV5 of $181 million at $2,000 gold suggests the project maintains positive economics even at lower gold prices. Conversely, the substantial upside of $398.2 million NPV5 at $3,000 gold provides asymmetric return potential if gold prices rise.

While the current seven-year mine life represents a potential limitation, the high-grade nature of the deposit (5.33 g/t gold in Indicated resources) combined with 5.21% zinc and 0.56% copper creates substantial economic value from a relatively modest-sized operation. The company's staged development approach, focusing first on permitting the underground access tunnel, represents a prudent capital allocation strategy that limits early expenditures while advancing the project.

FAIRBANKS, AK, May 6, 2025 /PRNewswire/ - Contango ORE, Inc. ("Contango" or the "Company") (NYSE American: CTGO) is pleased to announce that it has completed the Technical Report Summary ("TRS") on the Johnson Tract Project (the "Project" or "Johnson Tract"), located in Alaska, U.S.A. The TRS summarizes the results of an Initial Assessment ("IA") of the potential viability for a seven-year life of mine ("LOM"), underground mining operation, utilizing the same direct ship ore ("DSO") approach as the highly successful Manh Choh mine.

Rick Van Nieuwenhuyse, the Company's President and Chief Executive Officer said: "We are very pleased to release the results of our Initial Assessment for our Johnson Tract Project. Assuming a price of $2,200 per ounce of gold as the "Base Case", the Project generates a Post-Tax NPV5 of $225 million and IRR of 30% with a one-year payback from commencement of commercial production.  Assuming a price of $3,000 per ounce of gold price demonstrates an NPV5 of approximately $400 million and IRR of 45% with less than a year payback from commencement of production. Initial capital costs are estimated at a modest $214 million with an all-in-sustaining cost ("AISC")1 of $860 per gold equivalent ounce ("GEO") sold at an average GEO ore grade estimated at 7.58 grams per tonne ("g/t"). Based on current resources, it is estimated that Johnson Tract will produce an annual average of 102,258 GEO and that 90,692 GEO will be recovered after processing and refining over the seven-year operating life (following the Initial Capital/Pre-Production phase). Once we get underground, we believe that drilling will define additional resources that will extend the current LOM.  

We look forward to investigating potential upsides to improve the economics and extend the mine life, which includes additional underground drilling to expand the resource to extend the known orebody down dip and along strike. Another upside that we plan to evaluate is the use of ore sorting to upgrade run of mine ore grades at site by using sensor-based sorters (for example: Optical, XRT, Laser, X-Ray) to separate waste material from higher grade ore. This would result in two improvements - fewer tonnes to transport and higher head grade feed to the mill, resulting in improved economics.

We are currently focused on permitting the underground tunnel to access the million-ounce resource and conduct a detailed underground in-fill drill program. We will also conduct metallurgical, geotechnical and hydrology studies necessary to complete a feasibility study, which will include a detailed mining and transportation plan, as well as select a specific site for processing the ore along with any modifications necessary.  In addition, we will need to conduct detailed environmental baseline work along the Road and Port Easements that have already been granted to Cook Inlet Regional Inc. ("CIRI") by the Federal government earlier this year. We expect the permitting for the proposed tunnel and adjacent laydown site with the State of Alaska will take one year.  

Part of Contango's management team just spent a week in Washington D.C. for the "Alaska on the Hill" event. We began the week meeting with CIRI, our Alaska Native Corporation partner. We had great meetings with the heads of various federal agencies that will be involved with permitting the CIRI Road and Port Easements, along with constructive meetings with our two Senators, Murkowski and Sullivan, and our Congressman, Nick Begich. We were very impressed with the overwhelming support for permitting projects in Alaska, along with the recognition of the importance of developing a domestic source of critical metals. It was noted in such meetings that the Johnson Tract project is the only critical metals mining project in Alaska that is ready for permitting and may be selected when appropriate for FAST-41 priority permitting under the newly created National Energy Dominance Council ("NEDC") and Permitting Council under the direction of the President's Executive Order, "Immediate Measures to Increase American Mineral Production", issued on March 20, 2025.  We look forward to working with the Trump Administration and our Congressional delegation to develop the Johnson Tract project and help secure American supply chain of four critical metals." 

____________________________

1 AISC includes all direct and indirect operating cash costs related directly to the physical activities of producing gold, copper, zinc, lead and silver including mining, processing and other plant costs, third-party refining expense, on-site general and administrative costs, sustaining capital and reclamation costs. Excluded from AISC are initial capital costs in the amount of $213.6 million (pre-production costs), as well as royalty and mining production taxes.

