First Mining Intersects 7.18 g/t Au over 8 m at the Miroir Target and Provides Duparquet Project Update
Rhea-AI Summary
First Mining (OTCQX: FFMGF) reported results from its 2025 Duparquet drilling and an update on project work. The company completed 16,577 m of drilling in 2025 and extended the Miroir target to a vertical depth of 250 m. Key intercepts include 3.74 g/t Au over 15.5 m, 7.18 g/t over 8.0 m (incl. 30.58 g/t over 1.65 m), and 1.56 g/t over 33.15 m. First Mining also commenced a comprehensive environmental baseline program to support regulatory progress and plans further 2026 drilling focused on resource growth targets.
Positive
- Completed 16,577 m of drilling in 2025, expanding dataset
- Miroir extended to a vertical depth of 250 m, +150 m down-dip expansion
- Multiple high-grade intercepts: 30.58 g/t Au over 1.65 m and 11.20 g/t Au over 1.0 m
- Environmental baseline program started to support regulatory approvals and feasibility work
Negative
- None.
News Market Reaction – FFMGF
On the day this news was published, FFMGF gained 2.19%, reflecting a moderate positive market reaction.
Data tracked by StockTitan Argus on the day of publication.
- DUP25-085 returns 3.74 g/t Au over 15.5 m and 7.18 g/t over 8.0 m, including 30.58 g/t over 1.65 m
- DUP25-081 returns 1.56 g/t Au over 33.15 m, including 3.18 g/t Au over 7.6 m
- DUP25-090 returns 4.08 g/t Au over 12.0 m, including 11.20 g/t Au over 1.0 m, extending mineralization to vertical depth of 250 m
Assay results from drill hole DUP25-081 have returned 1.56 g/t Au over 33.15 m, including 3.18 g/t Au over 7.60 m. Drill hole DUP25-085 returned 3.74 g/t Au over 15.5 m and 7.18 g/t over 8.0 m, including 30.58 g/t over 1.65 m. DUP25-090 returned 4.08 g/t Au over 12.0 m, including 11.20 g/t Au over 1.0 m. Drilling at the Miroir target has continuously been building potential for a strong resource growth zone returning multiple robust gold intercepts, and it will be a key target to advance in the 2026 drilling campaign.
"The results from our 2025 drilling program at
Duparquet Project Update
First Mining is pleased announce that it has commenced a comprehensive environmental baseline data collection program at the Duparquet Project to support the information requirements to complete the regulatory approvals process for the Project. The program is led by First Mining's in-house Sustainability team and supported by Stantec, who both have significant related experience from the successful development of the Greenstone Gold Mine, which recently commenced production in
The baseline programs cover all areas of the environment starting with geochemistry and water quality, through to aquatic studies and other biophysical aspects required to advance Project planning. First Mining continues its engagement and collaboration with the
Exploration Program Update and Outlook
Drilling activities at the Duparquet Project concluded in October 2025, with a total of 16,577 m completed during the year. While all assays from the 2025 drilling program have been received, outstanding results and interpretations will be disclosed in a future update as ongoing integration and modelling work continues.
The Company is currently reviewing and incorporating the 2025 data into updated geological and exploration target models. In parallel, the 2026 exploration program is being finalized, with a targeted commencement in Q2 2026. Planned drilling will focus on high-priority targets, including Miroir, to further advance its potential as a key resource expansion opportunity.
Additional Drilling Details
Further highlights from the latest drilling results disclosed herein are from the Valentre target area (Figure 2). Drill hole DUP25-074 returned 1.92 g/t Au over 9.3 m, including 2.80 g/t Au over 4.8 m, and DUP25-083 returned 4.26 g/t Au over 3.5 m and 2.41 g/t Au over 10.95 m. The latest results continue to demonstrate the continuity of the CVD target area, with the target currently extending to 480 m below surface and remaining open at depth.
