First Mining Strengthens Miroir Discovery at Duparquet Gold Project with New Near-Surface Drilling Results and Expands Valentre Target Zone at Depth
Al ritrovamento Miroir:
- DUP25-052: 2,77 g/t Au su 11,1 m (inclusi 4,36 g/t Au su 6,5 m)
- DUP25-054: 1,41 g/t Au su 11,9 m (inclusi 2,52 g/t Au su 5,25 m)
Al bersaglio Valentre:
- DUP25-054: 3,96 g/t Au su 9,3 m (inclusi 5,71 g/t Au su 5,8 m)
L'azienda sta portando avanti una campagna di perforazione di 18.000 m con due trivelle, concentrandosi sull'espansione della risorsa in uno dei maggiori progetti auriferi in Quebec. Il programma ha confermato la continuità della mineralizzazione sia in prossimità della superficie che in profondità, con il bersaglio Valentre che mostra risultati promettenti a 335 m di profondità.
En el descubrimiento Miroir:
- DUP25-052: 2,77 g/t Au sobre 11,1 m (incluyendo 4,36 g/t Au sobre 6,5 m)
- DUP25-054: 1,41 g/t Au sobre 11,9 m (incluyendo 2,52 g/t Au sobre 5,25 m)
En el objetivo Valentre:
- DUP25-054: 3,96 g/t Au sobre 9,3 m (incluyendo 5,71 g/t Au sobre 5,8 m)
La compañía está llevando a cabo una campaña de perforación de 18.000 m con dos equipos de perforación, enfocándose en expandir el recurso en uno de los mayores proyectos de desarrollo aurífero en Quebec. El programa ha confirmado la continuidad de la mineralización tanto cerca de la superficie como a profundidad, con el objetivo Valentre mostrando resultados prometedores a 335 m de profundidad.
Miroir 발견 지점:
- DUP25-052: 11.1m 구간에서 2.77 g/t Au (이 중 6.5m 구간에서 4.36 g/t Au)
- DUP25-054: 11.9m 구간에서 1.41 g/t Au (이 중 5.25m 구간에서 2.52 g/t Au)
Valentre 목표 지점:
- DUP25-054: 9.3m 구간에서 3.96 g/t Au (이 중 5.8m 구간에서 5.71 g/t Au)
회사는 두 대의 시추 장비를 사용하여 18,000m 시추 캠페인을 진행 중이며, 퀘벡에서 가장 큰 금 개발 프로젝트 중 하나인 이 자원의 확장에 집중하고 있습니다. 이 프로그램은 표층 근처와 심층 모두에서 광물화의 연속성을 확인했으며, Valentre 목표 지점은 335m 깊이에서 유망한 결과를 보였습니다.
À la découverte Miroir :
- DUP25-052 : 2,77 g/t Au sur 11,1 m (dont 4,36 g/t Au sur 6,5 m)
- DUP25-054 : 1,41 g/t Au sur 11,9 m (dont 2,52 g/t Au sur 5,25 m)
À la cible Valentre :
- DUP25-054 : 3,96 g/t Au sur 9,3 m (dont 5,71 g/t Au sur 5,8 m)
L'entreprise mène une campagne de forage de 18 000 m avec deux foreuses, se concentrant sur l'expansion de la ressource dans l'un des plus grands projets de développement aurifère du Québec. Le programme a confirmé la continuité de la minéralisation à la fois près de la surface et en profondeur, la cible Valentre montrant des résultats prometteurs à 335 m de profondeur.
Beim Miroir Fund:
- DUP25-052: 2,77 g/t Au über 11,1 m (darunter 4,36 g/t Au über 6,5 m)
- DUP25-054: 1,41 g/t Au über 11,9 m (darunter 2,52 g/t Au über 5,25 m)
Beim Valentre Ziel:
- DUP25-054: 3,96 g/t Au über 9,3 m (darunter 5,71 g/t Au über 5,8 m)
Das Unternehmen führt eine 18.000 m lange Bohrkampagne mit zwei Bohrgeräten durch, mit dem Fokus, die Ressource bei einem der größten Goldentwicklungsprojekte in Quebec zu erweitern. Das Programm bestätigte die Kontinuität der Mineralisierung sowohl in der Nähe der Oberfläche als auch in der Tiefe, wobei das Valentre Ziel bei 335 m Tiefe vielversprechende Ergebnisse zeigte.
