Calibre Reports Q1 Financial and Production Results; Valentine Advances Toward Gold Production in Q3, Setting Up for Significant Growth; Calibre Mining & Equinox Gold Merger Anticipated to Close During Q2, 2025

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Positive)
Calibre Mining (CXBMF) reported strong Q1 2025 results with consolidated gold production of 71,539 ounces and AISC of $1,389/oz. The company's Valentine Gold Mine in Newfoundland is advancing toward production, now expected by end of Q3 2025, though facing an $80M capital increase to C$854M due to delays and scope changes. The project remains fully funded with $203M cash on hand. The company is progressing with its merger with Equinox Gold, expected to close in Q2 2025. Q1 financial highlights include revenue of $200.0M at an average realized gold price of $2,796/oz. The company maintains its 2025 production guidance of 230,000-280,000 ounces. Valentine's construction is materially complete, with final electrical and instrumentation work ongoing. The project is strengthened by new leadership appointment and is expected to produce approximately 200,000 ounces annually once at full capacity in Q1 2026.
Calibre Mining (CXBMF) ha riportato solidi risultati nel primo trimestre 2025 con una produzione consolidata di oro di 71.539 once e un AISC di 1.389 $/oz. La miniera d'oro Valentine in Terranova sta avanzando verso la produzione, ora prevista entro la fine del terzo trimestre 2025, nonostante un aumento del capitale di 80 milioni di dollari, portando il totale a 854 milioni di dollari canadesi a causa di ritardi e modifiche al progetto. Il progetto rimane completamente finanziato con 203 milioni di dollari in cassa. La società sta procedendo con la fusione con Equinox Gold, che si prevede si concluda nel secondo trimestre 2025. I punti salienti finanziari del primo trimestre includono un ricavo di 200,0 milioni di dollari con un prezzo medio realizzato dell'oro di 2.796 $/oz. L'azienda conferma la guida produttiva per il 2025 tra 230.000 e 280.000 once. La costruzione di Valentine è sostanzialmente completata, con i lavori finali di elettricità e strumentazione in corso. Il progetto è rafforzato dalla nomina di una nuova leadership e si prevede che produca circa 200.000 once all'anno una volta a piena capacità nel primo trimestre 2026.
Calibre Mining (CXBMF) reportó sólidos resultados en el primer trimestre de 2025 con una producción consolidada de oro de 71,539 onzas y un AISC de 1,389 $/oz. La mina de oro Valentine en Terranova avanza hacia la producción, ahora prevista para finales del tercer trimestre de 2025, aunque enfrenta un aumento de capital de 80 millones de dólares a 854 millones de dólares canadienses debido a retrasos y cambios en el alcance. El proyecto sigue totalmente financiado con 203 millones de dólares en efectivo. La compañía avanza con su fusión con Equinox Gold, que se espera se cierre en el segundo trimestre de 2025. Los aspectos financieros destacados del primer trimestre incluyen ingresos de 200.0 millones de dólares con un precio promedio realizado del oro de 2,796 $/oz. La empresa mantiene su guía de producción para 2025 de 230,000 a 280,000 onzas. La construcción de Valentine está prácticamente terminada, con trabajos finales de electricidad e instrumentación en curso. El proyecto se fortalece con un nuevo nombramiento en liderazgo y se espera que produzca aproximadamente 200,000 onzas anuales una vez que alcance su plena capacidad en el primer trimestre de 2026.
Calibre Mining (CXBMF)는 2025년 1분기에 통합 금 생산량 71,539온스와 AISC 1,389달러/온스를 기록하며 강력한 실적을 발표했습니다. 뉴펀들랜드에 위치한 Valentine 금광은 생산을 향해 순조롭게 진행 중이며, 지연 및 범위 변경으로 인해 자본금이 8,000만 달러 증가해 총 8억 5,400만 캐나다 달러가 되었으나 2025년 3분기 말까지 생산이 예상됩니다. 프로젝트는 현금 2억 300만 달러로 완전 자금 조달 상태를 유지하고 있습니다. 회사는 Equinox Gold와의 합병을 진행 중이며 2025년 2분기 종료가 예상됩니다. 1분기 재무 하이라이트로는 매출 2억 달러와 평균 실현 금 가격 2,796달러/온스가 포함됩니다. 회사는 2025년 생산 가이던스를 23만~28만 온스로 유지하고 있습니다. Valentine 건설은 사실상 완료되었으며, 최종 전기 및 계측 작업이 진행 중입니다. 새로운 리더십 임명으로 프로젝트가 강화되었으며 2026년 1분기 완전 가동 시 연간 약 20만 온스 생산이 기대됩니다.
Calibre Mining (CXBMF) a publié de solides résultats pour le premier trimestre 2025 avec une production d'or consolidée de 71 539 onces et un AISC de 1 389 $/oz. La mine d'or Valentine à Terre-Neuve progresse vers la production, désormais prévue d'ici la fin du troisième trimestre 2025, malgré une augmentation du capital de 80 millions de dollars à 854 millions de dollars canadiens en raison de retards et de modifications du périmètre. Le projet reste entièrement financé avec 203 millions de dollars en liquidités. La société avance dans sa fusion avec Equinox Gold, attendue pour le deuxième trimestre 2025. Les points financiers clés du premier trimestre incluent un chiffre d'affaires de 200,0 millions de dollars avec un prix de l'or moyen réalisé de 2 796 $/oz. L'entreprise maintient ses prévisions de production pour 2025 entre 230 000 et 280 000 onces. La construction de Valentine est pratiquement terminée, les travaux finaux d'électricité et d'instrumentation étant en cours. Le projet est renforcé par une nouvelle nomination à la direction et devrait produire environ 200 000 onces par an une fois à pleine capacité au premier trimestre 2026.
Calibre Mining (CXBMF) meldete starke Ergebnisse für das erste Quartal 2025 mit einer konsolidierten Goldproduktion von 71.539 Unzen und einem AISC von 1.389 $/oz. Die Valentine Goldmine in Neufundland schreitet in Richtung Produktion voran, die nun bis Ende Q3 2025 erwartet wird, trotz einer Kapitalerhöhung um 80 Mio. $ auf 854 Mio. CAD aufgrund von Verzögerungen und Änderungen im Umfang. Das Projekt ist mit 203 Mio. $ Barmitteln vollständig finanziert. Das Unternehmen arbeitet an der Fusion mit Equinox Gold, die im zweiten Quartal 2025 abgeschlossen werden soll. Die finanziellen Highlights des ersten Quartals umfassen Einnahmen von 200,0 Mio. $ bei einem durchschnittlichen realisierten Goldpreis von 2.796 $/oz. Das Unternehmen hält seine Produktionsprognose für 2025 von 230.000 bis 280.000 Unzen aufrecht. Der Bau von Valentine ist im Wesentlichen abgeschlossen, mit laufenden letzten Elektro- und Instrumentierungsarbeiten. Das Projekt wird durch eine neue Führungsbesetzung gestärkt und soll bei voller Kapazität im ersten Quartal 2026 etwa 200.000 Unzen jährlich produzieren.
Positive
  • Strong Q1 production of 71,539 ounces, positioning to meet or exceed full-year guidance
  • Healthy financial position with $177.4M cash and $36.6M restricted cash
  • Valentine Gold Mine remains fully funded with $203M cash available
  • Revenue increased to $200M in Q1 2025 from $129.2M in Q1 2024
  • AISC below budget at $1,389/oz
  • Merger with Equinox Gold to create second-largest gold producer in Canada
Negative
  • Valentine project capital cost increased by $80M to C$854M
  • Production delay at Valentine, now expected in Q3 instead of earlier timeline
  • Lower than planned productivity at Valentine construction
  • Nameplate capacity at Valentine not expected until Q1 2026