Two additional greenfields exploration targets, Normandie and Lumière, were drill tested in 2025 with a program (Figure 2) targeting geophysical anomalies hosted along favourable lithological contacts. Normandie, a geophysically interpreted structure located 150 m towards the northeast along strike from Miroir, returned 1.39 g/t Au over 4.0 m and 5.22 g/t Au over 1.0 m in DUP25-068, highlighting a favourable area for gold mineralization and further geological modelling and drill testing. Drilling at the Lumière target, located ~300 m northwest of Miroir, returned 7.74 g/t Au over 1.40 m as well as 2.23 g/t Au over 1.50 m near surface in drill hole DUP25-086, successfully demonstrating the presence of favourable mineralization and once further modelled, a favourable target for follow up drilling.
The latest reported assays represent approximately 2,550 m of drilling from a total of ~5,000 m across 22 drill holes drilled to date at the Miroir target. These holes were focused on advancing the understanding of mineralization controls at Miroir and extending the target depth while testing the down-dip potential. Assay highlights are provided in Table 1, with the full list of assay results presented in Table 3 and drill collar details in Table 4. All assay results from this target's drilling have now been disclosed.
Hole ID | From (m) | To (m) | Length (m) | Grade (Au g/t) | Target | |
DUP25-066 | 191.2 | 193.0 | 1.8 | 6.08 | Miroir | |
DUP25-066 | including | 192.0 | 193.0 | 1.0 | 8.53 | Miroir |
DUP25-066 | 197.5 | 202.0 | 4.5 | 1.23 | Miroir | |
DUP25-068 | 19.0 | 23.0 | 4.0 | 1.39 | Normandie | |
DUP25-068 | 77.4 | 78.4 | 1.0 | 5.22 | Normandie | |
DUP25-074 | 214.4 | 223.7 | 9.3 | 1.92 | Valentre | |
DUP25-074 | including | 218.9 | 223.7 | 4.8 | 2.80 | Valentre |
DUP25-081 | 12.1 | 14.15 | 2.05 | 2.57 | Miroir | |
DUP25-081 | 19.0 | 28.8 | 9.8 | 1.13 | Miroir | |
DUP25-081 | 128.4 | 148.7 | 20.30 | 0.61 | Miroir | |
DUP25-081 | 154.7 | 156.35 | 1.65 | 3.17 | Miroir | |
DUP25-081 | 196.9 | 206.5 | 9.6 | 1.53 | Miroir | |
DUP25-081 | 223.7 | 256.85 | 33.15 | 1.56 | Miroir | |
DUP25-081 | including | 243.7 | 251.3 | 7.6 | 3.18 | Miroir |
DUP25-081 | 276.6 | 277.5 | 0.9 | 7.54 | Miroir | |
DUP25-083 | 509.0 | 512.5 | 3.5 | 4.26 | Valentre | |
DUP25-083 | 523.65 | 534.6 | 10.95 | 2.41 | Valentre | |
DUP25-084 | 86.7 | 89.0 | 2.3 | 2.39 | Miroir | |
DUP25-084 | 184.0 | 213.0 | 29.0 | 1.47 | Miroir | |
DUP25-084 | 229.0 | 237.0 | 8.0 | 3.28 | Miroir | |
DUP25-084 | including | 235.0 | 236.0 | 1.0 | 18.20 | Miroir |
DUP25-084 | 245.0 | 255.0 | 10.0 | 1.83 | Miroir | |
DUP25-084 | including | 245.0 | 246.0 | 1.0 | 9.58 | Miroir |
DUP25-085 | 53.0 | 68.5 | 15.5 | 3.74 | Miroir | |
DUP25-085 | 148.0 | 156.0 | 8.0 | 7.18 | Miroir | |
DUP25-085 | including | 153.35 | 155.0 | 1.65 | 30.58 | Miroir |
DUP25-086 | 9.5 | 10.9 | 1.4 | 7.74 | Lumière | |
DUP25-087 | 41.0 | 46.25 | 5.25 | 3.35 | Miroir | |
DUP25-087 | including | 43.0 | 43.55 | 0.55 | 20.50 | Miroir |
DUP25-087 | 79.25 | 86.4 | 7.15 | 0.85 | Miroir |
Additional Details on Miroir, CVD, Aiguille, Lumière, and Normandie Drilling
Miroir
The 2025 drilling at the Miroir target focused on further delineating the extent of near-surface mineralization discovered in 2024. A series of significant intercepts have been returned at Miroir to date (Table 2), with the most recent drilling continuing to confirm and expand the target area, extending mineralization to a vertical depth of 250 m below surface and highlighting multiple near-surface gold zones.