- Multiple significant gold intercepts discovered near surface at Miroir target
- Successful expansion of Valentre target zone at depth with high-grade results
- Confirmation of mineralization continuity along strike and at depth
- Project confirmed as one of the largest gold development projects in Quebec
- Active exploration program with two drill rigs advancing key resource growth targets
- None.
- Miroir – Multiple positive gold intercepts returned near surface including:
- DUP25-052 returns 2.77 g/t Au over 11.1 m, including 4.36 g/t Au over 6.5 m, at a depth of 12.9 m
- DUP25-054 returns 1.41 g/t Au over 11.9 m, including 2.52 g/t Au over 5.25 m, at a depth of 26.7 m
- Valentre – Significant intercepts supporting target expansion at depth and along strike including:
- DUP25-054 returns 3.96 g/t Au over 9.3 m, including 5.71 g/t Au over 5.8 m
The newly discovered Miroir target remains an excellent expansion opportunity where the 2025 drilling program and strategy is focused on further delineating the near surface extent of the mineralization footprint. The initial drill holes tested a zone extending approximately 100 m along strike from the initial discovery hole DUP24-048. Multiple significant intercepts of gold mineralization have been returned from this drilling, confirming and expanding the known extent of mineralization at Miroir. Highlights include near surface mineralization intercepts from drill hole DUP25-052 that returned 2.77 g/t Au over 11.1 m, including 4.36 g/t Au over 6.5 m, and drill hole DUP25-054 that returned 1.41 g/t Au over 11.9 m, including 2.52 g/t Au over 5.25 m, demonstrating encouraging grade and widths of gold mineralization within this shallow target that remains open for expansion (Figure 1).
"Our exploration drilling continues to demonstrate significant resource growth potential by delineating new discovery zones as well as demonstrating the continuity of mineralization along strike and at depth within underexplored areas of the Duparquet Gold Project," stated Dan Wilton, CEO of First Mining. "The confirmation of the continuity of near-surface mineralization in the Valentre and Miroir areas demonstrates that this well-established resource, already one of the largest in
Further strong results also include assays from a secondary target within a dual-purpose exploration drill hole at Miroir, where the depth extension of mineralization at the Valentre target, located 225 m south of Miroir, has now been successfully intersected at a vertical depth of 335 m. Within the secondary target, drill hole DUP25-054 returned 3.96 g/t Au over 9.3 m from 409.7 m to 419.0 m, including 5.71 g/t Au over 5.8 m, confirming a large extension and continuity of gold mineralization at the Valentre target along a key plunge. The assay results returned from the Valentre target continues to demonstrate continuity in grade and furthermore continues to validate the open-ended mineralization at Valentre.
Assay highlights from the 1, 140 metres completed across the initial six drill holes of the 2025 program are shown in Table 1, with a full list of assays returned in Table 2 and collar details in Table 3.
