Energy Transfer and CloudBurst Sign Agreement for Natural Gas Supply to Data Center Project in Central Texas
Gas Supply Expected to Generate Up to 1.2 Gigawatts of Direct Power to AI-Focused Data Center
The agreement calls for Energy Transfer’s Oasis Pipeline, LP to provide up to 450,000 MMBtu per day of firm natural gas supply to CloudBurst’s Next-Gen Data Center campus outside of
This represents Energy Transfer’s first commercial arrangement to supply natural gas directly to a data center. Energy Transfer is uniquely positioned to provide reliable natural gas supply that is crucial to the data center operations under development, many of which are in close proximity to its vast network of more than 105,000 miles of natural gas gathering, and intrastate and interstate transportation pipelines and storage facilities with a combined storage capacity of nearly 236 billion cubic feet. Additionally, Energy Transfer is in discussions with a number of data center developers and expects this to be the first of many agreements to supply, store and transport natural gas to fuel data centers, electric generation facilities and other power demand customers throughout its nation-wide footprint.
“We are very excited about our close relationship with Energy Transfer and feel extremely confident in their ability to provide redundancy through their vast pipeline network and storage capacity. In addition, we will work closely with Energy Transfer to identify additional potential data center sites, on or close to their strategic natural gas pipeline network, using our proprietary site selection software,” said Cynthia Thompson Executive Chair, CloudBurst Data Centers, Inc.
About Energy Transfer
Energy Transfer LP (NYSE: ET) owns and operates one of the largest and most diversified portfolios of energy assets in
About CloudBurst
CloudBurst Data Centers, Inc., develops digital infrastructure powered by transition, green and renewable energy solutions with the aim of meeting the growing demand of the next generation (Next-Gen) of AI and data-led enterprises. Our mission is to build and operate AI/HDC, modular, Next-Gen Data Centers powered by the most economic energy solutions, but with an emphasis on being first to market offering Value, Reliability, Innovation, Service, Efficiency, Sustainability, and Security.
For more information, please visit CloudBurst’s website at www.cloudburstdc.com or contact Cynthia Thompson, Executive Chair, cthompson@cloudburstdc.com or Roy Davis, President, rdavis@cloudburstdc.com.
Forward-Looking Statements
This news release may include certain statements concerning expectations for the future that are forward-looking statements as defined by federal law. Such forward-looking statements are subject to a variety of known and unknown risks, uncertainties, and other factors that are difficult to predict and many of which are beyond management’s control. An extensive list of factors that can affect future results, including factors that may impact Energy Transfer’s operations, capital projects and future growth, are discussed in its Annual Report on Form 10-K and other documents filed from time to time with the Securities and Exchange Commission. Energy Transfer and CloudBurst undertake no obligation to update or revise any forward-looking statement to reflect new information or events.
The information contained in this press release is available on our website at energytransfer.com.
View source version on businesswire.com: https://www.businesswire.com/news/home/20250207943457/en/
Energy Transfer Contacts:
Media Relations
Vicki Granado or Jeff Tieszen
214-840-5820
media@energytransfer.com
Investor Relations
Bill Baerg, Brent Ratliff or Lyndsay Hannah
214-981-0795
CloudBurst Contacts:
Cynthia Thompson
Executive Chair & CBDO,
cthompson@cloudburstdc.com
713-443-7170
Roy Davis, President & CMO
rdavis@cloudburstdc.com
702-358-3929
Source: Energy Transfer LP