Notable results from the most recent drilling include drill hole DUP25-081 returning 1.56 g/t Au over 33.15 m, including 3.18 g/t Au over 7.60 m. Drillhole DUP25-085 returned 3.74 g/t Au over 15.5 m and 7.18 g/t over 8.0 m, including 30.58 g/t over 1.65 m, and DUP25-090 returned 4.08 g/t Au over 12.0 m, including 11.20 g/t Au over 1.0 m. These results continue to demonstrate the potential for multiple, high-quality gold zones within the Miroir target and reinforce its potential for further growth.
Drill Hole | Highlight Interval | Disclosure Date | |
DUP24-048 | 3.12 g/t Au over 19.35 m | January 20, 2025 | |
DUP25-052 | 2.77 g/t Au over 11.1 m, including 4.36 g/t Au over 6.5 m | May 28, 2025 | |
DUP25-064 | 3.23 g/t Au over 25.9 m, including 11.20 g/t Au over 2.0 m, and including 10.16 g/t Au over 1.4 m | September 24, 2025 | |
DUP25-078 | 2.01 g/t Au over 29.8 m, including 15.70 g/t Au over 0.75 m and 18.20 g/t Au over 1.0 m | November 10, 2025 |
High-grade mineralization at the Miroir target is associated with coincident brittle and ductile deformation within a volcanic package proximal to syenite contacts. Mineralized intercepts are spatially correlated with northeast–southwest–striking D2 deformation zones, coincident with a geophysically inferred basalt–syenite contact that plunges to the east.
In the most recent drill holes, mineralization is hosted within brecciated, silica-altered basalt and syenite, with 2–
Valentre
The 2025 drilling program further confirmed the continuity of the mineralization at the Valentre target and the latest notable results from the most recent drilling include drill hole DUP25-074 returning 1.92 g/t Au over 9.3 m, including 2.80 g/t Au over 4.8 m, and DUP25-083 returning 4.26 g/t Au over 3.5 m and 2.41 g/t Au over 10.95 m. The results continue to demonstrate the continuity of the Valentre target which currently extends to 480 m below surface and remains open at depth.
Gold mineralization at the Central Duparquet-Valentre-Dumico ("CVD") area is hosted within mineralized silica- and sericite-altered syenite units with very fine-grained disseminated pyrite ranging from 0.5-
Aiguille
In the 2025 drilling campaign, the up-dip and along-strike opportunities at the Aiguille target were investigated with a sequence of shallow drill holes, targeting a key geological contact to further enhance the resolution for modelling the extent of mineralization. Drill hole DUP25-071 returned 0.62 g/t Au over 1.0 m and DUP25-074 returned 0.48 g/t Au over 1.0 m. These holes successfully demonstrated anomalous gold values in key structures. The down-dip potential of the target continues to remain open at depth and will be validated with further drilling.
Normandie
The Normandie target, located 150 m northeast of Miroir, is a geophysical anomaly interpreted as a structural corridor linking the Miroir target with the greenfield Sid target (see press release dated February 22, 2024). Drilling in 2025 successfully intersected high-grade brecciated and shear-style veining along the syenite–volcanic contact, with hole DUP25-068 returning 1.39 g/t Au over 4.0 m and 5.22 g/t Au over 1.0 m. This maiden drill hole at Normandie validated the geological interpretation, demonstrating geological continuity and a favourable mineralization setting between the Miroir and Sid targets. Follow-up drilling will focus on testing the mineralization footprint along strike and down-dip.
