Fortuna Expands Mineral Reserves and Mineral Resources for the Séguéla Mine, Côte d'Ivoire
Fortuna Mining (NYSE: FSM) reported updated Séguéla Mine reserves and resources as of October 31, 2025: Proven & Probable Mineral Reserves of 13.0 million tonnes containing 1.2 million oz Au (an 11% increase vs. Dec 31, 2024). Measured & Indicated Resources (ex-reserves) total 794,000 oz Au (+100%), and Inferred Resources total 712,000 oz Au (+15%).
Company cited a 7.5-year life of mine, Sunbird underground growth (502,000 oz indicated), ongoing infill drilling, underground studies with a December 2025 milestone, and plant expansion evaluations to ~25% higher capacity (2.0–2.5 Mtpa).
Fortuna Mining (NYSE: FSM) ha riportato riserve e risorse aggiornate della Miniera Séguéla al 31 ottobre 2025: Riserve minerali provate e probabili di 13,0 milioni di tonnellate contenenti 1,2 milioni di oz Au (un aumento dell'11% rispetto al 31 dicembre 2024). Risorse misurate e indicate (ex riserve) totali 794.000 oz Au (+100%), e Risorse inferite totali 712.000 oz Au (+15%).
L'azienda cita una vita della miniera di 7,5 anni, crescita sotterranea Sunbird (502.000 oz indicate), trivellazioni di infill in corso, studi sotterranei con una pietra miliare prevista per dicembre 2025 e valutazioni per l'espansione dell'impianto fino a una capacità superiore di ~25% (2,0–2,5 Mtpa).
Fortuna Mining (NYSE: FSM) informó reservas y recursos actualizados de la Mina Séguéla al 31 de octubre de 2025: Reservas mineras probadas y probables de 13,0 millones de toneladas que contienen 1,2 millones de oz Au (un aumento del 11% con respecto al 31 de diciembre de 2024). Recursos medidos e indicados (ex-reservas) en total 794.000 oz Au (+100%), y Recursos indicados totales 712.000 oz Au (+15%).
La empresa cita una vida de mina de 7,5 años, crecimiento subterráneo Sunbird (502.000 oz indicadas), perforación de relleno en curso, estudios subterráneos con un hito para diciembre de 2025 y evaluaciones para ampliar la planta a una capacidad ~25% mayor (2,0–2,5 Mtpa).
Fortuna Mining (NYSE: FSM) 는 2025년 10월 31일 기준 Séguéla 광산의 매장량 및 자원 업데이트를 발표했습니다: 확정 및 가능 매장량 13.0백만 톤에 금 120만 온스 포함(2024년 12월 31일 대비 11% 증가). 계량 및 표시 자원 (이전의 매장량 제외) 총 794,000 oz Au (+100%), 추정 자원 총 712,000 oz Au (+15%).
회사는 광산 수명 7.5년, Sunbird 지하 성장(표시 502,000 oz), 보충 천공 진행, 2025년 12월 마일스톤의 지하 연구, 공장 용량을 약 25% 증가시켜 2.0–2.5 Mtpa로 확장 평가를 언급했습니다.
Fortuna Mining (NYSE: FSM) a publié les réserves et ressources mises à jour de la mine Séguéla au 31 octobre 2025 : Réserves minérales « Proved & Probable » de 13,0 millions de tonnes contenant 1,2 million d'oz d'or (une hausse de 11 % par rapport au 31 décembre 2024). Ressources Mesurées et Indiquées (ex-réserves) totalisant 794 000 oz d'or (+100 %), et Ressources Inférées totalisant 712 000 oz d'or (+15 %).
L'entreprise évoque une durée de vie de la mine de 7,5 ans, une croissance souterraine Sunbird (502 000 oz indiquées), des forages d'infill en cours, des études souterraines avec une étape clé en décembre 2025 et des évaluations d'extension de l'usine pour une capacité d'environ 25 % supérieure (2,0–2,5 Mtpa).