VANCOUVER, British Columbia, May 07, 2025 (GLOBE NEWSWIRE) -- Calibre Mining Corp. (TSX: CXB; OTCQX: CXBMF) (the "Company" or "Calibre") is pleased to announce financial and operating results for the three months (“Q1”) ended March 31, 2025, and an update on the Valentine Gold Mine (“Valentine”), located in Newfoundland & Labrador, Canada. Consolidated Q1 2025 filings can be found at www.sedarplus.ca and on the Company’s website at www.calibremining.com. All figures are expressed in U.S. dollars unless otherwise stated.

Darren Hall, President and Chief Executive Officer of Calibre, stated: “I am proud of the teams operational performance across the portfolio, responsibly delivering 71,539 ounces in Q1, positioning the Company to meet, and potentially exceed, full-year production guidance of 230,000 – 280,000 ounces. I am also pleased with our continued focus on cost discipline, with the Company’s consolidated all-in sustaining costs coming in below budget at $1,389/oz for the quarter.

At Valentine, construction continues to advance with first gold now expected by the end of Q3. The delay was due to lower than planned productivity, and minor scope growth, which has resulted in an $80 million (C$110 million) increase to the initial project capital since our October 2024 update of C$744 million. Approximately 75% of the capital increase is attributable to the schedule extension and 25% is related to scope growth and quantity. As at the end of April the initial project capital remains fully funded with $203 million (C$280 million) in cash and $73 million (C$101 million) remaining to be incurred.

With mass construction materially complete the focus is on final electrical, piping, and instrumentation activities within the process plant. The primary crusher has been commissioned, with the coarse ore stockpile building well underway and ready to receive material by the end of May.

To ensure smooth commissioning and transition to operations, we have strengthened contractor oversight and enhanced the owner’s team with the recent appointment of Pierre Légaré as Project Director for the process plant. Pierre is the Managing Director of Alvarez and Marsal INFRA Canada and has a proven track record over 30 years of project development across the mining and construction industries. His extensive career also includes over 20 years in senior roles at SNC-Lavalin, culminating in his position as Vice-President of Projects in the Mining & Metallurgy division.  These actions position us for a safe, more controlled, and efficient ramp-up, with operations expected to reach nameplate capacity in Q1 2026.

