Gunnison Copper Announces Johnson Camp Mineral Processing to Start by July with First Copper Sales in September

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags
Gunnison Copper Corp (GCUMF) has announced significant progress at its Johnson Camp Mine in Arizona, with mineral processing set to begin in July 2025 and first copper sales expected in September. The company has completed Phase-1 of the leach pad construction, with Phase-2 expected soon. Mining operations have already begun with material being stockpiled. Infrastructure development is proceeding as planned, including haul road construction, PLS sump installation, and pipeline completion to the SX/EW plant. The company plans to implement both conventional leach technology for initial ROM production and Nuton technology, with the latter expected to produce copper before year-end. The project represents a strategic addition to America's copper production capacity, supporting energy and defense security needs.
Gunnison Copper Corp (GCUMF) ha annunciato importanti progressi presso la sua miniera Johnson Camp in Arizona, con l'inizio della lavorazione dei minerali previsto per luglio 2025 e le prime vendite di rame attese per settembre. L'azienda ha completato la Fase 1 della costruzione della piattaforma di lisciviazione, con la Fase 2 in arrivo a breve. Le operazioni minerarie sono già iniziate con il materiale accatastato. Lo sviluppo delle infrastrutture procede secondo i piani, inclusa la costruzione della strada di accesso, l'installazione del bacino PLS e il completamento del tubo verso l'impianto SX/EW. La società intende utilizzare sia la tecnologia convenzionale di lisciviazione per la produzione iniziale di ROM sia la tecnologia Nuton, quest'ultima destinata a produrre rame entro fine anno. Il progetto rappresenta un'aggiunta strategica alla capacità produttiva di rame americana, supportando le esigenze di sicurezza energetica e difensiva.
Gunnison Copper Corp (GCUMF) ha anunciado avances significativos en su mina Johnson Camp en Arizona, con el inicio del procesamiento de minerales previsto para julio de 2025 y las primeras ventas de cobre esperadas en septiembre. La compañía ha completado la Fase 1 de la construcción de la plataforma de lixiviación, con la Fase 2 próxima a comenzar. Las operaciones mineras ya han comenzado con material acumulado. El desarrollo de infraestructuras avanza según lo planeado, incluyendo la construcción de la carretera de acarreo, la instalación del sumidero PLS y la finalización de la tubería hacia la planta SX/EW. La empresa planea implementar tanto la tecnología convencional de lixiviación para la producción inicial de ROM como la tecnología Nuton, esta última con expectativas de producir cobre antes de fin de año. El proyecto representa una adición estratégica a la capacidad de producción de cobre de Estados Unidos, apoyando las necesidades de seguridad energética y de defensa.
Gunnison Copper Corp (GCUMF)는 애리조나에 위치한 Johnson Camp 광산에서 중요한 진전을 발표했으며, 광물 가공은 2025년 7월에 시작되고 첫 구리 판매는 9월에 예상됩니다. 회사는 침출 패드 1단계 건설을 완료했으며, 2단계도 곧 시작될 예정입니다. 채굴 작업은 이미 시작되어 자재가 적치되고 있습니다. 인프라 개발도 계획대로 진행 중이며, 운반 도로 건설, PLS 집수조 설치, SX/EW 공장으로의 파이프라인 완공이 포함됩니다. 회사는 초기 ROM 생산을 위한 기존 침출 기술과 Nuton 기술을 모두 도입할 계획이며, 후자는 연말 전에 구리를 생산할 것으로 기대됩니다. 이 프로젝트는 미국의 구리 생산 능력에 전략적으로 중요한 추가로, 에너지 및 국방 안보 수요를 지원합니다.
Gunnison Copper Corp (GCUMF) a annoncé des progrès significatifs à sa mine Johnson Camp en Arizona, avec le début du traitement des minerais prévu pour juillet 2025 et les premières ventes de cuivre attendues en septembre. La société a achevé la phase 1 de la construction de la plateforme de lixiviation, la phase 2 étant imminente. Les opérations minières ont déjà commencé avec du matériel mis en stock. Le développement des infrastructures progresse comme prévu, incluant la construction de la route d'accès, l'installation du bassin PLS et l'achèvement du pipeline vers l'usine SX/EW. L'entreprise prévoit d'utiliser à la fois la technologie de lixiviation conventionnelle pour la production initiale de ROM et la technologie Nuton, cette dernière devant produire du cuivre avant la fin de l'année. Ce projet constitue un ajout stratégique à la capacité de production de cuivre américaine, soutenant les besoins en sécurité énergétique et de défense.
Gunnison Copper Corp (GCUMF) hat bedeutende Fortschritte in seiner Johnson Camp Mine in Arizona bekannt gegeben. Die Mineralaufbereitung soll im Juli 2025 beginnen, und die ersten Kupferverkäufe werden für September erwartet. Das Unternehmen hat die Phase 1 des Baues der Laugungsplattform abgeschlossen, Phase 2 steht kurz bevor. Der Bergbaubetrieb hat bereits begonnen und Material wird zwischengelagert. Die Infrastrukturentwicklung verläuft planmäßig, einschließlich des Baus der Zufahrtsstraße, der Installation der PLS-Sammelgrube und der Fertigstellung der Rohrleitung zur SX/EW-Anlage. Das Unternehmen plant, sowohl die konventionelle Laugungstechnologie für die anfängliche ROM-Produktion als auch die Nuton-Technologie einzusetzen, wobei letztere voraussichtlich noch vor Jahresende Kupfer produzieren wird. Das Projekt stellt eine strategische Erweiterung der US-Kupferproduktionskapazität dar und unterstützt die Anforderungen an Energie- und Verteidigungssicherheit.
Positive
  • Mining operations have already commenced with active stockpiling of mineralized material
  • Phase-1 leach pad construction is complete with Phase-2 expected shortly
  • Project is progressing on schedule for July mineral processing start
  • Implementation of both conventional leach and advanced Nuton technology for copper production
  • Strategic positioning as a new American copper producer supporting critical mineral needs
Negative
  • None.