Fortuna Mining (NYSE: FSM) meldete aktualisierte Reserven und Ressourcen der Séguéla-Mine zum 31. Oktober 2025: Belegbare & Wahrscheinlich belegbare Mineralreserven von 13,0 Millionen Tonnen mit 1,2 Millionen Unzen Gold (11% gegenüber dem 31. Dezember 2024). Gemessene & Indizierte Ressourcen (ehemals Reserven) insgesamt 794.000 oz Au (+100%), und Abgeleitete Ressourcen insgesamt 712.000 oz Au (+15%).
Das Unternehmen nennt eine Lebensdauer der Mine von 7,5 Jahren, das Untertagewachstum von Sunbird (502.000 oz indicierte), laufende Infill-Bohrungen, untertägige Studien mit einem Meilenstein im Dezember 2025 und Bewertungen zur Erweiterung der Anlage auf ca. 25% höhere Kapazität (2,0–2,5 Mtpa).
Fortuna Mining (NYSE: FSM) أبلغت عن تحديثات للاحتياطيات والموارد في منجم سيغويللا حتى 31 أكتوبر 2025: احتياطيات معدنية موثوقة ومرجحة تبلغ 13,0 مليون طن وتحتوي على 1,2 مليون أونصة من الذهب (زيادة قدرها 11% مقارنةً بـ31 ديسمبر 2024). الموارد المقاسة والمحددة (سابقاً احتياطيات) بإجمالي 794,000 أونصة ذهب (+100%)، والموارد المستنتجة بإجمالي 712,000 أونصة ذهب (+15%).
ذكرت الشركة عمر منجم قدره 7.5 سنوات، ونمو تحت الأرض في Sunbird (502,000 أونصة محددة)، حفر تكميلي جارٍ، دراسات تحت الأرض مع معلم ديسمبر 2025، وتقييمات لتوسيع المصنع لزيادة السعة بنحو 25% إلى 2.0–2.5 Mtpa.
- Proven & Probable Mineral Reserves: 1.2M oz Au (+11%)
- Measured & Indicated Resources: 794k oz Au (+100%)
- Sunbird underground Indicated: 502k oz Au
- Plant expansion studies targeting ~25% higher capacity to 2.0–2.5 Mtpa
- Global reserve grade declined by 17% to 2.81 g/t Au
- Mining depletion Jan–Oct 2025: 129k oz Au
- Average reserve strip ratio of 13.4:1 (higher mining intensity)
Insights
Séguéla's reserve and resource growth materially improves mine life and supports plant expansion studies through 2026.
Fortuna reports Proven and Probable Mineral Reserves of 13.0 million tonnes containing 1.2 million ounces of gold and Measured and Indicated Resources (exclusive of reserves) of 794,000 ounces, with Inferred Resources of 712,000 ounces. The change reflects a 33% rise in reserve tonnes, a 17% decline in average reserve grade to 2.81 g/t Au, and a net 11% increase in contained gold ounces versus year-end
Production and geometry drove grade dilution: mined depletion of 129,000 ounces in the first ten months of
The principal dependencies and risks are explicit: reported estimates rely on specified assumptions including a gold price basis of
VANCOUVER, British Columbia, Nov. 18, 2025 (GLOBE NEWSWIRE) -- Fortuna Mining Corp. (NYSE: FSM | TSX: FVI) is pleased to announce updated Mineral Reserves and Mineral Resources excluding Mineral Reserves for the Séguéla Mine, reporting 1.2 million ounces of gold in Mineral Reserves, 794,000 ounces of gold in Indicated Resources, and 712,000 ounces of gold in Inferred Resources.
Jorge A. Ganoza, President and CEO, commented, “Continued exploration success over the last two years has created a clear pathway to not only extend the life of mine at Séguéla, but also to evaluate a further plant expansion and a potential increase in annual gold production.” Mr. Ganoza continued, “Séguéla now boasts a 7.5-year life of mine and its largest Mineral Resource inventory on record. In response, we have launched aggressive infill drilling programs, advanced underground mining studies, and initiated plant expansion evaluations to fully capture the opportunities created by our exploration success.” Mr. Ganoza concluded, “With robust exploration programs underway and continuing into 2026, we are confident in our ability to unlock further value from our commanding land position at Séguéla.”
