STOCK TITAN

Notifications

Limited Time Offer! Get Platinum at the Gold price until January 31, 2026!

Sign up now and unlock all premium features at an incredible discount.

Read more on the Pricing page

Endeavour Silver provides a Q2 2024 construction progress update on Terronera; the surface construction progress has reached 77% completion

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

Endeavour Silver Corp. (NYSE: EXK; TSX: EDR) has provided a Q2 2024 construction update for its Terronera Project in Jalisco, Mexico. The project has reached 64.5% overall completion, with surface construction at 77%. Key highlights include:

- Commissioning remains on track for Q4 2024
- $204 million spent to date, with $260 million committed out of $271 million budget
- Upper Platform Plant Site is 88% complete
- Underground development totals nearly 4,500 meters
- Workforce increased to over 190 Endeavour employees and 700 contractors

The project's critical path includes the Tailing Storage Facility, Lower Platform construction, and underground mine advancement. Endeavour is also implementing a business readiness plan for operating its next core asset.

Loading...
Loading translation...

Positive

  • Project remains on schedule for Q4 2024 commissioning
  • Overall project progress reached 64.5% completion
  • Surface mill and infrastructure construction is 88% complete
  • Underground development totals nearly 4,500 meters
  • Workforce expanded to over 890 employees and contractors

Negative

  • Environmental and social impact assessment delayed by 3 months
  • Lower Platform excavation only 50% complete, potentially affecting timeline
  • Temporary power to be used for initial commissioning, indicating potential delays in permanent power infrastructure

Insights

Endeavour Silver's Q2 2024 progress update on the Terronera Project is pivotal for investors. The project has reached 64.5% completion with $204 million already spent, indicating strong commitment and significant advancement. Financially, nearly $260 million of the $271 million budget has been committed, leaving only a small margin for cost overruns. The fact that the project is on track for Q4 2024 commissioning suggests that the timeline is being managed effectively, which can instill confidence in shareholders. This level of detail in financial planning and expenditure tracking is crucial, as it provides transparency and demonstrates managerial efficiency, ultimately building investor trust. The relatively minor delay in environmental and social impact assessments (3 months) should be monitored but is not currently alarming.

The technological advancements and infrastructural progress reported by Endeavour Silver on the Terronera Project are noteworthy. The mechanical installations, including the completion of the structural and mechanical construction of primary facilities like the Upper Platform and Primary Crusher, showcase effective project management and technological implementation. The installation of advanced equipment such as the SAG and ball mills, along with ongoing piping and electrical work, highlights the project's readiness for the next phases. This structured approach to technology deployment ensures minimal downtime and operational efficiency upon commissioning. The focus on critical path purchases for electrical components and reducing bulk material lead times further underscores the project’s strong logistical and supply chain management.

From a market perspective, Endeavour Silver’s update on the Terronera Project is significant. The articulated progress, especially the 77% completion of surface construction, aligns well with market expectations for project timelines. The attention to community relations and environmental stewardship signals a commitment to corporate social responsibility, which can enhance the company’s reputation and appeal to ESG-focused investors. The active engagement in local workforce training programs and the establishment of business support services reflect a forward-thinking strategy that can yield long-term community support and stability in operations. These factors collectively strengthen Endeavour Silver's market position and can positively influence stock performance as the project approaches its completion.

VANCOUVER, British Columbia, July 24, 2024 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q2 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos. All dollar ($) references in this news release are United States dollars.

The Terronera project continued to make significant progress in the second quarter, as concrete and structural steel work are nearing completion on the Upper Plant Platform for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. The Project remains on track for commissioning in Q4 2024 as major mechanical installations continued to advance on schedule.

"Construction is well past the halfway mark, and site activities are beginning to peak," commented Don Gray, Chief Operating Officer. "We are very pleased with the advance at the Upper Platform, which should be ready for dry commissioning in Q3 2024. We are concentrating resources on the Lower Platform to finalize earthworks and begin concrete works in early Q3. Underground mine development continues advancing in line with expectations as we accessed ore in Q2. We are extremely pleased with our Terronera team and their progress. With project completion in sight, our focus has expanded to implementing our business readiness plan as we prepare for operating Endeavour's next core asset."