Lumière
The Lumière target, located approximately 300 m northwest of Miroir (Figure 2), was drill tested in 2025, with hole DUP25-086 returning 7.74 g/t Au over 1.4 m and 2.23 g/t Au over 1.5 m near surface. Drilling targeted a geophysical anomaly and syenite–volcanic contacts along the northern margin of the syenite body.
High-grade gold values are associated with brecciated and sheared volcanic units with fracture-controlled silica alteration. Structural and geochemical interpretations will be integrated to update the 3D geological model along the contact and identify priority areas for follow-up drilling.
Drill Hole | From (m) | To (m) | Length (m) | Grade (Au g/t) | Target | |
DUP25-066 | 191.2 | 193.0 | 1.8 | 6.08 | Miroir | |
DUP25-066 | including | 192.0 | 193.0 | 1.0 | 8.53 | Miroir |
DUP25-066 | 197.5 | 202.0 | 4.5 | 1.23 | Miroir | |
DUP25-066 | 213.0 | 219.5 | 6.5 | 0.62 | Miroir | |
DUP25-066 | 228.7 | 229.7 | 1.0 | 0.73 | Miroir | |
DUP25-066 | 274.5 | 275.0 | 0.5 | 5.12 | Miroir | |
DUP25-068 | 19.0 | 23.0 | 4.0 | 1.39 | Normandie | |
DUP25-068 | 77.4 | 78.4 | 1.0 | 5.22 | Normandie | |
DUP25-071 | 147.0 | 148.0 | 1.0 | 0.62 | Aiguille | |
DUP25-072 | no significant mineralization | |||||
DUP25-073 | 56.0 | 57.0 | 1.0 | 0.46 | Aiguille | |
DUP25-073 | 121.0 | 122.0 | 1.0 | 0.47 | Aiguille | |
DUP25-074 | 46.0 | 47.0 | 1.0 | 0.46 | Valentre | |
DUP25-074 | 60.0 | 61.0 | 1.0 | 0.66 | Valentre | |
DUP25-074 | 106.3 | 106.95 | 0.65 | 0.52 | Valentre | |
DUP25-074 | 111.05 | 111.95 | 0.9 | 4.99 | Valentre | |
DUP25-074 | 155.0 | 156.0 | 1.0 | 0.42 | Valentre | |
DUP25-074 | 159.25 | 160.0 | 0.75 | 0.69 | Valentre | |
DUP25-074 | 163.0 | 165.0 | 2.0 | 0.58 | Valentre | |
DUP25-074 | 168.6 | 169.3 | 0.7 | 0.40 | Valentre | |
DUP25-074 | 214.4 | 223.7 | 9.3 | 1.92 | Valentre | |
DUP25-074 | including | 218.9 | 223.7 | 4.8 | 2.80 | Valentre |
DUP25-074 | 405.3 | 406.25 | 0.95 | 0.46 | Aiguille | |
DUP25-074 | 411.0 | 412.0 | 1.0 | 0.48 | Aiguille | |
DUP25-081 | 7.0 | 8.0 | 1.0 | 0.71 | Miroir | |
DUP25-081 | 12.1 | 14.15 | 2.05 | 2.57 | Miroir | |
DUP25-081 | including | 12.1 | 12.65 | 0.55 | 7.77 | Miroir |
DUP25-081 | 19.0 | 28.8 | 9.8 | 1.13 | Miroir | |
DUP25-081 | 83.0 | 83.85 | 0.85 | 0.49 | Miroir | |
DUP25-081 | 103.2 | 107.0 | 3.8 | 0.46 | Miroir | |
DUP25-081 | 128.4 | 148.7 | 20.3 | 0.61 | Miroir | |
DUP25-081 | 144.0 | 146.9 | 2.9 | 0.45 | Miroir | |
DUP25-081 | 147.85 | 148.7 | 0.85 | 1.08 | Miroir | |
DUP25-081 | 154.7 | 156.35 | 1.65 | 3.17 | Miroir | |
DUP25-081 | 168.35 | 169.2 | 0.85 | 2.30 | Miroir | |
DUP25-081 | 192.0 | 193.0 | 1.0 | 0.56 | Miroir | |
