Quarterly Activities Report June 2026
Rhea-AI Summary
Galan Lithium (OTC:GLNLF) reported its June 2026 quarter marked its transition from developer to producer at the 100% owned Hombre Muerto West (HMW) project in Argentina, completing Phase 1 construction, wet commissioning and producing first processed lithium chloride.
The company is ramping up operations toward stabilised production at an annualised rate of 4 ktpa LCE in 2026, targeting first lithium chloride concentrate and product sales in H2 2026. Galan has built circa 10,000 t LCE brine inventory in evaporation ponds to support the ramp-up. Phase 1 expansion to 5.2 ktpa LCE remains on track, with new pond construction due to start in the September 2026 quarter and capacity uplift targeted for H1 2027. Galan ended the quarter with A$35.5 million cash and no debt, holds permits for a Phase 2 expansion to 21 ktpa LCE, and plans staged growth up to 60 ktpa LCE.
Positive
- Transition to producer at HMW with first processed lithium chloride completed in June 2026 quarter
- Ramp-up target stabilised production at 4 ktpa LCE and first sales in H2 2026
- Inventory buffer ~10,000 t LCE brine in ponds for sustained ramp-up
- Phase 1 expansion from 4 ktpa to 5.2 ktpa LCE targeted by H1 2027
- Strong balance sheet A$35.5 million cash and no debt at 30 June 2026
- Permitted growth construction permits in place for Phase 2 at 21 ktpa LCE and staged plan to 60 ktpa LCE
Negative
- Severe winter weather temporarily halted plant operations, slowing evaporation and productivity during the ramp-up phase
AI-generated analysis. How Rhea-AI works. Not financial advice.
Highlights
Production ramp-up continues with inventory of processed lithium chloride building in final evaporation ponds
Excellent rejection of impurities from the nanofiltration plant, consistent with plant design specifications
Optimisation phase now underway, targeting stabilised production at an annualised rate of 4 ktpa LCE; lithium chloride concentrate and first product sales targeted in H2 2026
Circa 10,000 t LCE brine inventory in the evaporation ponds provides immediate feedstock for a sustained production ramp-up
Expansion of Phase 1 from 4 ktpa LCE to 5.2 ktpa LCE on track; pond construction works starting in September quarter, targeting a capacity uplift in H1 2027
Strong cash position of A
$35.5 million with no debt
PERTH, AU / ACCESS Newswire / July 30, 2026 / Galan Lithium Limited (Galan or the Company) presents its quarterly activities report for the quarter ended 30 June 2026, along with activities up to the date of this release.
Figure 1. Final evaporation pond with processed brine.

The June 2026 quarter marked Galan's transition from developer to producer, with the successful completion of wet commissioning of the plant at the Company's
The Company is now undertaking a ramp-up phase where plant operations will be optimised ahead of achieving stabilised production at an annualised rate of 4 ktpa LCE. Galan remains on track to produce lithium chloride concentrate and deliver first product sales in H2 2026.
Juan Pablo (JP) Vargas de la Vega, Managing Director commented:
"The June quarter was a defining period for Galan. Following completion of Phase 1 construction, we successfully commissioned the HMW plant and produced our first processed lithium chloride, with the mining operation now de-risked from start to finish. To our knowledge, Galan will be the only greenfield lithium project coming online in 2026 and, with circa 10,000 t LCE of brine inventory ready to process, we are focused on a disciplined ramp-up to first product sales in the second half of the year."
Project Execution - Hombre Muerto West (HMW)
Galan announced in April 2026 that all major processing infrastructure at HMW, including the nanofiltration plant, evaporation ponds and associated process facilities, had been installed, with HMW transitioning into its testing and commissioning phase.
Following the successful execution of electrical and mechanical testing programs, Galan transitioned HMW into wet commissioning. The nanofiltration plant was first commissioned with raw brine at low pressures before being fed with pre-concentrated brine, with around
Figure 2. Operational HMW nanofiltration plant.