Updated Mineral Reserves and Mineral Resources Highlights
- Growth in Mineral Reserves offset production-related depletion, with an estimated 1.2 million ounces of gold, representing an
11% increase compared to December 31, 2024. - Measured and Indicated Mineral Resources, exclusive of Mineral Reserves, are reported containing 794,000 ounces of gold, a
100% increase compared to December 31, 2024. - Inferred Mineral Resources are reported containing 712,000 ounces of gold, reflecting a
15% increase compared to December 31, 2024. - Kingfisher and Sunbird host the largest Mineral Reserves and Mineral Resources where mineralization remains open at both deposits.
- Completion of the underground mining study, supporting the potential conversion of up to 502,000 gold ounces of Sunbird Indicated Resources into Mineral Reserves, is expected in December 2025.
- Technical studies have been initiated to evaluate a plant expansion of approximately
25% capacity to between 2.0 and 2.5 million tonnes per year; studies are expected to be completed in the second quarter of 2026.
Mineral Reserves
| Proven and Probable | ||||
| Contained Metal | ||||
| Location | Classification | Tonnes (000) | Au (g/t) | Au (koz) |
| Stockpile | Proven | 962 | 1.32 | 41 |
| Open Pit | ||||
| Antenna | Probable | 2,489 | 2.20 | 176 |
| Koula | Probable | 786 | 5.35 | 135 |
| Ancien | Probable | 1,183 | 4.23 | 161 |
| Agouti | Probable | 754 | 2.61 | 63 |
| Boulder | Probable | 532 | 1.88 | 32 |
| Sunbird | Probable | 2,409 | 3.31 | 256 |
| Badior | Probable | 404 | 4.25 | 55 |
| Kingfisher | Probable | 3,497 | 2.28 | 257 |
| Total | Proven + Probable | 13,016 | 2.81 | 1,177 |
Mineral Resources
| Measured and Indicated | ||||
| Contained Metal | ||||
| Location | Classification | Tonnes (000) | Au (g/t) | Au (koz) |
| Open Pit (OP) | ||||
| Antenna | Indicated | 1,461 | 1.58 | 74 |
| Koula | Indicated | 149 | 5.33 | 26 |
| Ancien | Indicated | 112 | 4.19 | 15 |
| Agouti | Indicated | 59 | 2.26 | 4 |
| Boulder | Indicated | 329 | 1.47 | 16 |
| Sunbird | Indicated | 255 | 3.12 | 26 |
| Badior | Indicated | 61 | 3.48 | 7 |
| Kingfisher | Indicated | 752 | 1.66 | 40 |
| OP Combined | Indicated | 3,177 | 2.03 | 207 |
| Underground (UG) | ||||
| Koula | Indicated | 23 | 3.83 | 3 |
| Ancien | Indicated | 472 | 5.43 | 82 |
| Sunbird | Indicated | 3,597 | 4.34 | 502 |
| UG Combined | Indicated | 4,093 | 4.46 | 587 |
| Total | Indicated | 7,270 | 3.40 | 794 |
| Inferred | ||||
| Contained Metal | ||||
| Location | Classification | Tonnes (000) | Au (g/t) | Au (koz) |
| Open Pit (OP) | ||||
| Antenna | Inferred | 1,498 | 1.91 | 92 |
| Koula | Inferred | 155 | 3.61 | 18 |
| Ancien | Inferred | 25 | 4.87 | 4 |
| Agouti | Inferred | 160 | 1.64 | 8 |
| Sunbird | Inferred | 88 | 1.46 | 4 |
| Badior | Inferred | 46 | 5.08 | 8 |
| Kestrel | Inferred | 60 | 1.73 | 3 |
| Kingfisher | Inferred | 4,554 | 1.82 | 267 |
| OP Combined | Inferred | 6,586 | 1.91 | 404 |
| Underground (UG) | ||||
| Koula | Inferred | 316 | 4.70 | 48 |
| Ancien | Inferred | 22 | 3.86 | 3 |
| Sunbird | Inferred | 1,719 | 4.41 | 244 |
| Kingfisher | Inferred | 135 | 2.98 | 13 |
| UG Combined | Inferred | 2,193 | 4.36 | 307 |
| Total | Inferred | 8,779 | 2.52 | 712 |