DUP25-081 | 196.9 | 206.5 | 9.6 | 1.53 | Miroir | |
DUP25-081 | 223.7 | 256.85 | 33.15 | 1.6 | Miroir | |
DUP25-081 | including | 243.7 | 251.3 | 7.6 | 3.18 | Miroir |
DUP25-081 | 276.6 | 277.5 | 0.9 | 7.54 | Miroir | |
DUP25-081 | 281.25 | 281.75 | 0.5 | 1.33 | Miroir | |
DUP25-081 | 296.0 | 297.0 | 1.0 | 0.72 | Miroir | |
DUP25-081 | 307.2 | 308.0 | 0.8 | 0.46 | Miroir | |
DUP25-082 | 70.55 | 72.0 | 1.45 | 0.72 | Miroir | |
DUP25-082 | 110.75 | 111.35 | 0.6 | 0.78 | Miroir | |
DUP25-082 | 214.9 | 215.4 | 0.5 | 0.56 | Miroir | |
DUP25-083 | 123.0 | 124.0 | 1.0 | 1.37 | Miroir | |
DUP25-083 | 287.0 | 288.0 | 1.0 | 0.42 | Valentre | |
DUP25-083 | 318.0 | 319.0 | 1.0 | 0.53 | Valentre | |
DUP25-083 | 336.0 | 337.0 | 1.0 | 0.58 | Valentre | |
DUP25-083 | 351.3 | 358.0 | 6.7 | 2.07 | Valentre | |
DUP25-083 | 361.55 | 366.0 | 4.45 | 0.62 | Valentre | |
DUP25-083 | 373.0 | 376.0 | 3.0 | 0.48 | Valentre | |
DUP25-083 | 381.0 | 383.0 | 2.0 | 0.47 | Valentre | |
DUP25-083 | 427.5 | 428.2 | 0.7 | 0.40 | Valentre | |
DUP25-083 | 488.0 | 489.0 | 1.0 | 1.28 | Valentre | |
DUP25-083 | 509.0 | 512.5 | 3.5 | 4.26 | Valentre | |
DUP25-083 | 523.65 | 534.6 | 10.95 | 2.41 | Valentre | |
DUP25-083 | 564.0 | 565.0 | 1.0 | 1.45 | Valentre | |
DUP25-083 | 573.25 | 575.0 | 1.75 | 2.39 | Valentre | |
DUP25-084 | 16.0 | 18.0 | 2.0 | 0.51 | Miroir | |
DUP25-084 | 25.3 | 26.3 | 1.0 | 0.57 | Miroir | |
DUP25-084 | 39.0 | 44.0 | 5.0 | 0.75 | Miroir | |
DUP25-084 | 59.3 | 59.8 | 0.5 | 0.49 | Miroir | |
DUP25-084 | 63.2 | 65.7 | 2.5 | 1.01 | Miroir | |
DUP25-084 | 68.2 | 69.5 | 1.3 | 0.81 | Miroir | |
DUP25-084 | 86.7 | 89.0 | 2.3 | 2.39 | Miroir | |
DUP25-084 | 103.5 | 104.0 | 0.5 | 0.72 | Miroir | |
DUP25-084 | 130.0 | 130.5 | 0.5 | 1.83 | Miroir | |
DUP25-084 | 159.0 | 164.7 | 5.7 | 0.60 | Miroir | |
DUP25-084 | 184.0 | 213.0 | 29.0 | 1.47 | Miroir | |
DUP25-084 | 229.0 | 237.0 | 8.0 | 3.28 | Miroir | |
DUP25-084 | including | 235.0 | 236.0 | 1.0 | 18.20 | Miroir |
DUP25-084 | 245.0 | 255.0 | 10.0 | 1.83 | Miroir | |
DUP25-084 | including | 245.0 | 246.0 | 1.0 | 9.58 | Miroir |
DUP25-085 | 13.5 | 14.3 | 0.8 | 0.43 | Miroir | |
DUP25-085 | 22.8 | 24.3 | 1.5 | 0.66 | Miroir | |
DUP25-085 | 33.6 | 35.0 | 1.4 | 1.08 | Miroir | |
DUP25-085 | 45.75 | 47.0 | 1.25 | 1.94 | Miroir | |
DUP25-085 | 53.0 | 68.5 | 15.5 | 3.74 | Miroir | |
DUP25-085 | 76.0 | 76.8 | 0.8 | 0.46 | Miroir | |
DUP25-085 | 78.4 | 80.35 | 1.95 | 3.94 | Miroir | |
DUP25-085 | 85.1 | 90.9 | 5.8 | 2.95 | Miroir | |
DUP25-085 | 137.0 | 138.0 | 1.0 | 1.21 | Miroir | |
DUP25-085 | 148.0 | 156.0 | 8.0 | 7.18 | Miroir | |
DUP25-085 | including | 153.35 | 155.0 | 1.65 | 30.58 | Miroir |