Table 1: Selected Significant Drill Intercepts, 2025 Program – Miroir and Valentre Targets
Hole ID | From (m) | To (m) | Length (m) | Grade (Au g/t) | Target | |
DUP25-050 | 8.0 | 14.9 | 6.9 | 1.48 | Miroir | |
DUP25-051 | 8.0 | 13.0 | 5.0 | 1.47 | Miroir | |
DUP25-051 | 24.2 | 27.4 | 3.2 | 3.54 | Miroir | |
DUP25-051 | inc. | 25.0 | 25.7 | 0.7 | 12.00 | Miroir |
DUP25-052 | 12.9 | 24.0 | 11.1 | 2.77 | Miroir | |
DUP25-052 | inc. | 12.9 | 19.4 | 6.5 | 4.36 | Miroir |
DUP25-052 | and inc. | 12.9 | 13.6 | 0.7 | 13.40 | Miroir |
DUP25-052 | 34.3 | 36.5 | 2.2 | 2.92 | Miroir | |
DUP25-052 | 103.0 | 104.0 | 1.0 | 5.03 | Miroir | |
DUP25-054 | 26.7 | 38.6 | 11.9 | 1.41 | Miroir | |
DUP25-054 | inc. | 27.3 | 32.55 | 5.25 | 2.52 | Miroir |
DUP25-054 | and inc. | 29.4 | 30.5 | 1.1 | 7.27 | Miroir |
DUP25-054 | 380.35 | 390.1 | 9.75 | 1.14 | Valentre | |
DUP25-054 | inc. | 383.2 | 387.9 | 4.7 | 1.65 | Valentre |
DUP25-054 | and inc. | 384.2 | 384.7 | 0.5 | 6.19 | Valentre |
DUP25-054 | 409.7 | 419.0 | 9.3 | 3.96 | Valentre | |
DUP25-054 | inc. | 412.0 | 417.8 | 5.8 | 5.71 | Valentre |
DUP25-054 | and inc. | 415.0 | 417.8 | 2.8 | 7.50 | Valentre |
Exploration activities are ongoing at the Duparquet Project with two drill rigs actively advancing at key resource growth targets through to the fall. Regional field campaigns will be commencing at the end of May 2025 with a focus on target generation across favourable lithologies and structures. The North Zone drilling will continue to focus on testing the syenite-mafic volcanic contact that has previously demonstrated an ability to host higher grade gold mineralization. Drilling at the South Zone will be targeting the extension of mineralization below the historical Donchester mine workings. Additional targets to be followed up on is the Aiguille Target, where drilling will be following up on the two discovery holes to further drill test the target's open-ended potential. A plan map of the key targets for exploration drilling activities is shown in Figure 2.
Additional Details on the Miroir and Valentre Drilling
Miroir
The 2025 Miroir drilling is focused on further delineating the extent of mineralization around the 2024 discovery hole, DUP24-048, that returned 3.12 g/t Au over 19.35 m close to surface (refer to news release dated January 20, 2025). An area of approximately 100 m along strike has thus far been drill tested with six drill holes (Table 3) intersecting seven unique significant mineralization intervals including DUP25-052 that returned 2.77 g.t Au over 11.1 m, including 4.36 g/t Au over 6.5 m (Tables 1 and 2). The mineralized intercepts confirm the open-ended nature of the Miroir target (Figure 1).
The Miroir target is situated 225 m north of the Valentre target, hosted along the northern contact between the mafic volcanic and the syenite (Figure 3). This contact zone has traditionally demonstrated a stronger affinity for higher-grade mineralization, a characteristic also observed at the North Zone target area of the project, located 1.5 km to the west.
Mineralization at the Miroir target is associated with silica-altered, sheared and brecciated basalt and syenite, featuring dark smoky quartz veining and up to
Valentre
The objective of the 2025 drilling campaign at the Valentre target is to evaluate grade continuity and to refine the understanding of higher-grade mineralized zones at depth through a targeted drilling campaign. A dual-target hole, DUP25-054, was designed to drill test both the Miroir and the Valentre targets, as illustrated in Figure 4. Significant results returned from DUP25-054 for the Valentre target are 3.96 g/t Au over 9.3 m, including 5.71 g/t Au over 5.8 m at a depth of approximately 330 m below surface.
Mineralization in hole DUP25-054 consists of brecciated silica-altered syenite and lath syenite with up to
Follow-up drilling is planned at the Valentre target, with the objective of advancing exploration definition through additional resolution and step-out drilling to support updated geological modelling with a potential for incorporation into future mineral resource estimates (Figure 5).