We have successfully completed Valentine mine and mill staffing in preparation for commissioning and ramp-up activities. Importantly, key roles have commissioning experience which is critical to a smooth ramp up and long-term operational performance.

As a long-life, low-cost cornerstone asset in Canada, Valentine is expected to produce approximately 200,000 ounces of gold annually. The asset also offers significant exploration upside, highlighted by our new discovery where drilling intercepted 172.8 metres grading 2.43 g/t gold. 2025 will mark the largest pure exploration program in the property’s history.

We greatly appreciate the support of our shareholders for approving the merger with Equinox Gold, which is expected to close by the end of Q2. Through enhanced scale, a diversified asset base, and new high quality Canadian production, this merger is positioned to deliver greater value than either company could achieve independently.”

Q1 2025 Highlights

  • Consolidated gold production of 71,539 ounces; Nicaragua 64,469 ounces and Nevada 7,070 ounces;
  • The multi-million-ounce Valentine Gold Mine is set to achieve production in Q3;
  • The largest pure exploration drill program is underway at Valentine totalling 100,000 metres; recent Frank Zone discovery drilling highlights (see Calibre news releases dated November 25, 2024, and February 11, 2025), southwest of the Leprechaun pit includes:
    • 2.43 g/t Au over 172.8 metres ETW including 3.84 g/t Au over 90.9 metres ETW in Hole FZ-24-048; and
    • 2.12 g/t Au over 95.4 metres ETW in Hole FZ-24-046, 2.26 g/t Au over 78.3 metres ETW in Hole FZ-24-040, 3.08 g/t Au over 48.2 metres ETW in Hole FZ-24-062.

Equinox Gold and Calibre Combine to Create a Major Americas-Focused Gold Producer

  • Announced the merger of Calibre and Equinox Gold to create a major Americas-focused gold producer with enhanced diversification, scale, financial strength, and operational expertise. The combined company will deliver long-term value to all stakeholders. Key highlights include:
    • Strengthened combined leadership team with a proven track record of value creation;
    • Immediate increase in production and substantial cash flow from a larger asset portfolio;
    • Creation of the second largest gold producer in Canada;
    • Significant re-rate potential based on valuation of peers;
    • A major diversified gold producer in the Americas;
    • Exceptional growth profile with a pipeline of development and expansion projects; and
    • Strong balance sheet with ability to rapidly deleverage and return capital to shareholders.

Gold Sales and Cost Metrics

  • Consolidated gold sales of 71,545 ounces, generating $200.0 million in gold revenue (Q1 2024 - $129.2 million), at an average realized gold price of $2,796/oz; Nicaragua 64,469 ounces and Nevada 7,076 ounces;
  • Consolidated Total Cash Cost1 (“TCC”) of $1,221/oz; Nicaragua $1,173/oz and Nevada $1,654/oz;
  • Consolidated All-In Sustaining Cost1 (“AISC”) of $1,389/oz; Nicaragua $1,255/oz and Nevada $1,748/oz; and
  • Cash and restricted cash of $177.4 million and $36.6 million, respectively, as at March 31, 2025, with the final $25.0 million of restricted cash released to the Company in April 2025.

Valentine Update

  • Tailings Management Facility is complete;
  • Structural steel is complete;
  • Mass construction nearing completion; project has transitioned to system/sub-system completion;
  • Primary crusher installation and commissioning complete;
  • Mills motors and mill liners are installed, and pre-commissioning is underway;
  • Conveyors are complete and commissioned;
  • CIL tanks piping and electrical continue, and pre-commissioning to follow;
  • Coarse ore stockpile building, reclaim tunnel, and apron feeder construction nearly complete and progressing toward pre-commissioning;
  • ADR plant and gravity circuit mechanically complete and have been turned over to pre-commissioning;
  • Cable tray, cable installation, and terminations progressing;
  • Commencement of ore processing expected during Q3, reflecting minor scope growth in certain areas such as electrical cabling and current contractor performance;
  • Updated initial project capital cost is now estimated at approximately C$854 million (excluding sunk costs). At April 30, 2025, initial project capital costs on an incurred basis totalled C$753 million (excluding sunk costs);
  • Initial project capital cost is fully funded with over $203 million (C$280 million) in cash at April 30, 2025; and
  • Phase 2 technical studies progressing, targeting an increase in the plant throughput from 2.5 Mtpa to >5 Mtpa.