IA HIGHLIGHTS:

  • Pre-Tax net present value discounted at 5% ("NPV5") of USD $359.0 million
  • Pre-Tax Internal Rate of Return ("IRR") of 37.4%
  • Post-Tax NPV5 of USD $224.5 million with a post-tax IRR of 30.2%
  • 7-year LOM
  • LOM annual average production of 102,258 GEO at 7.58 g/t
  • Initial Capital costs of $213.6 million, including $36 million for contingency costs
  • Sustaining Capital costs of USD $61.3 million, including $12.3 million for contingency costs
  • AISC estimated at $860 per GEO sold
  • Discounted payback period of 1.3 years

BACKGROUND:

  • As a U.S. domestic and domiciled company, Contango is required to report its mineral resources in accordance with Subpart 1300 of Regulation S-K ("S-K 1300").
  • S-K 1300 was adopted by the Securities and Exchange Commission (the "SEC") to modernize mineral property disclosure requirements for mining registrants and to align U.S. disclosure requirements for mineral properties with current industry and global regulatory standards.
  • The mineral resource estimate set forth in this TRS for the Johnson Tract Project has not previously been reported under the S-K 1300 format. The TRS was prepared in accordance with S-K 1300 and will be filed on or before May 12, 2025 with the SEC through EDGAR on Form 8-K.

IA SUMMARY

The IA is preliminary in nature and includes Indicated and Inferred resources that are considered too speculative to apply the economic considerations that would enable them to be categorized as mineral reserves. There is no certainty the estimates presented in the IA will be realized. This economic analysis is based on a Resource Estimate for the deposit listed in Table 3.

TABLE 1: KEY ECONOMIC PARAMETERS (Base Case - $2,200 Gold Price)

ITEM

Description

Unit

Value

Finance





NPV (Pre-Tax)

US$ (m)

359.0


IRR (Pre-Tax)

%

37.4 %


NPV (Post-Tax)

US$ (m)

224.5


IRR (Post-Tax)

%

30.2 %


Non-Discounted Payback Period

yr

1.1


Discounted Payback Period

yr

1.3

Economics Summary





Revenue (NSR less Royalties)

US$ (m)

1,296.7


Operating Costs

US$ (m)

484.8


Initial Capital Costs

US$ (m)

213.6


Sustaining Capital Costs

US$ (m)

61.3


Payable Metal Value




Copper

US$ (m)

120.2


Zinc

US$ (m)

274.2


Lead

US$ (m)

36.6


Gold

US$ (m)

1,014.0


Silver

US$ (m)

5.1

Initial Capital





Project Team

US$ (m)

5.0


Development - Lateral + Ramp

US$ (m)

19.5


Development - Vertical

US$ (m)

0.6


Mobile Equipment

US$ (m)

18.9


Surface Infrastructure

US$ (m)

91.5


Underground Infrastructure

US$ (m)

13.3


Capitalized Operating

US$ (m)

28.8


Contingency

US$ (m)

36.0


Initial Capital Total

US$ (m)

213.6

Sustaining Capital





Project Team

US$ (m)

0.0


Development - Lateral + Ramp

US$ (m)

8.9


Development - Vertical

US$ (m)

0.4


Mobile Equipment

US$ (m)

2.5


Surface Infrastructure

US$ (m)

1.2


Underground Infrastructure

US$ (m)

6.0


Closure

US$ (m)

30.0


Capitalized Operating

US$ (m)

0.0


Contingency

US$ (m)

12.3


Sustaining Capital Total

US$ (m)

61.3

Operating





Mining

US$ (m)

213.4


Mill

US$ (m)

102.9


Transport to Dock

US$ (m)

11.6


Surface Transportation (Barge)

US$ (m)

85.0


Surface Transportation (Truck to Mill)

US$ (m)

18.8


G&A

US$ (m)

53.1


Operating Total

US$ (m)

484.8

Ore Production





Ore Milled

mt

2.7


Payable Metal




Copper

mlb

32.2


Zinc

mlb

279.3


Lead

mlb

41.8


Gold

moz

0.5


Silver

moz

0.5





Metrics





Mine Cost per Tonne Feed

US$/tonne

85.97


Cash Cost per Tonne Feed

US$/tonne

191.25


All–In-Sustaining Costs2

US$/ GEO

860.00


Average Annual GEO Produced

Au Eq Oz / Yr

102,258


Average Annual GEO Payable

Au Eq Oz / Yr

90,692

Mining Method





LHOS Mining Cost per Tonne Feed

US$/tonne

85.24


C&F Mining Cost per Tonne Feed

US$/tonne

90.89

____________________________

2 AISC includes all direct and indirect operating cash costs related directly to the physical activities of producing gold, copper, zinc, lead and silver including mining, processing and other plant costs, third-party refining expense, on-site general and administrative costs, sustaining capital and reclamation costs. Excluded from AISC are initial capital costs in the amount of $213.6 million (pre-production costs), as well as royalty and mining production taxes.