Table 2: Initial Assay Results from 2025 Drill Program
Hole ID | From (m) | To (m) | Length (m) | Grade (Au g/t) | Target | |
DUP25-049 | 14.1 | 15.0 | 0.9 | 1.29 | Miroir | |
DUP25-049 | 73.3 | 74.0 | 0.7 | 0.62 | ||
DUP25-049 | 105.6 | 108.6 | 3.0 | 0.42 | ||
DUP25-050 | 8.0 | 14.9 | 6.9 | 1.48 | ||
DUP25-050 | 33.7 | 34.4 | 0.7 | 0.45 | ||
DUP25-050 | 38.25 | 39.0 | 0.75 | 0.47 | ||
DUP25-050 | 58.3 | 58.9 | 0.6 | 0.46 | ||
DUP25-050 | 97.0 | 98.0 | 1.0 | 0.50 | ||
DUP25-051 | 8.0 | 13.0 | 5.0 | 1.47 | ||
DUP25-051 | 18.0 | 19.6 | 1.6 | 2.71 | ||
DUP25-051 | 24.2 | 27.4 | 3.2 | 3.54 | ||
DUP25-051 | inc. | 25.0 | 25.7 | 0.7 | 12.00 | |
DUP25-051 | 41.0 | 42.0 | 1.0 | 0.54 | ||
DUP25-051 | 55.5 | 56.4 | 0.9 | 0.52 | ||
DUP25-051 | 68.0 | 69.0 | 1.0 | 0.42 | ||
DUP25-051 | 107.0 | 108.0 | 1.0 | 1.29 | ||
DUP25-051 | 132.0 | 136.9 | 4.9 | 0.84 | ||
DUP25-052 | 12.9 | 24.0 | 11.1 | 2.77 | ||
DUP25-052 | inc. | 12.9 | 19.4 | 6.5 | 4.36 | |
DUP25-052 | and inc. | 12.9 | 13.6 | 0.7 | 13.40 | |
DUP25-052 | 30.0 | 30.85 | 0.85 | 0.89 | ||
DUP25-052 | 34.3 | 36.5 | 2.2 | 2.92 | ||
DUP25-052 | 101.0 | 102.0 | 1.0 | 0.63 | ||
DUP25-052 | 103.0 | 104.0 | 1.0 | 5.03 | ||
DUP25-053 | 19.0 | 20.5 | 1.5 | 0.72 | ||
DUP25-053 | 27.0 | 32.4 | 5.4 | 0.41 | ||
DUP25-053 | 90.0 | 90.75 | 0.75 | 0.51 | ||
DUP25-054 | 15.0 | 16.0 | 1.0 | 0.52 | ||
DUP25-054 | 26.7 | 38.6 | 11.9 | 1.41 | ||
DUP25-054 | inc. | 27.3 | 32.55 | 5.25 | 2.52 | |
DUP25-054 | and inc. | 29.4 | 30.5 | 1.1 | 7.27 | |
DUP25-054 | 57.4 | 58.05 | 0.65 | 1.41 | ||
DUP25-054 | 127.55 | 128.65 | 1.1 | 1.44 | Valentre | |
DUP25-054 | 180.25 | 184.25 | 4.0 | 0.65 | ||
DUP25-054 | 295.8 | 296.75 | 0.95 | 2.20 | ||
DUP25-054 | 310.2 | 312.0 | 1.8 | 0.56 | ||
DUP25-054 | 337.0 | 338.6 | 1.6 | 0.96 | ||
DUP25-054 | 342.3 | 342.8 | 0.5 | 0.43 | ||
DUP25-054 | 349.0 | 350.25 | 1.25 | 0.60 | ||
DUP25-054 | 354.1 | 354.6 | 0.5 | 2.28 | ||
DUP25-054 | 357.5 | 362.5 | 5.0 | 0.95 | ||
DUP25-054 | inc. | 357.5 | 358.4 | 0.9 | 3.75 | |
DUP25-054 | 374.9 | 376.0 | 1.1 | 2.27 | ||
DUP25-054 | 380.35 | 390.1 | 9.75 | 1.14 | ||
DUP25-054 | inc. | 383.2 | 387.9 | 4.7 | 1.65 | |
DUP25-054 | and inc. | 384.2 | 384.7 | 0.5 | 6.19 | |
DUP25-054 | 397.0 | 398.35 | 1.35 | 0.97 | ||
DUP25-054 | 409.7 | 419.0 | 9.3 | 3.96 | ||
DUP25-054 | inc. | 412.0 | 417.8 | 5.8 | 5.71 | |
DUP25-054 | and inc. | 415.0 | 417.8 | 2.8 | 7.50 | |
DUP25-054 | 424.15 | 427.25 | 3.1 | 0.67 | ||
DUP25-054 | 431.8 | 432.8 | 1.0 | 1.55 | ||
DUP25-054 | 439.2 | 439.7 | 0.5 | 0.84 |
*Reported intervals are drilled core lengths (true widths are estimated at 75
Table 3: 2025 Drill Hole Locations, Miroir and Valentre Targets
Hole ID | Azimuth (°) | Dip (°) | Length (m) | Easting | Northing |
DUP25-049 | 180 | -45 | 111 | 633567 | 5374072 |
DUP25-050 | 180 | -45 | 129 | 633591 | 5374067 |
DUP25-051 | 183 | -45 | 136.9 | 633622 | 5374076 |
DUP25-052 | 179 | -57 | 158.3 | 633629 | 5374129 |
DUP25-053 | 180 | -45 | 114 | 633648 | 5374074 |
DUP25-054 | 180 | -55 | 490 | 633596 | 5374094 |
Note: Collar coordinates in UTM NAD 83 z17
About the Duparquet Gold Project
The Duparquet Project is geologically situated in the southern part of the Abitibi Greenstone Belt and is geographically located approximately 50 km north of the city of
The Duparquet Project totals approximately 5,800 hectares focused on an area of 19 km of strike length along the prolific Destor-Porcupine Fault Zone, along with numerous mineralized splays and influential secondary lineaments. The Duparquet Project includes the past-producing Beattie, Donchester and Duquesne mines as well as the
1 Further details on the Duparquet PEA can be found in the technical report entitled "NI 43-101 Technical Report: Preliminary Economic Assessment, Duparquet Gold Project,