| Notes: 1. Mineral Reserves and Mineral Resources are as defined by the 2014 CIM Definition Standards for Mineral Resources and Mineral Reserves. 2. Mineral Resources are exclusive of Mineral Reserves. 3. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. 4. Factors that could materially affect the reported Mineral Resources or Mineral Reserves include changes in metal price and exchange rate assumptions; changes in local interpretations of mineralization; changes to assumed metallurgical recoveries, mining dilution and recovery; and assumptions as to the continued ability to access the site, retain mineral and surface rights titles, maintain environmental and other regulatory permits, and maintain the social license to operate. 5. Mineral Resources and Mineral Reserves are reported as of October 31, 2025. 6. Mineral Reserves are reported on a 7. Eric Chapman, P. Geo. (EGBC #36328), is the Qualified Person responsible for Mineral Resources; Raul Espinoza (FAUSIMM (CP) #309581) is the Qualified Person responsible for Mineral Reserves; both being employees of Fortuna Mining Corp. 8. Totals may not add due to rounding. |
Mineral Reserves
As of October 31, 2025, the Séguéla Mine has Proven and Probable Mineral Reserves of 13.0 million tonnes containing 1.2 million ounces of gold.
From December 31, 2024, to October 31, 2025, Mineral Reserve tonnes increased by
The reduction in the global reserve gold grade from 3.38 g/t Au to 2.81 g/t Au is a direct consequence of incorporating the Kingfisher deposit Mineral Reserves, while production during the period of January to October 2025 depleted higher grade material from the Koula and Ancien deposits. Although the Kingfisher deposit exhibits lower average grades relative to the high grade deposits, it benefits from a lower strip ratio of 7.6:1, compared to the average strip ratio of the Mineral Reserves of 13.4:1.
Changes in the Séguéla Mine's Mineral Reserves are a result of:
- Mining-related depletion in the first ten months of 2025 totaling 129,000 ounces of gold.
- The first-time estimation of Mineral Reserves for the Kingfisher deposit, totaling 3.5 million tonnes at an average grade of 2.28 g/t Au containing 257,000 ounces of gold.
- Additional variations driven by an updated geologic interpretation of the Koula deposit, as a result of grade-control drilling, as well as adjustments to operational costs and gold price assumptions.
Mineral Resources
Measured and Indicated Mineral Resource gold ounces, exclusive of Mineral Reserves, increased by
Inferred Resources tonnage increased by
Ongoing Exploration and Infill Drilling to Support Resource Growth
Drill activities remain ongoing across the Séguéla property, with five drill rigs currently active. Current drilling is focused on the potential for upgrading Inferred to Indicated Resources at the Sunbird Underground Project, while also evaluating mineralization potential at existing deposits and across the wider land package. However, insufficient tonnes were identified at the Gabbro North prospect to support a potentially economical open pit at this time.
Advancing Studies for Process Plant Expansion
Séguéla’s processing plant was commissioned in mid-2023 with a design throughput capacity of 156 t/hr, approximately 1.25 million tonnes per year. Since commissioning, several low-capital optimization initiatives have been implemented to enhance the efficiency of the plant, and the operation is now expected to treat 1.75 million tonnes per year beginning in 2026. Until recently, the increase in the mining rate required to sustain this higher throughput had been constrained by the mine life, which limited the rationale for investing in expanding the processing capacity.