TABLE 2: GOLD PRICE SENSITIVITY ANALYSIS

Sensitivity

$2,000 Au

$2,200 Au

$3,000 Au

$4,000 Au

Post-Tax NPV5 (US$ m)

$181.0

$224.5

$398.2

$615.4

TABLE 3: RESOURCE ESTIMATE

Category


Tonnes
(000s)

Au
(g/t)


Ag
(g/t)


Cu
(%)


Pb
(%)


Zn
(%)


AuEq
(g/t)

Indicated


3,489


5.33


6.0


0.56


0.67


5.21


9.39

Inferred


706


1.36


9.1


0.59


0.30


4.18


4.76

Contained Metal

Category




Au
(K oz) 


Ag
(K oz) 


Cu
(M lb)


Pb
(M lb)


Zn
(M lb)


AuEq
(K oz)

Indicated




598


673


43.1


51.5


400.8


1,053

Inferred




31


207


9.2


4.7


65.1


108

Notes


1.

Includes all drill holes completed at Johnson Tract Deposit, with drilling completed between 1982 and most recently as October 2021

2.

Assumed metal prices are US$1650/oz for gold (Au), US$20/oz for silver (Ag), US$3.50/lb copper (Cu), US$1/lb lead (Pb), and US$1.50/lb for zinc (Zn). Metal prices were established considering the review of three-year averages of published monthly values.

3.

Gold Equivalent (AuEq) is based on assumed metal prices and payable metal recoveries of 97% for Au, 85% for Ag, 85% Cu, 72% Pb and 92% Zn from metallurgical testwork completed in 2022.

4.

AuEq equals = Au g/t + Ag g/t × 0.01 + Cu% × 1.27 + Pb% × 0.31 + Zn% × 0.59

5.

An average bulk density value of 2.84 used as determined by conventional analytical methods for assay samples

6.

Capping applied to assays to restrict the impact of high-grade outliers

7.

Preliminary underground constraints were applied, including the elimination of isolated or scattered blocks above cut-off grade to define the "reasonable prospects of eventual economic extraction" for the Mineral Resource Estimate

8.

Mineral resources as reported are undiluted

9.

Mineral resource tonnages have been rounded to reflect the precision of the estimate

10.

Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability

QUALIFIED PERSON DISCLOSURE:

This report dated May 6, 2025 was prepared as an Initial Assessment Technical Report Summary, in accordance with the Securities and Exchange Commission (SEC) S-K regulations (Title 17, Part 229, Item 601 and Subpart 1300 until 1305) for Contango by SRK Consulting (Canada) Inc. (SRK) on the Johnson Tract Polymetallic (Gold, Zinc, Copper, Silver, Lead) Project (the Project). Additional Qualified Persons were engaged by Contango to complete the Initial Assessment Technical Report as SRK is not the sole owner of the work and study. The TRS was prepared in accordance with S-K 1300 and will be filed on or before May 12, 2025 with the SEC through EDGAR on Form 8-K.

In accordance with the SEC S-K regulations, SRK Consulting (Canada) Inc. has authored Sections 13 (Mining Methods), 15 (Infrastructure), 17 (Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups), 18 (Capital and Operating Costs), and 19 (Economic Analysis), as well as relevant content in Sections 1 (Executive Summary), 22 (Interpretations and Conclusions), and 23 (Recommendations) of the TRS report as a Qualified Person under Item 1302 of Regulation S-K,  and has reviewed the inclusion of its summary of the report in this news release.

In accordance with the SEC S-K regulations, James Gray, P.Geo, Advantage Geoservices has authored Section 11 (Mineral Resource Estimates) of the TRS report as the Qualified Person under item 1302 of Regulation S-K, and has reviewed the inclusion of its summary of the report in this news release. International Metallurgical and Environmental, Inc. has authored Section 10 (Mineral Processing and Metallurgical Testing) of the TRS report as the Qualified Person under item 1302 of Regulation S-K, and has reviewed the inclusions of its summary of the report in this news release.