Analytical Laboratory and QA/QC Procedures
All sampling completed by First Mining within its exploration programs is subject to a Company standard of internal quality control and quality assurance (QA/QC) programs which include the insertion of certified reference materials, blank materials and a level of duplicate analysis. Core samples from the 2025 drilling program at
Qualified Person
James Maxwell, P.Geo., VP, Exploration and Project Operations for First Mining, is a "Qualified Person" for the purposes of NI 43-101 Standards of Disclosure for Mineral Projects and has reviewed and approved the scientific and technical disclosure contained in this news release.
About First Mining Gold Corp.
First Mining is a gold developer advancing two of the largest gold projects in
First Mining was established in 2015 by Mr. Keith Neumeyer, founding President and CEO of First Majestic Silver Corp.
ON BEHALF OF FIRST MINING GOLD CORP.
Daniel W. Wilton
Chief Executive Officer and Director
Cautionary Note Regarding Forward-Looking Statements
This news release includes certain "forward-looking information" and "forward-looking statements" (collectively "forward-looking statements") within the meaning of applicable Canadian and
Forward-looking statements in this news release relate to future events or future performance and reflect current estimates, predictions, expectations or beliefs regarding future events. All forward-looking statements are based on First Mining's or its consultants' current beliefs as well as various assumptions made by them and information currently available to them. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements reflect the beliefs, opinions and projections on the date the statements are made and are based upon a number of assumptions and estimates that, while considered reasonable by the respective parties, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Such factors include, without limitation the Company's business, operations and financial condition potentially being materially adversely affected by the outbreak of epidemics, pandemics or other health crises, and by reactions by government and private actors to such outbreaks; risks to employee health and safety as a result of the outbreak of epidemics, pandemics or other health crises, that may result in a slowdown or temporary suspension of operations at some or all of the Company's mineral properties as well as its head office; fluctuations in the spot and forward price of gold, silver, base metals or certain other commodities; fluctuations in the currency markets (such as the Canadian dollar versus the
First Mining cautions that the foregoing list of factors that may affect future results is not exhaustive. When relying on our forward-looking statements to make decisions with respect to First Mining, investors and others should carefully consider the foregoing factors and other uncertainties and potential events. First Mining does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by the Company or on our behalf, except as required by law.
Cautionary Note to United States Investors
The Company is a "foreign private issuer" as defined in Rule 3b-4 under the United States Securities Exchange Act of 1934, as amended, and is eligible to rely upon the
Technical disclosure contained in this news release has not been prepared in accordance with the requirements of
NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning the issuer's material mineral projects.
View original content to download multimedia:https://www.prnewswire.com/news-releases/first-mining-strengthens-miroir-discovery-at-duparquet-gold-project-with-new-near-surface-drilling-results-and-expands-valentre-target-zone-at-depth-302466486.html
SOURCE First Mining Gold Corp.