The potential to extend mine life is supported by several key developments:
- Expansion of Mineral Resources at the Sunbird and Kingfisher deposits.
- Strong conversion of Inferred to Indicated Resources.
- Positive results from ongoing drilling of the Sunbird Underground Project completed after the June 30, 2025 data cut-off.
- Mineralization at both Kingfisher and Sunbird remains open in all directions.
Together, these factors provide increasing confidence in the potential to extend the mine life through future drilling and mining studies.
Given this improved visibility, Fortuna has initiated engineering studies to evaluate options for further expansion of processing plant capacity.
Sunbird Underground Project
Engineering work continues with the objective of converting Mineral Resources to Mineral Reserves by December 2025. All major technical studies, including among others, geotechnical, metallurgical, hydrogeological, are now complete, and the project team is currently developing the pre-feasibility report.
The Sunbird Underground Project has the potential to underpin strong Séguéla production for several years. Planned upcoming activities include:
- Updating Sunbird Underground Project Mineral Resources by year end.
- Ordering long-lead equipment for underground mining.
- Planning and execution of early works activities.
- Advancing government permitting.
Qualified Person
Eric Chapman, Senior Vice President, Technical Services, is a Professional Geoscientist of the Association of Professional Engineers and Geoscientists of the Province of British Columbia (Registration Number 36328) and a Qualified Person as defined by National Instrument 43-101- Standards of Disclosure for Mineral Projects. Mr. Chapman has reviewed and approved the scientific and technical information contained in this news release and has verified the underlying data.
About Fortuna Mining Corp.
Fortuna Mining Corp. is a Canadian precious metals mining company with three operating mines and a portfolio of exploration projects in Argentina, Côte d'Ivoire, Mexico, and Peru, as well as the Diamba Sud Gold Project in Senegal. Sustainability is at the core of our operations and stakeholder relationships. We produce gold and silver while creating long-term shared value through efficient production, environmental stewardship, and social responsibility. For more information, please visit our website at www.fortunamining.com.
ON BEHALF OF THE BOARD
Jorge A. Ganoza
President, CEO, and Director
Fortuna Mining Corp.
Investor Relations:
Carlos Baca | info@fmcmail.com | fortunamining.com | X | LinkedIn | YouTube
Forward-looking Statements
This news release contains forward-looking statements which constitute “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995 (collectively, “Forward-looking Statements”). All statements included herein, other than statements of historical fact, are Forward-looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward-looking Statements. The Forward-looking Statements in this news release may include, without limitation, the Mineral Resource and Mineral Reserve estimates; statements regarding extending the life of mine at Séguéla; statements regarding converting resources to reserves at the Sunbird Underground Project and the anticipated timing thereof; upcoming planned activities at the Sunbird Underground Project; the Company’s expectations regarding the expansion of processing plant capacity and a potential increase in annual gold production at Séguéla; the Company’s proposed exploration plans and objectives; statements about the Company’s business strategies, plans and outlook; the Company’s plans for its mines and mineral properties; changes in general economic conditions and financial markets; the impact of inflationary pressures on the Company’s business and operations; the future results of exploration activities; expectations with respect to metal grade estimates and the impact of any variations relative to metals grades experienced; assumed and future metal prices; the merit of the Company’s mines and mineral properties; and the future financial or operating performance of the Company. Often, but not always, these Forward-looking Statements can be identified by the use of words such as “estimated”, “potential”, “open”, “future”, “assumed”, “projected”, “proposed”, “used”, “detailed”, “has been”, “gain”, “planned”, “reflecting”, “will”, “anticipated”, “estimated” “containing”, “remaining”, “to be”, or statements that events, “could” or “should” occur or be achieved and similar expressions, including negative variations.