Q2 2024 Construction and Development Highlights

As of June 30, 2024, site works and activities included:

  • Safety – The highest workplace priority is the health and safety of our employees and contractors, with a commitment to provide the tools, training, and resources needed to identify risks and apply effective controls. Recently, underground operations increased rescue brigade participation by 40%, and two self-contained mine refuge stations were installed.
  • Progress – Overall project progress (mine development and surface construction) reached 64.5% completion, with more than $204 million (1) of the project's budget spent to date. Project commitments total $260 million (1,2), 96% of the $271 million capital budget.
  • Engineering – Efforts have transitioned to construction support. During the quarter, a detailed design was completed for the tailing storage facility, Portal 2 waste dump, and the Lower Platform excavation.
  • Mine Development – Over the quarter, over 1,270 meters were developed underground, totaling nearly 4,500 meters.
  • Upper Platform Plant Site – Surface mill and infrastructure construction is 88% complete and progressing on schedule. Concrete work and structural steel erection are 100% complete.
    • Primary Crusher – Structural and mechanical construction is complete on the conveyor and apron feeder support steel, and the apron feeder was placed in position. Conveyors are belted, and belts vulcanized. Cabling and terminations are ongoing.
    • Coarse Ore Stockpile and Reclaim ("COS") Tunnel – SAG Feed Conveyor and belt were installed. Piping, electrical, and instrumentation are ongoing.
    • Grinding – SAG and ball mill are installed. Piping, mechanical, electrical, and instrumentation are ongoing.
    • Flotation – Piping, mechanical, electrical, and instrumentation are ongoing. Flotation equipment, including blowers, instruments, and valves, is expected to be procured in early Q3.
    • Tailing Thickener – The Tailings thickener is complete and signed off. Some steel modifications, such as piping, mechanical, electrical, and instrumentation, are ongoing. Procurement monitoring of some equipment (tanks), instruments, and valves is ongoing.
  • Lower Facilities Platform and Tailing Storage Facility – Excavation for the tailing storage facility embankment key trench was over 95% complete, and the Lower Platform area was nearly 50% complete. Concrete work on the lower platform is scheduled to start in early Q3.
  • Procurement – Bulk materials purchase orders have been released, and lead times are aligned with the current schedule. The Procurement team has focused on critical path purchases, such as electrical components and transfer chutes, and reducing bulk material lead times to increase schedule float.
  • Onsite Personnel – At the end of Q2, the workforce increased to over 190 Endeavour employees and over 700 contractor workers.
  • Community Relations – Local community support continues to be a major commitment. A plant-operator training program for local community members has been established. The Company is also preparing a comprehensive training and support services plan for groups and individuals seeking to form businesses that can provide local goods and services.
  • Environmental – Environmental and social impact assessment initiatives continue and will be presented in early Q3 (July 2024), with a 3-month delay compared to the schedule outlined under the Equator Principles requirements for project loan financing.

Next Steps and Planning

The Terronera Project remains on track for commissioning in Q4 2024.

For Q3 2024, surface construction will continue to focus on mechanical, piping, and electrical installations. Completing the Lower Platform excavation is anticipated to be no later than mid-Q3 2024. Concrete work for the tailing and concentrate filtration areas is expected to begin in early Q3 2024, with the LNG and power generation areas to follow. The Company anticipates commissioning using temporary power with the LNG and power generation to be operational subsequent to commissioning. The temporary power has been planned and is expected to be available for Q4. Concentrate and tailing filtration structural, mechanical, and electrical installations will commence as concrete work is completed.

Mine development in Portals 1, 2, and 4 declines will continue, with a test long-hole stop being developed in Q3 2024. Initial long-hole production is planned for early Q4, followed by cut-and-fill mining; ore will be stockpiled for mill ramp-up. At La Luz, development activities are anticipated to begin in Q3, with the portal being constructed and the ramp to ore access being advanced in Q4.