DUP25-086 | 9.5 | 10.9 | 1.4 | 7.74 | Lumière | |
DUP25-086 | 33.0 | 34.5 | 1.5 | 2.23 | Lumière | |
DUP25-086 | 112.6 | 113.5 | 0.9 | 1.47 | Lumière | |
DUP25-086 | 117.0 | 118.0 | 1.0 | 1.69 | Lumière | |
DUP25-086 | 161.0 | 162.0 | 1.0 | 0.56 | Lumière | |
DUP25-087 | 41.0 | 46.25 | 5.25 | 3.35 | Miroir | |
DUP25-087 | including | 43.0 | 43.55 | 0.55 | 20.50 | Miroir |
DUP25-087 | 51.3 | 51.9 | 0.6 | 1.40 | Miroir | |
DUP25-087 | 57.55 | 62.25 | 4.7 | 0.95 | Miroir | |
DUP25-087 | 79.25 | 86.4 | 7.15 | 0.85 | Miroir | |
DUP25-087 | 114.95 | 115.9 | 0.95 | 0.85 | Miroir | |
DUP25-087 | 119.0 | 120.55 | 1.55 | 3.05 | Miroir | |
DUP25-088 | 5.0 | 6.0 | 1.0 | 0.91 | Lumière | |
DUP25-089 | 31.0 | 31.6 | 0.6 | 0.82 | Miroir | |
DUP25-089 | 111.7 | 115.25 | 3.55 | 1.52 | Miroir | |
DUP25-089 | 129.0 | 129.7 | 0.7 | 0.77 | Miroir | |
DUP25-089 | 208.65 | 210.35 | 1.7 | 1.79 | Miroir | |
DUP25-089 | 214.35 | 217.0 | 2.65 | 0.72 | Miroir | |
DUP25-089 | 222.2 | 223.65 | 1.45 | 1.91 | Miroir | |
DUP25-089 | 233.5 | 235.5 | 2.0 | 1.46 | Miroir | |
DUP25-089 | 238.6 | 239.55 | 0.95 | 0.74 | Miroir | |
DUP25-089 | 247.0 | 252.0 | 5.0 | 1.45 | Miroir | |
DUP25-089 | 255.0 | 258.0 | 3.0 | 0.41 | Miroir | |
DUP25-089 | 264.0 | 268.0 | 4.0 | 1.26 | Miroir | |
DUP25-089 | 271.0 | 278.0 | 7.0 | 1.53 | Miroir | |
DUP25-089 | 285.0 | 288.1 | 3.1 | 1.48 | Miroir | |
DUP25-089 | 291.4 | 292.95 | 1.55 | 0.99 | Miroir | |
DUP25-089 | 308.0 | 310.25 | 2.25 | 7.88 | Miroir | |
DUP25-089 | including | 313.0 | 314.6 | 1.6 | 2.55 | Miroir |
DUP25-089 | 344.2 | 347.0 | 2.8 | 0.42 | Miroir | |
DUP25-089 | 359.0 | 359.6 | 0.6 | 0.69 | Miroir | |
DUP25-090 | 6.0 | 7.0 | 1.0 | 0.51 | Miroir | |
DUP25-090 | 157.0 | 159.3 | 2.3 | 1.68 | Miroir | |
DUP25-090 | 162.0 | 163.0 | 1.0 | 0.74 | Miroir | |
DUP25-090 | 177.0 | 178.0 | 1.0 | 0.77 | Miroir | |
DUP25-090 | 190.0 | 191.0 | 1.0 | 0.60 | Miroir | |
DUP25-090 | 269.7 | 273.0 | 3.3 | 3.49 | Miroir | |
DUP25-090 | including | 269.7 | 270.25 | 0.55 | 6.87 | Miroir |
DUP25-090 | and inc. | 270.8 | 271.4 | 0.6 | 11.00 | Miroir |
DUP25-090 | 306.9 | 316.4 | 9.5 | 0.61 | Miroir | |
DUP25-090 | 320.9 | 332.9 | 12.0 | 4.08 | Miroir | |
DUP25-090 | including | 327.0 | 328.0 | 1.0 | 11.20 | Miroir |
DUP25-091 | 34.0 | 38.0 | 4.0 | 0.50 | Miroir | |
DUP25-091 | 172.0 | 173.0 | 1.0 | 0.76 | Miroir | |
DUP25-091 | 177.0 | 184.0 | 7.0 | 0.54 | Miroir | |
DUP25-091 | 188.0 | 191.0 | 3.0 | 0.45 | Miroir | |
DUP25-091 | 255.0 | 256.0 | 1.0 | 0.47 | Miroir | |
DUP25-091 | 269.0 | 270.0 | 1.0 | 5.18 | Miroir | |
DUP25-091 | 312.0 | 313.0 | 1.0 | 1.06 | Miroir | |
DUP25-091 | 327.0 | 328.0 | 1.0 | 1.17 | Miroir | |