Phoenix, Arizona--(Newsfile Corp. - June 9, 2025) - Gunnison Copper Corp. (TSX: GCU) (OTCQB: GCUMF) (FSE: 3XS0) ("Gunnison" or the "Company") is pleased to announce that mineral processing will commence by July with first copper sales in September at the fully-permitted Johnson Camp Mine ("JCM"), in southeast Arizona.

Progress as of the Company's last update (see Gunnison news release dated March 21st) included:

  • Mining of mineralized material had commenced (Figure 1).
  • Material was being stockpiled in advance of the completion of the leach pads (Figure 2).
  • Leach pad Phase-1 was complete.
  • Phase-2 leach pad was expected in the near term.

Since the Company's last update, the Company is pleased to report that JCM construction activities are progressing as planned. The haul road to the run of mine oxide Phase-1 pad, PLS sump, culverts and overflow pond construction have started ahead of first acid irrigation. The pipelines from the leach pads to the SX/EW plant are nearing completion, and Phase-1 pad irrigation is anticipated by July, with first copper cathode from Run-of-mine (ROM) production using conventional leach technology scheduled for September. First copper using Nuton technology is expected before the end of the year.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2744/254883_ad99f12ba4c1198e_002.jpg

Figure 1 - Mining mineralized material from the JCM pit.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2744/254883_ad99f12ba4c1198e_002full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2744/254883_ad99f12ba4c1198e_003.jpg

Figure 2 - Leach Pad Overhead View, 8 million square feet with dimensions of approximately 1220m by 640m. Phase 1 shows the protective, crushed rock, over-liner material on bottom half of the image and Phase 2 shows the crusher pad and Nuton process equipment area. Phase 3 in the upper right corner is the Nuton heap location with liner and overliner being installed.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2744/254883_ad99f12ba4c1198e_003full.jpg

"Construction activity continues its fast pace and we are getting ever closer to first irrigation of oxide mine production at JCM SX/EW restart," states Robert Winton, SVP Operations of Gunnison Copper. He continues, "There is no better time than now to bring a new copper mine online in America, with this critical mineral playing a vital role in our energy and defense security. The efforts of our team and contractors have been second to none during the entire project."

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2744/254883_ad99f12ba4c1198e_004.jpg

Figure 3 - New LNG infrastructure storage tank and vaporizers to ensure grade 1 copper production at JCM.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2744/254883_ad99f12ba4c1198e_004full.jpg

ABOUT GUNNISON COPPER

Gunnison Copper Corp. is a multi-asset pure-play copper developer and producer that controls the Cochise Mining District (the district), containing 12 known deposits within an 8 km economic radius, in the Southern Arizona Copper Belt.

Its flagship asset, the Gunnison Copper Project, has a measured and indicated mineral resource containing over 831 million tons with a total copper grade of 0.31% (measured mineral resource of 191.3 million tons at 0.37% and indicated mineral resource of 640.2 million tons at 0.29%), and a preliminary economic assessment ("PEA") yielding robust economics including an NPV8% of $1.3Billion, IRR of 20.9%, and payback period of 4.1 years. It is being developed as a conventional operation with open pit mining, heap leach, and SX/EW refinery to produce finished copper cathode on-site with direct rail link.

The PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the conclusions reached in the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

In addition, Gunnison's Johnson Camp Asset, which is under construction with first copper production expected in Q3 2025, is fully funded by Nuton LLC, a Rio Tinto Venture, with a production capacity of up to 25 million lbs of finished copper cathode annually.

Other significant deposits controlled by Gunnison in the district, with potential to be economic satellite feeder deposits for Gunnison Project infrastructure, include Strong and Harris, South Star, and eight other deposits.

For additional information on the Gunnison Project, including the PEA and mineral resource estimate, please refer to the Company's technical report entitled "Gunnison Project NI 43-101 Technical Report Preliminary Economic Assessment" dated effective November 1, 2024 and available on SEDAR+ at www.sedarplus.ca.

Dr. Stephen Twyerould, Fellow of AUSIMM, President and CEO of the Company is a Qualified Person as defined by NI 43-101. Dr. Twyerould has reviewed and is responsible for the technical information contained in this news release.

For more information on Gunnison, please visit our website at www.GunnisonCopper.com.