The critical path remains the TSF, Lower Platform construction, and the advancing underground mine.

Visit www.terronera.com, our dedicated project website, to stay informed on the ongoing development at Terronera. Explore updates, learn about our commitment to environmental stewardship, and discover the positive impacts on local communities.

About Endeavour Silver: Endeavour is a mid-tier precious metals company committed to sustainable and responsible mining practices. With operations in Mexico and the development of the new cornerstone mine in Jalisco State, the Company aims to contribute positively to the mining industry and the communities in which it operates. In addition, Endeavour has a portfolio of exploration projects in Mexico, Chile, and the United States, which has helped it achieve its goal of becoming a premier senior silver producer. 

Contact Information

Allison Pettit, Director of Investor Relations
Tel: (604) 640 4804
Email: apettit@edrsilver.com
Website: www.edrsilver.com

Follow Endeavour Silver on Facebook, X, Instagram and LinkedIn

Footnote:

  1. Financial figures are based on a preliminary estimate. Final unaudited figures will be released with the Q2 2024 financial statements on August 1, 2024.
  2. Project commitments include total project expenditures.

Cautionary Note Regarding Forward-Looking Statements

This news release contains "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding the development and financing of the Terronera Project, including capital cost estimates, the anticipated timing of the project construction, Terronera's forecasted operations, costs and expenditures, and the timing and results of various related activities. The Company does not intend to and does not assume any obligation to update forward-looking statements or information other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties, and other factors that may cause Endeavor's actual results, level of activity, production levels, performance, or achievements, and its operations to be materially different from those expressed or implied by such statements. Such factors include but are not limited changes in production and costs guidance; the ongoing effects of inflation and supply chain issues on mine economics; national and local governments, legislation, taxation, controls, regulations and political or economic developments in Canada, Chile, the USA and Mexico; financial risks due to precious metals prices; operating or technical difficulties in mineral exploration, development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature of mineral exploration and development; risks in obtaining necessary licenses and permits; satisfaction of conditions precedent to drawdown under the project loan debt facility; the ongoing effects of inflation and supply chain issues on the Terronera Project economics; fluctuations in the prices of silver and gold, fluctuations in the currency markets (particularly the Mexican peso, Chilean peso, Canadian dollar and US dollar); and challenges to the Company's title to properties; as well as those factors described in the section "risk factors" contained in the Company's most recent form 40F/Annual Information Form filed with the SEC and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to the continued operation of the Company's mining operations, no material adverse change in the market price of commodities forecasted Terronera mine economics as of 2024, mining operations will operate, and the mining products will be completed under management's expectations and achieve their stated production outcomes, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or information, other factors may cause results to be materially different from those anticipated, described, estimated, assessed, or intended. There can be no assurance that any forward-looking statements or information will be accurate, as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.


FAQ

What is the current completion percentage of Endeavour Silver's Terronera Project (EXK)?

As of Q2 2024, Endeavour Silver's Terronera Project (EXK) has reached 64.5% overall completion, with surface construction at 77% completion.

When is the expected commissioning date for Endeavour Silver's Terronera Project (EXK)?

Endeavour Silver's Terronera Project (EXK) remains on track for commissioning in Q4 2024.

How much of the Terronera Project budget has been spent by Endeavour Silver (EXK) as of Q2 2024?

As of Q2 2024, Endeavour Silver (EXK) has spent over $204 million of the Terronera Project's $271 million capital budget, with total commitments of $260 million.

What is the current status of underground development at Endeavour Silver's Terronera Project (EXK)?

As of Q2 2024, underground development at Endeavour Silver's Terronera Project (EXK) totals nearly 4,500 meters, with over 1,270 meters developed in the second quarter alone.
Endeavour Sil

NYSE:EXK

EXK Rankings

EXK Latest News

EXK Latest SEC Filings

EXK Stock Data

2.54B
293.54M
0.19%
50.55%
9.81%
Silver
Basic Materials
Link
Canada
Vancouver