DUP25-091 | 346.0 | 349.4 | 3.4 | 0.39 | Miroir | |
DUP25-091 | 352.0 | 353.0 | 1.0 | 0.68 | Miroir | |
DUP25-091 | 507.0 | 509.0 | 2.0 | 0.85 | Miroir | |
DUP25-091 | 518.0 | 522.2 | 4.2 | 1.01 | Miroir | |
*Reported intervals are drilled core lengths (true widths are estimated at 75 |
Table 4: Latest 2025 Drill Hole Locations
Hole ID | Azimuth (°) | Dip (°) | Length (m) | Easting | Northing |
DUP25-066 | 330 | -45 | 294 | 633650 | 5374024 |
DUP25-068 | 340 | -45 | 225 | 633860 | 5374080 |
DUP25-071 | 180 | -50 | 159 | 633437 | 5373738 |
DUP25-072 | 180 | -50 | 174 | 633369 | 5373751 |
DUP25-073 | 180 | -50 | 153 | 633568 | 5373739 |
DUP25-074 | 180 | -55 | 495 | 633552 | 5373921 |
DUP25-081 | 340 | -50 | 330 | 633639 | 5373996 |
DUP25-082 | 340 | -50 | 270 | 633591 | 5373980 |
DUP25-083 | 180 | -70 | 625 | 633681 | 5374086 |
DUP25-084 | 342 | -52 | 282 | 633651 | 5374024 |
DUP25-085 | 338 | -54 | 201 | 633569 | 5374057 |
DUP25-086 | 350 | -50 | 201 | 633409 | 5374075 |
DUP25-087 | 340 | -50 | 150 | 633534 | 5374044 |
DUP25-088 | 355 | -50 | 150 | 633105 | 5374188 |
DUP25-089 | 327 | -54 | 366 | 633716 | 5374030 |
DUP25-090 | 335 | -52 | 351 | 633694 | 5373963 |
DUP25-091 | 330 | -53 | 600 | 633834 | 5373899 |
Note: Collar coordinates in UTM NAD 83 z17 |
About the Duparquet Gold Project
The Duparquet Project is situated in the southern part of the Abitibi Greenstone Belt and is geographically located approximately 50 km northwest of the city of
The Duparquet Project totals approximately 5,800 hectares focused on an area of 19 km of strike length along the prolific Destor-Porcupine Fault Zone, along with numerous mineralized splays and influential secondary lineaments. The Duparquet Project includes the past-producing Beattie, Donchester and Duquesne mines as well as the
1 Further details on the Duparquet PEA can be found in the technical report entitled "NI 43-101 Technical Report: Preliminary Economic Assessment, Duparquet Gold Project, |
Analytical Laboratory and QA/QC Procedures
All sampling completed by First Mining within its exploration programs is subject to a Company standard of internal quality control and quality assurance (QA/QC) programs which include the insertion of certified reference materials, blank materials and a level of duplicate analysis. Core samples from the 2025 drilling program at
Qualified Person
James Maxwell, P.Geo., VP, Exploration and Project Operations for First Mining, is a "Qualified Person" for the purposes of NI 43-101 Standards of Disclosure for Mineral Projects and has reviewed and approved the scientific and technical disclosure contained in this news release.