CONFERENCE CALL AND WEBCAST 

Contango will host a conference call and webcast to discuss this release on May 8, 2025, at 1pm EST / 10am PST. Participants may join the webcast using the following call-in details:   Contango Announces S-K 1300 Technical Report Summary with Robust Economics

ABOUT CONTANGO

Contango is a NYSE American listed company that engages in exploration for gold and associated minerals in Alaska. Contango holds a 30% interest in the Peak Gold JV, which leases approximately 675,000 acres of land for exploration and development on the Manh Choh project, with the remaining 70% owned by KG Mining (Alaska), Inc., an indirect subsidiary of Kinross Gold Corporation, operator of the Peak Gold JV. The Company and its subsidiaries also have (i) a lease on the Johnson Tract project from the underlying owner, CIRI Native Corporation, (ii) a lease on the Lucky Shot project from the underlying owner, Alaska Hardrock Inc., (iii) 100% ownership of approximately 8,600 acres of peripheral State of Alaska mining claims, and (iv) a 100% interest in approximately 145,000 acres of State of Alaska mining claims that give Contango the exclusive right to explore and develop minerals on these lands. Additional information can be found on our web page at www.contangoore.com.  

FORWARD-LOOKING STATEMENTS

This press release contains forward-looking statements regarding Contango that are intended to be covered by the safe harbor for "forward-looking statements" provided by the Private Securities Litigation Reform Act of 1995, based on Contango's current expectations and includes statements regarding future results of operations, quality and nature of the asset base, the assumptions upon which estimates are based and other expectations, beliefs, plans, objectives, assumptions, strategies or statements about future events or performance (often, but not always, using words such as "expects", "projects", "anticipates", "plans", "estimates", "potential", "possible", "probable", or "intends", or stating that certain actions, events or results "may", "will", "should", or "could" be taken, occur or be achieved). Forward-looking statements are based on current expectations, estimates and projections that involve a number of risks and uncertainties, which could cause actual results to differ materially from those reflected in the statements. These risks include, but are not limited to: the risks of the exploration and the mining industry (for example, operational risks in exploring for and developing mineral reserves; risks and uncertainties involving geology; the speculative nature of the mining industry; the uncertainty of estimates and projections relating to future production, costs and expenses; the volatility of natural resources prices, including prices of gold and associated minerals; the existence and extent of commercially exploitable minerals in properties acquired by Contango or the Peak Gold JV; ability to realize the anticipated benefits of the Peak Gold JV; potential delays or changes in plans with respect to exploration or development projects or capital expenditures; the interpretation of exploration results and the estimation of mineral resources; the loss of key employees or consultants; health, safety and environmental risks and risks related to weather and other natural disasters); uncertainties as to the availability and cost of financing; Contango's inability to retain or maintain its relative ownership interest in the Peak Gold JV; inability to realize expected value from acquisitions; inability of our management team to execute its plans to meet its goals; the extent of disruptions caused by an outbreak of disease, such as the COVID-19 pandemic; and the possibility that government policies may change, political developments may occur or governmental approvals may be delayed or withheld, including as a result of presidential and congressional elections in the U.S. or the inability to obtain mining permits. Additional information on these and other factors which could affect Contango's exploration program or financial results are included in Contango's other reports on file with the U.S. Securities and Exchange Commission. Investors are cautioned that any forward-looking statements are not guarantees of future performance and actual results or developments may differ materially from the projections in the forward-looking statements. Forward-looking statements are based on the estimates and opinions of management at the time the statements are made. Contango does not assume any obligation to update forward-looking statements should circumstances or management's estimates or opinions change.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/contango-announces-s-k-1300-technical-report-summary-with-robust-economics-and-one-year-payback-for-its-johnson-tract-project-302446621.html

SOURCE Contango Ore

FAQ

What is the expected annual gold production at Contango's Johnson Tract Project?

The Johnson Tract Project is expected to produce an annual average of 102,258 gold equivalent ounces (GEO) with 90,692 GEO recovered after processing over the seven-year mine life.

What is the initial capital cost for CTGO's Johnson Tract Project?

The initial capital cost for the Johnson Tract Project is $213.6 million, which includes $36 million for contingency costs.

What is the NPV and IRR of Contango's Johnson Tract Project at $2,200 gold price?

At a $2,200 gold price, the project has a Post-Tax NPV5 of $224.5 million and an IRR of 30.2%.

How long is the expected mine life of CTGO's Johnson Tract Project?

The Johnson Tract Project has a planned seven-year life of mine (LOM) based on current resources.

What is the all-in sustaining cost (AISC) for Contango's Johnson Tract Project?

The all-in sustaining cost (AISC) is estimated at $860 per gold equivalent ounce sold.
Contango Ore

NYSE:CTGO

CTGO Rankings

CTGO Latest News

CTGO Stock Data

173.56M
8.43M
37.86%
26.76%
6.32%
Gold
Gold and Silver Ores
Link
United States
HOUSTON