Valentine Construction Progress Photos

Pebble Crusher and Recirculating Conveyors – April 2025

Image 1

SAG and Ball Mill - April 2025

Image 2

CONSOLIDATED RESULTS Q1 2025

Consolidated Results (1)



$'000 (except per share and per ounce amounts)
Three Months Ended
Q1 2025Q4 2024Q1 2024
Revenue$202,622 $202,966 $131,888 
Cost of sales, including depreciation and amortization$(123,322)$(138,607)$(102,631)
Earnings from mine operations$79,300 $64,359 $29,257 
EBITDA(2)$83,226 $73,456 $26,479 
Adjusted EBITDA(2)$100,764 $95,573 $37,320 
Net earnings$22,599 $16,661 $(3,636)
Adjusted net earnings(2)$40,137 $38,550 $5,587 
Operating cash flows before working capital(2)$55,074 $127,587 $62,862 
Operating cash flow$53,476 $91,404 $45,815 
Capital expenditures (sustaining)(2)$4,605 $6,940 $7,708 
Capital expenditures (growth)(2)$121,206 $125,485 $68,149 
Capital expenditures (exploration)$13,494 $13,985 $7,707 
Operating Results   
Gold ounces produced 71,539  76,269  61,767 
Gold ounces sold 71,545  76,252  61,778 
Per Ounce Data   
Average realized gold price(2) ($/oz)$2,796 $2,616 $2,092 
TCC ($/oz) (2)$1,221 $1,243 $1,337 
AISC ($/oz) (2)$1,389 $1,423 $1,555 
Weighted Avg. Numbers of Shares Outstanding   
Basic (in thousands) 848,747  838,038  653,855 
Diluted (in thousands) 905,293  869,947  681,420 
Per Share Data   
Earnings per share – basic$0.03 $0.02 $(0.01)
Earnings per share – fully diluted$0.02 $0.02 $(0.01)
Adjusted net earnings per share – basic(2)$0.05 $0.05 $0.01 
Operating cash flows before working capital/share(2)$0.06 $0.15 $0.10 
Operating cash flow per share$0.06 $0.11 $0.07 
Balance Sheet Data (in thousands, except for ratio)   
Cash and cash equivalents$177,385 $131,093 $54,385 
Adjusted net debt(2)$164,670 $165,201 $241,454 
Adj. Net debt/Adj. EBITDA (LTM) ratio(2, 3)$0.63 $0.77 $1.07 
  1. Consolidated financial and operational results for Q1 2024 include the results from Marathon since its acquisition from the period of January 25, 2024, to March 31, 2024.
  2. This is a non-IFRS measure, for further information refer to the Non-IFRS Measures section in the Notes below.
  3. LTM is defined as the last twelve months.

Operating Results

 Three Months Ended
NICARAGUAQ1 2025Q4 2024Q1 2024
Ore mined (t)522,710796,789534,788
Ore milled (t)585,576617,415531,011
Grade (g/t Au)4.143.973.32
Recovery (%)90.689.191.6
Gold produced (ounces)64,46966,57855,007
Gold sold (ounces)64,46966,57855,007
 
  Three Months Ended
NEVADAQ1 2025Q4 2024Q1 2024
Ore mined (t)1,174,2811,116,192988,694
Ore placed on leach pad (t)1,162,1801,136,772975,354
Grade (g/t Au)0.310.360.37
Gold produced (ounces)7,0709,6916,760
Gold sold (ounces)7,0769,6746,771


2025 GUIDANCE

 Q1 ACTUALSCONSOLIDATEDNICARAGUANEWFOUNDLANDNEVADA
Gold Production/Sales (ounces) 71,539230,000 - 280,000200,000 - 250,000N/A30,000 - 40,000
TCC ($/ounce)1$1,221$1,300 - $1,400$1,200 - $1,300N/A$1,600 - $1,700
AISC ($/ounce)1$1,389$1,500 - $1,600$1,400 - $1,500N/A$1,600 - $1,700
Growth Capital ($ million)$19$70 - $80$60 - $70N/A$5 - $10
Exploration ($ million)$13$50 - $60$25 - $30$15 - $20$5 - $10


The 2025 guidance currently covers gold production, TCC, AISC, and growth capital for operations in Nicaragua and Nevada. The consolidated exploration guidance includes drilling activities at the Valentine gold mine. Guidance for Valentine, including production, TCC, AISC, growth and full-year consolidated details, will be provided after first gold is produced from Valentine, expected in Q3 of this year.

Calibre continues to reinvest in exploration and growth, with approximately 200,000 metres of diamond, RC and RAB drilling and the development of new satellite deposits across its entire asset portfolio. Growth capital investments include underground and open pit mine development, waste stripping and strategic land acquisitions.

   
Q1 2025 Conference Call Details
   
Date: Thursday, May 8, 2025
Time: 10:00 am ET
Webcast link: https://edge.media-server.com/mmc/p/owjabixj
   

Instructions for obtaining conference call dial-in number:

  1. All parties must register at the link below to participate in Calibre’s Q1 2025 Conference Call.
  2. To register click https://dpregister.com/sreg/10197889/febb10ad93 and complete the online registration form.
  3. Once registered, registered participants will receive the dial-in numbers and PIN number for input at the time of the call.