About First Mining Gold Corp.
First Mining is a gold developer advancing two of the largest gold projects in
First Mining was established in 2015 by Mr. Keith Neumeyer, founder and CEO of First Majestic Silver Corp.
ON BEHALF OF FIRST MINING GOLD CORP.
Daniel W. Wilton
Chief Executive Officer and Director
Cautionary Note Regarding Forward-Looking Statements
This news release includes certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the meaning of applicable Canadian and
Forward-looking statements in this news release relate to future events or future performance and reflect current estimates, predictions, expectations or beliefs regarding future events and include but are not limited to, statements with respect to: (i) the potential for resource growth and future exploration success at the Project; (ii) the commencement and success of any environmental baseline programs at the Project; (iii) the compilation and interpretation of the drilling results at the Project; (iv) publication of a feasibility at the Duparquet Project; (v) feasibility and permitting activities related to the Springpole Gold Project; and (vi) realizing the value of the Company's gold projects for the Company's shareholders. All forward-looking statements are based on First Mining's or its consultants' current beliefs as well as various assumptions made by them and information currently available to them. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements reflect the beliefs, opinions and projections on the date the statements are made and are based upon a number of assumptions and estimates that, while considered reasonable by the respective parties, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Such factors include, without limitation the Company's business, operations and financial condition potentially being materially adversely affected by the outbreak of epidemics, pandemics or other health crises, and by reactions by government and private actors to such outbreaks; risks to employee health and safety as a result of the outbreak of epidemics, pandemics or other health crises, that may result in a slowdown or temporary suspension of operations at some or all of the Company's mineral properties as well as its head office; fluctuations in the spot and forward price of gold, silver, base metals or certain other commodities; fluctuations in the currency markets (such as the Canadian dollar versus the
First Mining cautions that the foregoing list of factors that may affect future results is not exhaustive. When relying on our forward-looking statements to make decisions with respect to First Mining, investors and others should carefully consider the foregoing factors and other uncertainties and potential events. First Mining does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by the Company or on our behalf, except as required by law.
Cautionary Note to United States Investors
The Company is a "foreign private issuer" as defined in Rule 3b-4 under the United States Securities Exchange Act of 1934, as amended, and is eligible to rely upon the
Technical disclosure contained in this news release has not been prepared in accordance with the requirements of
NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning the issuer's material mineral projects.
View original content to download multimedia:https://www.prnewswire.com/news-releases/first-mining-intersects-7-18-gt-au-over-8-m-at-the-miroir-target-and-provides-duparquet-project-update-302707838.html
SOURCE First Mining Gold Corp.
FAQ
What did First Mining (FFMGF) report about the Miroir target on March 9, 2026?
What were the standout drill intercepts reported by First Mining (FFMGF) at Duparquet in 2025?
How much drilling did First Mining (FFMGF) complete at Duparquet in 2025 and what's planned for 2026?
What is the scope of First Mining's environmental baseline program for the Duparquet Project?
How do the 2025 Duparquet results affect First Mining (FFMGF) resource planning and next steps?