Forward-looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward-looking Statements. Such uncertainties and factors include, among others, operational risks associated with mining and mineral processing; uncertainty relating to Mineral Resource and Mineral Reserve estimates; uncertainty relating to capital and operating costs, production schedules and economic returns; risks relating to the Company’s ability to replace its Mineral Reserves; risks related to the conversion of Mineral Resources to Mineral Reserves; risks associated with mineral exploration and project development; uncertainty relating to the repatriation of funds as a result of currency controls; environmental matters including obtaining or renewing environmental permits and potential liability claims; uncertainty relating to nature and climate conditions; laws and regulations regarding the protection of the environment (including greenhouse gas emission reduction and other decarbonization requirements and the uncertainty surrounding the interpretation of omnibus Bill C-59 and the related amendments to the Competition Act (Canada); risks associated with political instability and changes to the regulations governing the Company’s business operations; changes in national and local government legislation, taxation, controls, regulations and political or economic developments in countries in which the Company does or may carry on business; risks associated with war, hostilities or other conflicts, such as the Ukrainian – Russian, and Israeli – Hamas conflicts, and the impacts they may have on global economic activity; risks relating to the termination of the Company’s mining concessions in certain circumstances; developing and maintaining relationships with local communities and stakeholders; risks associated with losing control of public perception as a result of social media and other web-based applications; potential opposition to the Company’s exploration, development and operational activities; risks related to the Company’s ability to obtain adequate financing for planned exploration and development activities; property title matters; risks related to the ability to retain or extend title to the Company’s mineral properties; risks relating to the integration of businesses and assets acquired by the Company; impairments; risks associated with climate change legislation; reliance on key personnel; adequacy of insurance coverage; operational safety and security risks; legal proceedings and potential legal proceedings; uncertainties relating to general economic conditions; risks relating to a global pandemic, which could impact the Company’s business, operations, financial condition and share price; competition; fluctuations in metal prices; risks associated with entering into commodity forward and option contracts for base metals production; fluctuations in currency exchange rates and interest rates; tax audits and reassessments; risks related to hedging; uncertainty relating to concentrate treatment charges and transportation costs; sufficiency of monies allotted by the Company for land reclamation; risks associated with dependence upon information technology systems, which are subject to disruption, damage, failure and risks with implementation and integration; labor relations issues; as well as those factors discussed under “Risk Factors” in the Company's Annual Information Form for the fiscal year ended December 31, 2024. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in Forward-looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.
Forward-looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including, but not limited to, the accuracy of the Company’s current Mineral Resource and Mineral Reserve estimates; that the Company’s activities will be conducted in accordance with the Company’s public statements and stated goals; that there will be no material adverse change affecting the Company, its properties or its production estimates (which assume accuracy of projected ore grade, mining rates, recovery timing, and recovery rate estimates and may be impacted by unscheduled maintenance, labor and contractor availability and other operating or technical difficulties); the duration and effect of global and local inflation; the duration and impacts of geo-political uncertainties on the Company’s production, workforce, business, operations and financial condition; the expected trends in mineral prices, inflation and currency exchange rates; that all required approvals and permits will be obtained for the Company’s business and operations on acceptable terms; that there will be no significant disruptions affecting the Company's operations and such other assumptions as set out herein. Forward-looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward-looking Statements, whether as a result of new information, future events, or results or otherwise, except as required by law. There can be no assurance that these Forward-looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward-looking Statements.
Cautionary Note to United States Investors Concerning Estimates of Reserves and Resources
All reserve and resource estimates included in this news release have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") and the Canadian Institute of Mining, Metallurgy, and Petroleum Definition Standards on Mineral Resources and Mineral Reserves. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for public disclosure by a Canadian company of scientific and technical information concerning mineral projects. All Mineral Reserve and Mineral Resource estimates contained in the technical disclosure have been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards on Mineral Resources and Reserves. Canadian standards, including NI 43-101, differ significantly from the requirements of the Securities and Exchange Commission, and mineral reserve and resource information included in this news release may not be comparable to similar information disclosed by U.S. companies.
PDF available: http://ml.globenewswire.com/Resource/Download/dd7f0f37-f0cf-48a9-861e-1b83ba3fb291