The live webcast and registration link can also be accessed at www.calibremining.com under the Events section under the Investors tab. The live audio webcast will be archived and available for replay for 12 months after the event at www.calibremining.com. Presentation slides that will accompany the conference call will be made available in the Investors section of the Calibre website under Presentations prior to the conference call.

Qualified Person

The scientific and technical information contained in this news release was approved by David Schonfeldt P.GEO, Calibre’s Corporate Chief Geologist and a "Qualified Person" under National Instrument 43-101.

About Calibre

Calibre (TSX: CXB) is a Canadian-listed, Americas focused, growing mid-tier gold producer with a strong pipeline of development and exploration opportunities across Newfoundland & Labrador in Canada, Nevada and Washington in the USA, and Nicaragua. Calibre is focused on delivering sustainable value for Securityholders, local communities and all stakeholders through responsible operations and a disciplined approach to growth. With a strong balance sheet, a proven management team, strong operating cash flow, accretive development projects and district-scale exploration opportunities Calibre will unlock significant value.

ON BEHALF OF THE BOARD

“Darren Hall”

Darren Hall, President & Chief Executive Officer

For further information, please contact:

Ryan King
SVP Corporate Development & IR
T: 604.628.1012
E: calibre@calibremining.com
W: www.calibremining.com

Calibre’s head office is located at Suite 1560, 200 Burrard St., Vancouver, British Columbia, V6C 3L6.

YouTube / Instagram / LinkedIn / Facebook / X

The Toronto Stock Exchange has neither reviewed nor accepts responsibility for the adequacy or accuracy of this news release.

NOTES

* Refer to the “Valentine Gold Project NI 43-101 Technical Report and Feasibility Study, Newfoundland & Labrador, Canada” dated November 30, 2022 and found on the Calibre website at www.calibremining.com and on SEDAR+ at www.sedarplus.ca.

(1) NON-IFRS FINANCIAL MEASURES

Calibre has included certain non-IFRS measures as discussed below. The Company believes that these measures, in addition to conventional measures prepared in accordance with IFRS, provide investors with an improved ability to evaluate the underlying performance of the Company. These non-IFRS measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers.

TCC per Ounce of Gold: TCC include production costs, royalties, production taxes, refinery charges, and transportation charges. Production costs consist of mine site operating costs such as mining, processing, local administrative costs (including stock-based compensation related to mine operations) and current inventory write-downs, if any. Production costs are exclusive of depreciation and depletion, reclamation, capital and exploration costs. TCC are net of by-product silver sales and are divided by gold ounces sold to arrive at a per ounce figure.

AISC per Ounce of Gold: AISC is a performance measure that reflects the total expenditures that are required to produce an ounce of gold from current operations. While there is no standardized meaning of the measure across the industry, the Company’s definition is derived from the definition as set out by the World Gold Council in its guidance dated June 27, 2013, and November 16, 2018, respectively. The World Gold Council is a non-regulatory, non-profit organization established in 1987 whose members include global senior mining companies. The Company believes that this measure is useful to external users in assessing operating performance and the ability to generate free cash flow from operations.

Calibre defines AISC as the sum of TCC, corporate general and administrative expenses (excluding one-time charges), reclamation accretion related to current operations and amortization of asset retirement obligations (“ARO”), sustaining capital (capital required to maintain current operations at existing production levels), lease repayments, and exploration expenditures designed to increase resource confidence at producing mines. AISC excludes capital expenditures for significant improvements at existing operations deemed to be expansionary in nature, exploration and evaluation related to resource growth, rehabilitation accretion not related to current operations, financing costs, debt repayments, and taxes. Total AISC is divided by gold ounces sold to arrive at a per ounce figure

Average Realized Price per Ounce Sold: Average Realized Gold Price Per Ounce Sold is intended to enable management to understand the average realized price of gold sold in each reporting period after removing the impact of non-gold revenues and by-produce credits, which in the Company’s case are not significant, and to enable investors to understand the Company’s financial performance based on the average realized proceeds of selling gold production in the reporting period. Average Realized Gold Price Per Ounce Sold is a common performance measure that does not have any standardized meaning. The most directly comparable measure prepared in accordance with IFRS is revenue from gold sales.

Adjusted Net Earnings: Adjusted Net Earnings and Adjusted Net Earnings Per Share - Basic exclude a number of temporary or one-time items considered exceptional in nature and not related to the Company’s core operation of mining assets or reflective of recurring operating performance. Management believes Adjusted Net Earnings may assist investors and analysts to better understand the current and future operating performance of the Company’s core mining business. Adjusted Net Earnings and Adjusted Net Earnings Per Share do not have a standard meaning under IFRS. They should not be considered in isolation, or as a substitute for measures of performance prepared in accordance with IFRS and are not necessarily indicative of earnings from mine operations, earnings, or cash flow from operations as determined under IFRS.

