Evolution Metals & Technologies Corp. Announces Major 750 Megawatt Power Infrastructure Expansion to Scale Magnet Production to Approximately 10,000 Metric Tons Annually
Rhea-AI Summary
Evolution Metals & Technologies (Nasdaq: EMAT) has agreed principal terms with Korea Electric Power Corporation to expand electrical infrastructure for its Pohang, Korea operations from 130 MW to 750 MW, with a right of first refusal on additional capacity. Power availability is planned to align with facility expansion and ULVAC equipment installation in November 2026.
According to EM&T, the company plans to acquire about 1.3 million sq ft of adjacent land from Pohang City on a freehold basis and expand its magnet manufacturing footprint from 24,000 sq ft to 482,000 sq ft. Together with increased power and infrastructure, this is expected to support production of more than 10,000 metric tons of high-performance sintered and bonded magnets annually, in addition to planned U.S. capacity. EM&T has received conditional approval for an approximately US$20.7 million (₩28.3 billion) grant from Pohang City and Gyeongbuk Province, and KEPCO is expected to fund about 90% of substation, cabling and civil works costs.
Positive
- Power capacity increase from 130 MW to 750 MW for Pohang operations
- Manufacturing footprint expansion from 24,000 sq ft to 482,000 sq ft
- Land acquisition of approximately 1.3 million sq ft on a freehold basis
- Planned magnet output exceeding 10,000 metric tons annually in Pohang
- Conditional grant of about US$20.7 million (₩28.3 billion) for expansion
- KEPCO funding of roughly 90% of substation, cabling and civil works
Negative
- None.
News Explained
The Pohang expansion remains planned rather than completed: EM&T says the combined power, land, facilities, and equipment program is intended to increase magnet production from 1,000 tons to 10,000 tons by the end of 2026, while the property acquisition needed for the grant remains pending.
Market reaction after power infrastructure expansion: EMAT -5.65% in the Aug 27 session
In the Aug 27 session, EMAT declined 5.65%, reflecting a notable negative market reaction. Argus tracked a peak move of +5.2% during that session. Argus tracked a trough of -12.6% from its starting point during tracking. Our momentum scanner triggered 21 alerts that day, indicating elevated trading interest and price volatility. Trading volume was exceptionally heavy at 6.7x the daily average, suggesting significant selling pressure.
Data tracked by StockTitan Argus on the day of publication.
Key Figures
Historical Context
| Date | Event | Sentiment | 24h Move | Catalyst |
|---|---|---|---|---|
| Aug 24 | Index inclusion | Positive | +6.0% | Preliminary Russell 3000 and Russell 2000 inclusion effective September 21, 2026 |
| Aug 17 | Q2 earnings report | Neutral | -7.9% | Revenue began while reported losses and financing activity remained material |
| Aug 13 | Board appointment | Positive | +34.1% | Retired General Thomas A. Bussiere joined the board as an independent director |
| Mar 18 | Operations video | Positive | +5.5% | Corporate video showcased sintered and bonded magnet production operations |
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Three of four recent events had positive reactions, while the Q2 earnings event had a negative reaction amid mixed reported results.
Key Terms
right of first refusal regulatory
freehold basis regulatory
dfars regulatory
sintered magnets technical
AI-generated analysis. How Rhea-AI works. Not financial advice.
Agreement provides for expansion of electrical infrastructure serving EM&T’s Pohang operations from the current 130 MW capacity to 750 MW, a nearly six-fold increase in available power capacity
EM&T’s expansion in power, land, magnet manufacturing facilities and the recent magnet production equipment purchase are the essential infrastructure for EM&T to scale from 1,000 tons to 10,000 tons of rare earth magnet production by end 2026
EM&T’s Pohang magnet manufacturing expansion plans also include a larger manufacturing facility and additional land, and conditional approval of a connected
MIAMI, FL, Aug. 27, 2026 (GLOBE NEWSWIRE) -- Evolution Metals & Technologies Corp. (“EM&T” or the “Company”) (Nasdaq: EMAT), a U.S.-based critical materials and advanced manufacturing company, today announced that it has agreed to principal terms with its local power authority regarding a significant expansion of the electrical infrastructure supporting the Company’s operations in Pohang, Republic of Korea to approximately 750 megawatts, together with the planned expansion of its Pohang manufacturing facility, related land acquisitions and anticipated governmental financial grant of approximately US
Under the terms, the local power authority, Korea Electric Power Corporation (“KEPCO”), is expected to increase the electrical infrastructure serving EM&T’s Pohang operations from the current 130-megawatt (“MW”) capacity to a 750 MW capacity, with EM&T also having the right of first refusal with respect to additional available power capacity. This is expected to provide substantial additional power infrastructure to support the continued expansion of EM&T’s critical materials processing and rare earth permanent magnet manufacturing platform in Pohang, which is a natural location for EM&T’s expansion as Pohang is the center of Korea’s steel manufacturing industry. Following execution of the power supply documentation, the current implementation plan contemplates the power to be available upon EM&T’s facilities expansion and ULVAC equipment installation, planned for November 2026.