ABOUT NUTON

Nuton is an innovative venture that aims to help grow Rio Tinto's copper business. At the core of Nuton is a portfolio of proprietary copper leaching technologies and capability. Nuton has the potential to economically unlock copper from hard-to-leach ores, including primary sulfides and, in doing so, increase domestic production of critical minerals to support the energy transition. Nuton technologies can achieve market-leading recovery rates and boost copper production in new, ongoing and historical operations, increasing resource utilization and maximizing their value.

With significantly lower energy and water needs than conventional concentrating and smelting, and the ability to produce copper cathode at the mine site, Nuton offers a reliable source of domestically produced copper, with a short mine-to-metal supply chain and the ambition to set industry-leading ESG credentials.

One of the key differentiators of Nuton is the ambition to produce the world's lightest environmental footprint copper while having at least one Positive Impact at each of its deployment sites, across its five pillars: water, energy, land, materials and society.

For more information, please visit https://nuton.tech.

For further information regarding this press release, please contact:

Gunnison Copper Corp.
Concord Place, Suite 300, 2999 North 44th Street, Phoenix, AZ, 85018

Shawn Westcott
T: 604.365.6681
E: info@GunnisonCopper.com
www.GunnisonCopper.com

Cautionary Note Regarding Forward-Looking Information

This news release contains "forward-looking information" concerning anticipated developments and events that may occur in the future. Forward-looking information contained in this news release includes, but is not limited to, statements with respect to: (i) the intention to deploy the Nuton® technology at the Johnson Camp mine and future production therefrom; (ii) the continued funding of the stage 2 work program by Nuton; (iii) the details and expected results of the stage two work program; (iv) timelines for future production and production capacity from the Company's mineral projects; (v) timelines for continued construction at JCM; (vI) the results of the preliminary economic assessment on the Gunnison Project; and (vIi) the exploration and development of the Company's mineral projects.

In certain cases, forward-looking information can be identified by the use of words such as "plans", "expects" or "does not expect", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might", "occur" or "be achieved" suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions or statements about future events or performance. Forward-looking information contained in this news release is based on certain factors and assumptions regarding, among other things, Nuton will continue to fund the stage 2 work program, the availability of financing to continue as a going concern and implement the Company's operational plans, the estimation of mineral resources, the realization of resource and reserve estimates, copper and other metal prices, the timing and amount of future development expenditures, the estimation of initial and sustaining capital requirements, the estimation of labour and operating costs (including the price of acid), the availability of labour, material and acid supply, receipt of and compliance with necessary regulatory approvals and permits, the estimation of insurance coverage, and assumptions with respect to currency fluctuations, environmental risks, title disputes or claims, and other similar matters. While the Company considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include risks related to the Company not obtaining adequate financing to continue operations, Nuton failing to continue to fund the stage 2 work program, the breach of debt covenants, risks inherent in the construction and operation of mineral deposits, including risks relating to changes in project parameters as plans continue to be redefined including the possibility that mining operations may not be sustained at the Gunnison Copper Project, risks related to the delay in approval of work plans, variations in mineral resources and reserves, grade or recovery rates, risks relating to the ability to access infrastructure, risks relating to changes in copper and other commodity prices and the worldwide demand for and supply of copper and related products, risks related to increased competition in the market for copper and related products, risks related to current global financial conditions, risks related to current global financial conditions on the Company's business, uncertainties inherent in the estimation of mineral resources, access and supply risks, risks related to the ability to access acid supply on commercially reasonable terms, reliance on key personnel, operational risks inherent in the conduct of mining activities, including the risk of accidents, labour disputes, increases in capital and operating costs and the risk of delays or increased costs that might be encountered during the construction or mining process, regulatory risks including the risk that permits may not be obtained in a timely fashion or at all, financing, capitalization and liquidity risks, risks related to disputes concerning property titles and interests, environmental risks and the additional risks identified in the "Risk Factors" section of the Company's reports and filings with applicable Canadian securities regulators.

Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Accordingly, readers should not place undue reliance on forward-looking information. The forward-looking information is made as of the date of this news release. Except as required by applicable securities laws, the Company does not undertake any obligation to publicly update or revise any forward-looking information.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/254883

FAQ

When will Gunnison Copper (GCUMF) begin mineral processing at Johnson Camp Mine?

Gunnison Copper will begin mineral processing at Johnson Camp Mine by July 2025, with first copper sales expected in September 2025.

What technologies will GCUMF use for copper production at Johnson Camp?

GCUMF will use both conventional leach technology for initial ROM production and Nuton technology, with Nuton-based production expected before the end of 2025.

What is the current status of the Johnson Camp Mine leach pad construction?

Phase-1 of the leach pad is complete, and Phase-2 is expected in the near term. The total pad area is approximately 8 million square feet.

Where is the Johnson Camp Mine located and what is its significance?

Johnson Camp Mine is located in southeast Arizona and represents a strategic new copper mine supporting America's energy and defense security needs.

What infrastructure developments are currently underway at Johnson Camp Mine?

Current developments include haul road construction, PLS sump installation, culverts, overflow pond construction, and completion of pipelines from leach pads to the SX/EW plant.