Cash From Operating Activities Before Changes in Working Capital: Cash from Operating Activities before Changes in Working Capital is a non-IFRS measure with no standard meaning under IFRS, which is calculated by the Company as net cash from operating activities less working capital items. The Company believes that Net Cash from Operating Activities before Changes in Working Capital, which excludes these non-cash items, provides investors with the ability to better evaluate the operating cash flow performance of the Company.

Net Debt and Adjusted Net Debt: The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use net debt to evaluate the Company’s performance. Net debt does not have any standardized meaning prescribed under IFRS, and therefore it may not be comparable to similar measures employed by other companies. This measure is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performances prepared in accordance with IFRS. Net debt is calculated as the sum of the current and non-current portions of loans and borrowings, net of the cash and cash equivalent balance as at the balance sheet date. Adjusted Net Debt is calculated as Net Debt less fair value and other non-cash adjustments that will not result in a cash outflow to the Company. The Company believes that Adjusted Net Debt provides a better understanding of the Company’s liquidity.

EBITDA and Adjusted EBITDA: The Company believes that certain investors use the EBITDA and the adjusted EBITDA (“Adjusted EBITDA”) measures to evaluate the Company’s performance and ability to generate operating cash flows to service debt and fund capital expenditures. EBITDA and Adjusted EBITDA do not have a standardized meaning as prescribed under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The Company calculates EBITDA as earnings or loss before taxes for the period excluding depreciation and depletion and finance costs. EBITDA excludes the impact of cash costs of financing activities and taxes and the effects of changes in working capital balances and therefore is not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Adjusted EBITDA is calculated by excluding one-off costs or credits relating to non-routine transactions from EBITDA that are not indicative of recurring operating performance. Management believes this additional information is useful to investors in understanding the Company’s ability to generate operating cash flow by excluding from the calculation these non-cash and cash amounts that are not indicative of the recurring performance of the underlying operations for the reporting periods.

Adjusted Net Debt to Adjusted EBITDA: The Adjusted Net Debt to Adjusted EBITDA measures provide investors and analysts with additional transparency about the Company’s liquidity position, specifically, the Company’s ability to generate sufficient operating cash flows to meet its mandatory interest obligations and pay down its outstanding debt balance in full at maturity. This measure is a Non-IFRS measure and it is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The calculation of Adjusted Net Debt is shown above.

TCC and AISC per Ounce of Gold Sold Reconciliations

The tables below reconcile TCC and AISC for the three months ended March 31, 2025, December 31, 2024, and March 31, 2024:

 Q1 2025
(in thousands - except per ounce amounts)NicaraguaNevadaCorporateConsolidated
Production costs$70,669 $10,900 $-$81,569 
Less: silver by-product revenue (2,595) (0) - (2,595)
Royalties and production taxes 7,578  805  - 8,383 
Total cash costs$75,652 $11,705 $-$87,357 


Corporate and general administration
 

-
  

-
  

6,073
 

6,093
 
Reclamation accretion and amortization of ARO 730  525  - 1,255 
Sustaining capital(1) 4,465  140  - 4,605 
Sustaining exploration 82  -  - 82 
Total AISC$80,930 $12,370 $6,073$99,372 
     
Gold ounces sold 64,469  7,076  - 71,545 
Total Cash Costs$1,173 $1,654 $-$1,221 
AISC$1,255 $1,748 $-$1,389 

1. Sustaining capital expenditures are shown in the Growth and Sustaining Capital table in the Q1 2025 MD&A.

  
  Q4 2024
(in thousands - except per ounce amounts) Nicaragua   Nevada   Corporate   Consolidated  
Production costs$77,823 $ 13,325 $ -$ 91,148 
Less: silver by-product revenue (3,465)  (28)  -  (3,493)
Royalties and production taxes 5,924   1,211   -  7,135 
Total cash costs$80,282 $ 14,508 $ -$ 94,790 


Corporate and general administration
 

-
   

-
   

5,394
  

5,394
 
Reclamation accretion and amortization of ARO 1,093   148   -  1,241 
Sustaining capital(1) 6,634   306   -  6,940 
Sustaining exploration 167   -   -  167 
Total AISC$88,176 $ 14,962 $ 5,394$ 108,532 


Gold ounces sold 66,578 9,674 - 76,252


Total Cash Costs


$


1,206


$


1,500


$


-


$


1,243
AISC$1,324$1,547$-$1,423

1. Sustaining capital expenditures are shown in the Growth and Sustaining Capital table in the Q1 2025 MD&A.

 Q1 2024
(in thousands - except per ounce amounts)NicaraguaNevadaCorporateConsolidated
Production costs$70,501 $9,646 $-$80,147 
Less: silver by-product revenue (2,671) (7) - (2,678)
Royalties and production taxes 4,193  560  - 4,753 
Refinery, transportation and other 366  37  - 403 
Total cash costs$72,389 $10,236 $-$82,625 


Corporate and general administration
 

-
  

-
  

4,525
 

4,525
 
Reclamation accretion and amortization of ARO 1,094  137  - 1,231 
Sustaining capital(1) 7,411  297  - 7,708 
Total AISC$80,894 $10,670 $4,525$96,089 
     
Gold ounces sold 55,007  6,771  - 61,778 


Total Cash Costs


$


1,316
 

$


1,512
 

$


-


$


1,337
 
AISC$1,471 $1,576 $-$1,555 
  1. Sustaining capital expenditures are shown in the Growth and Sustaining Capital table in the Q1 2025 MD&A.