In connection with the planned expansion of its Pohang operations, EM&T plans to acquire approximately 1.3 million square feet of land adjacent to EM&T’s current Pohang operations through direct land acquisition from the Pohang City Government on a freehold basis. On this newly acquired land, EM&T intends to expand its existing magnet manufacturing facility footprint from 24,000 square feet to 482,000 square feet. The expanded facility is expected to accommodate EM&T’s additional rare earth permanent magnet manufacturing equipment, processing capacity and related infrastructure, including but not limited to, the ULVAC machinery currently set for delivery and installation in November 2026. EM&T’s planned expansion of the Pohang facility, together with the increased power availability and related infrastructure enhancements, will support EM&T’s production of more than 10,000 metric tons of high performance sintered and bonded magnets, in addition to the Company’s previously announced production capacity targets for its planned U.S. industrial campus.
EM&T has also received conditional approval for an approximate US
KEPCO is expected to fund approximately
“Securing access to power at this scale is a major strategic milestone for EM&T and, in our view, a meaningful competitive advantage,” said Frank Moon, Chief Executive Officer of EM&T. “This is an enormous amount of energy capacity. We also expect to benefit from extremely attractive power rates. Together, this gives us the infrastructure to continuously operate and materially scale our rare earth magnet manufacturing platform in Pohang and support additional high-value applications over time as we execute our expansion plans. The global markets are at a critical moment and the government of Korea and related public and private companies are stepping up big in our mission to reshape the current landscape as we move towards building a meaningful, reliable, and continuous supply chain for the Western world. We expect to continuously execute on our expansion timelines with a foundation of our existing operations, world class operators, and partners delivering power, land, and equipment.”
“With guidance led by US Government policy, we are executing,” David Wilcox, Executive Chairman of EM&T commented. “DFARS and tariff implementations are center stage. Large blocks of reliable power are becoming incredibly difficult to secure as demand for power accelerates across advanced manufacturing, artificial intelligence infrastructure, data centers and other power-intensive industries. With a combination of DFARS compliant material, commercial operating history, operators, inbound expansion equipment, permits, land, power and two allied countries, we have a recipe to permanently untangle supply chain dependency on China for rare earth permanent magnets. Our Board and Management team are led by U.S. defense veterans, world class operators, and visionaries that are determining the future of magnet production.”
About Evolution Metals & Technologies Corp.
Evolution Metals & Technologies Corp. (Nasdaq: EMAT) is a U.S.-based critical materials and advanced manufacturing company for rare earth permanent magnets, battery materials, and related critical minerals and technologies. By leveraging proven commercial-scale operations, advanced processing technologies, and strategic partnerships, EM&T operates what it believes is the only vertically integrated critical materials supply chain spanning end-of-life electronics and batteries, high-grade concentrates, and the manufacture of finished rare earth magnets (including high-performance rare earth magnets) and battery materials. For additional information, please visit https://investors.evolution-metals.com and follow the Company on LinkedIn.
Cautionary Note Regarding Forward-Looking Statements
This press release may contain forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, Section 21E of the Securities Exchange Act of 1934, as amended, and the United States Private Securities Litigation Reform Act of 1995. Forward-looking statements include, but are not limited to, statements regarding the contemplated expansion of electrical infrastructure supporting EM&T’s Pohang operations; the contemplated increase from 130 MW to 750 MW; the anticipated ability of the expanded electrical infrastructure to support continuous operation of EM&T’s Pohang facilities and planned expansion; anticipated infrastructure funding arrangements; expected power economics; completion of the Company’s land-use arrangements; the planned expansion of the Company’s Pohang manufacturing facility; the anticipated receipt, amount and use of governmental grants, incentives or other financial support; execution of applicable power supply documentation; and EM&T’s plans to expand its critical materials processing and permanent magnet manufacturing operations. These forward-looking statements, together with terms such as anticipate, expect, intend, may, will, should, believe, positioned and other comparable terms, involve risks and uncertainties because they relate to events and depend on circumstances that will occur in the future. Such risks include, among others, the Company’s ability to obtain the funding necessary to complete the applicable land-use arrangements; the Company’s ability to complete the applicable land-use arrangements and execute power supply documentation; changes in the contemplated terms of the power infrastructure arrangements; the ability of the applicable power provider and other counterparties to perform their obligations; changes in anticipated infrastructure costs, funding arrangements, power availability or pricing; the Company’s ability to complete its planned facility expansion; the availability and timing of governmental grants, incentives or other financial support and the Company’s ability to satisfy any conditions applicable thereto; infrastructure, engineering and construction delays; permitting and regulatory requirements; equipment delivery and commissioning; the Company’s ability to achieve contemplated production levels; financing, supply-chain and market risks; and the other risks described in EM&T’s filings with the U.S. Securities and Exchange Commission. Forward-looking statements are not guarantees of future performance, and actual results, performance or achievements may differ materially from those expressed or implied. Readers are cautioned not to place undue reliance on these statements, which speak only as of the date made. EM&T undertakes no obligation to update any forward-looking statement except as required by law. Additional information concerning factors that may affect EM&T’s expectations and projections is contained in its Annual Report on Form 10-K for the year ended December 31, 2025, filed with the SEC on February 20, 2026, its Quarterly Report on Form 10-Q for the three and six months ended June 30, 2026, filed with the SEC on August 17, 2026, including the disclosures under “Risk Factors” therein, and other documents filed or to be filed with the SEC by EM&T. SEC filings are available at www.sec.gov.
Investor Relations Contacts
Judith McGarry
Evolution Metals & Technologies Corp.
investor.relations@evolution-metals.com
Arx Investor Relations
North American Equities Desk
EMAT@arxhq.com