As announced in May 2026, processed lithium chloride has been discharged into the final evaporation ponds, where water will be removed and the contained lithium concentrated through evaporation. Following this final evaporation period, lithium chloride concentrate with a
Figure 3. Processed brine flowing into final evaporation pond.

It is common within the lithium brine industry for productivity gains in the plant and ponds to be realised during the warmer seasons where brine temperatures are elevated and solar and wind evaporation is at its greatest. Conversely productivity is generally less in the cooler seasons. Recent winter weather conditions at site have been severe resulting in lower evaporation and periods where the plant operations were temporarily placed on hold for safety reasons. As a result of the precautions there were no injuries or safety incidents reported. Notwithstanding the challenging conditions, the Company is confident of achieving first lithium chloride concentrate production and sales in the second half of 2026 and achieving a stabilised production rate (4 ktpa LCE target) within 2026.
In relation to the expansion of Phase 1 production to 5.2 ktpa LCE, pond construction works will commence within the September 2026 quarter. The nanofiltration plant has been designed with the flexibility to support this expanded rate of production, so no associated plant modifications will be required. The production capacity uplift is targeted for H1 2027 and is enabled by the existing lithium chloride inventory of c.10,000 t LCE, which has been accumulated over a period of more than 2 years.
Galan holds construction permits for Phase 2 (21 ktpa LCE) and plans for a staged, low-risk production growth pathway across four phases to up to 60 ktpa LCE. The scale and quality of the HMW resource, a top 10 global lithium resource by contained LCE, underpins the long-term production potential of the project as a significant supplier into the global lithium market.
Figure 4. HMW phased development plan to 60 ktpa LCE.
Galan continues to work closely with its offtake and operating partner, Authium Limited, and gratefully acknowledges the ongoing support of the Federal Government of Argentina, the Provincial Government of Catamarca and its local stakeholders, as well as the benefits of Argentina's RIGI investment framework in supporting HMW's development.
Figure 5. Operators undergoing training in the nanofiltration plant electrical room.

Greenbushes South (WA)
During the quarter, Galan was awarded co-funding of up to
Financial Position
Cash outflows during the June 2026 quarter were primarily directed to the completion of construction and the commissioning of the HMW processing plant, evaporation pond works and associated site infrastructure, as well as corporate overheads.
The closing cash balance as at 30 June 2026 was A
Payments to related parties during the quarter totalled approximately
The Galan Board has authorised the release of this June 2026 Quarterly Activities Report.
For further information contact:
COMPANY Juan Pablo ("JP") Vargas de la Vega | MEDIA Matt Worner |
About Galan
Galan Lithium Limited (ASX:GLN) is an ASX-listed lithium exploration and development business. Galan's flagship assets comprise two world-class lithium brine projects, HMW and Candelas, located on the Hombre Muerto Salar in Argentina, within South America's 'lithium triangle'. Galan is distinguished by:
The size of its mineral resource. HMW is placed within the top 10 producing or development lithium projects globally,1
The purity of its mineral resource. The HMW mineral resource has the lowest impurity profile of any published lithium brine resource in Argentina,
Positioning on the cost curve. When in production, HMW is profiled to be in the first quartile of the industry cost curve,2
Near term production with permitted expansion. Galan is on track for first lithium chloride production in 2026 and has the construction permits to expand HMW to 21 ktpa LCE,
The RIGI. The RIGI is a large-scale investment framework in Argentina which provides income tax benefits, 30 years of fiscal stability and a range of other financial benefits. Galan and Rio Tinto are the only recipients of the RIGI within the lithium industry in Argentina, and
Exploration licences at Greenbushes South in Western Australia, close to and just south of the Tier 1 Greenbushes Lithium Mine.
1 S&P Global Metals & Mining.
2 Wood Mackenzie, iLi Markets
SOURCE: Galan Lithium Limited