(2) AVERAGE REALIZED GOLD PRICE PER OUNCE SOLD

The following table provides a reconciliation of Average Realized Gold Price Per Ounce Sold to gold revenue per the consolidated statement of operations and comprehensive income for the reporting periods:

 Three Months Ended
 March 31, 2025December 31, 2024March 31, 2024
Gold revenue (in thousands)$200,027$199,473$129,210
Ounces of gold sold 71,545 76,252 61,778
Average realized price per ounce sold (1)$2,796$2,616$2,092
  1. Average realized gold price per ounce sold includes 6,900 ounces in Q1 2025 (6,900 ounces in Q4, 2024 and nil ounces in Q1 2024) at $2,239 per ounce as delivered in accordance with the Prepay I Agreement.

(3) ADJUSTED NET EARNINGS

The following table provides a reconciliation of Adjusted Net Earnings and Adjusted Net Earnings Per Share to the consolidated statement of operations and comprehensive income for the reporting periods:

 Three Months Ended
(in thousands – except per share)March 31, 2025December 31, 2024March 31, 2024
Net earnings$22,599 $16,661$(3,636)
Adjusting items:   
  Foreign exchange (378) 16,516 - 
  Loss on financial instruments 10,108  115 - 
  Project assessment costs 6,299  885 8,933 
  Nicaragua one-time expenses -  1,209 - 
  Non-recurring finance expenses 1,509  - - 
  Mineral property write-off -  3,164 290 
Adjusted net earnings$40,137 $38,550$5,587 
Weighted average number of shares outstanding 848,747  838,038 653,855 
Adjusted net earnings per share - basic$0.05 $0.05$0.01 
  1. Adjusted from net earnings to derive Adjusted Net Earnings are one-time transaction costs primarily related to the Equinox Transaction and the acquisition of Marathon, foreign exchange impacts resulting from the translation of the Sprott Loan from US dollars to Canadian dollars, which is the functional currency of Marathon and the non-cash change in fair value of the Company’s gold derivative contracts. Notes Warrants and the derivative conversion option in the CAD Convertible Notes. See Note 18 in the Company’s Q1 2025 Financial Statements.

(4) CASH FROM OPERATING ACTIVITIES BEFORE CHANGES IN WORKING CAPITAL

The following table provides a reconciliation of Cash from Operating Activities before Changes in Working Capital to the consolidated statement of cash flows for the reporting periods:

 Three Months Ended
(in thousands)
March 31, 2025
December 31 2024
March 31, 2024   
Net cash provided by operating activities$53,476 $91,404 $45,815 
Working capital adjustments (1,599) (36,183) (17,047)
Cash from operating activities before working capital$55,074 $127,587 $62,862 


(5)
 NET DEBT and ADJUSTED NET DEBT

The following table provides a reconciliation of Net Debt and Adjusted Net Debt to the consolidated statement of financial position for the reporting periods:

(in thousands of dollars)March 31, 2025December 31, 2024March 31, 2024
Current portion of debt$68,376 $42,860 $11,915 
Non-current portion of debt 313,801  293,556  319,032 
Total Debt$382,177 $336,416 $330,947 
Less: Cash and cash equivalents (unrestricted) (177,385) (131,093) (54,385)
Net Debt$204,792 $205,323 $276,562 
Less: Fair value adjustment of Sprott Loan (40,122) (40,122) (35,108)
Adjusted Net Debt$164,670 $165,201 $241,454 


(6)
 EBITDA and ADJUSTED EBITDA

The following table provides a reconciliation of EBITDA and Adjusted EBITDA to the consolidated statement of operations and comprehensive income for the reporting periods:

 Three Months Ended
(in thousands)March 31, 2025December 31, 2024March 31, 2024
Earnings before taxes$46,337 $34,015 $7,465
Add back: Depreciation and amortization 33,370  40,324  17,328
Add back: Finance expense 3,519  (883) 1,686
EBITDA$83,226 $73,456  26,479
Add back: Non-cash and other adjustments (378) 16,423  1,618
Add back: Net loss on financial instruments 10,108  115  -
Add back: Project assessment costs 6,299  885  8,933
Add back: Nicaragua one-time expenses -  4,694  -
Add back: Non-recurring finance expenses 1,509  -  -
Add back: Mineral property write-off -  -  290
Adjusted EBITDA$100,764 $95,573 $37,320
  1. Adjusted from net earnings to derive adjusted net earnings are one-time transaction costs primarily related to the Equinox Transaction and the acquisition of Marathon, foreign exchange impacts resulting from the translation of the Sprott Loan from US dollars to Canadian dollars, which is the functional currency of Marathon and the non-cash change in fair value of the Company’s gold derivative contracts. Notes Warrants and the derivative conversion option in the CAD Convertible Notes. See Note 18 in the Company’s Q1 2025 Financial Statements. 

(7) ADJUSTED NET DEBT TO ADJUSTED EBITDA

The following table provides the reconciliation of Adjusted Net Debt to Adjusted EBITDA using the last twelve months of Adjusted EBITDA for the reporting periods:

(in thousands of dollars, except ratio)March 31, 2025December 31, 2024March 31, 2024
Adjusted Net Debt$164,670$165,201$241,454
Adjusted EBITDA (LTM) 262,569 215,827 225,330
Adjusted Net Debt to Adjusted EBITDA (LTM) ratio 0.63 0.77 1.07


Cautionary Note Regarding Forward Looking Information

This new release contains “forward-looking information” and “forward-looking statements” (collectively “forward-looking statements”) within the meaning of applicable Canadian securities legislation.

Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as “expect”, “plan”, “anticipate”, “project”, “target”, “potential”, “schedule”, “forecast”, “budget”, “estimate”, “assume”, “intend”, “strategy”, “goal”, “objective”, “possible” or “believe” and similar expressions or their negative connotations, or that events or conditions “will”, “would”, “may”, “could”, “should” or “might” occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made.

Forward-looking statements in this news release include, but are not limited to, the Company’s ability to achieve gold production, cost, development and exploration expectations for its operations and projects; the success and timing of completing construction of the Valentine Gold Mine (“Valentine”), its production and operating capabilities and the upside potential of Valentine; additional exploration success at Valentine; the initial project costs to complete Valentine; the phase two expansion project at Valentine proceeding in accordance with current expectations; the Company’s reinvestment into its existing portfolio of properties for further exploration and growth; statements relating to the Company’s priority resource expansion opportunities; statements regarding expectations for the combined entity ("New Equinox Gold") resulting from the business combination (the “Transaction”) of Calibre and Equinox Gold Corp. (“Equinox”) post-closing; the consummation and timing of the Transaction; the strategic vision for New Equinox Gold following the closing of the Transaction and expectations regarding exploration potential, production capabilities and future financial or operating performance of New Equinox Gold post-closing, including investment returns and share price performance; 2025 production and cost guidance; the potential valuation of New Equinox Gold following the closing of the Transaction; the accuracy of the pro forma financial position and outlook of New Equinox Gold following the closing of the Transaction; the success of the new management team; the conversion of Mineral Resource and Mineral Reserves; the success of Equinox and Calibre in combining operations upon closing of the Transaction; the potential of New Equinox Gold to meet production guidance, industry targets, public profile and expectations; and future plans, projections, objectives, estimates and forecasts and the timing related thereto. Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond Calibre's control. For a listing of risk factors applicable to the Company, please refer to Calibre's annual information form, its audited consolidated financial statements and its management discussion and analysis for the year ended December 31, 2024, and other disclosure documents of the Company filed on the Company’s SEDAR+ profile at www.sedarplus.ca.

Calibre’s forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date hereof. Calibre does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations or opinions should change other than as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, no assurance can be given that any events anticipated by the forward-looking statements will transpire or occur, or if any of them do, what benefits or liabilities Calibre will derive therefrom. For the reasons set forth above, undue reliance should not be placed on forward-looking statements.

Photos accompanying this announcement are available at: 

https://www.globenewswire.com/NewsRoom/AttachmentNg/11be9a24-a0c5-41b3-a835-9910d9fd8eb3

https://www.globenewswire.com/NewsRoom/AttachmentNg/1700c5fb-ed4e-41bb-aaa2-d71535fd6fe2


FAQ

What was Calibre Mining's (CXBMF) gold production in Q1 2025?

Calibre Mining produced 71,539 ounces of gold in Q1 2025, with 64,469 ounces from Nicaragua and 7,070 ounces from Nevada operations.

When is Calibre's Valentine Gold Mine expected to begin production?

The Valentine Gold Mine is expected to begin production by the end of Q3 2025, with full nameplate capacity expected to be reached in Q1 2026.

What is the new capital cost estimate for the Valentine Gold Mine project?

The updated initial project capital cost for Valentine is estimated at C$854 million, an increase of C$110 million from the October 2024 estimate of C$744 million.

When is the merger between Calibre Mining and Equinox Gold expected to close?

The merger between Calibre Mining and Equinox Gold is expected to close by the end of Q2 2025.

What was Calibre Mining's revenue and average gold price in Q1 2025?

Calibre Mining generated revenue of $200.0 million in Q1 2025, with an average realized gold price of $2,796 per ounce.