STOCK TITAN

G Mining Ventures Announces Formal Construction Decision for the Oko West Gold Project and Provides Project Development Update

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) announced its Board approved full construction of the 100%‑owned Oko West Gold Project with an initial capital cost of $973M. Detailed engineering is 36% complete and $334M (33% of capex) is committed; total project expenditure to date is $156M (including $110M spent plus $46M prepayments). The project is fully permitted under Environmental Permit No. 20230912‑RGIGM (issued Aug 29, 2025; five‑year term). Early works and procurement are progressing; first gold is targeted in H2 2027. Workforce totals 710 (over 80% Guyanese); TRIFR is 0.33. Major suppliers include Wärtsilä, Komatsu, Metso, and FLSmidth.

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) ha annunciato che il Consiglio ha approvato la costruzione completa della proprietà Oko West Gold Project al 100% detenuta, con un costo iniziale di capitale di $973M. L'ingegneria dettagliata è 36% completa e $334M (33% del capex) è impegnato; la spesa totale del progetto ad oggi è di $156M (incluse $110M già spesi e $46M di anticipi). Il progetto è completamente autorizzato ai sensi della Environmental Permit No. 20230912‑RGIGM (emessa il 29 agosto 2025; validità di cinque anni). I lavori preliminari e gli acquisti procedono; la prima consegna d'oro è prevista nel H2 2027. L'organico ammonta a 710 (più dell'80% dei Guyanesi); il TRIFR è 0.33. I principali fornitori includono Wärtsilä, Komatsu, Metso e FLSmidth.

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) anunció que su Junta aprobó la construcción completa de la propiedad 100% propiedad de Oko West Gold Project con un costo inicial de capital de $973M. La ingeniería detallada está 36% completa y $334M (33% del capex) está comprometido; el gasto total del proyecto a la fecha es de $156M (incluidos $110M gastados y $46M de prepagos). El proyecto está totalmente permitido bajo el Permiso Ambiental No. 20230912‑RGIGM (emitido el 29 de agosto de 2025; plazo de cinco años). Los trabajos iniciales y las adquisiciones están en progreso; la primera onza de oro se apunta para la H2 2027. La fuerza laboral totaliza 710 (más del 80% guyanés); el TRIFR es 0.33. Los principales proveedores incluyen Wärtsilä, Komatsu, Metso y FLSmidth.

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) 이사회가 소유주 100%의 Oko West Gold Project의 전면 건설을 승인했다고 발표했습니다. 초기 자본 비용은 $973M입니다. 상세 엔지니어링은 36% 완료되었고 $334M (자본 지출의 33%)이 약정되었습니다; 현재까지의 총 프로젝트 지출은 $156M이며 $110M 지출 + $46M 예치금을 포함합니다. 이 프로젝트는 환경 허가 No. 20230912‑RGIGM에 따라 완전 허가를 받았으며(발급일: 2025년 8월 29일; 5년 유효), 조기 작업 및 조달이 진행 중이고 초기 금 생산은 2027년 상반기를 목표로 하고 있습니다. 고용 인원은 710명(80% 이상은 가이아나 사람)이고 TRIFR은 0.33입니다. 주요 공급업체로는 Wärtsilä, Komatsu, Metso, FLSmidth가 있습니다.

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) a annoncé que son conseil d'administration a approuvé la construction complète du projet Oko West Gold Project détenu à 100% avec un coût d'investissement initial de $973M. L'ingénierie détaillée est à 36% terminée et $334M (33% du capex) sont engagés; les dépenses totales du projet à ce jour s'élèvent à $156M (dont $110M déjà dépensés et $46M d'acomptes). Le projet est entièrement autorisé sous le Permis Environnemental No. 20230912‑RGIGM (émis le 29 août 2025; durée de cinq ans). Les travaux préliminaires et les achats progressent; la première or est visée pour H2 2027. Les effectifs totalisent 710 (plus de 80% Guyanais); le TRIFR est 0,33. Les principaux fournisseurs incluent Wärtsilä, Komatsu, Metso et FLSmidth.

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) gab dem Vorstand bekannt, dass der Bau des zu 100% im Besitz befindlichen Oko West Gold Project vollständig genehmigt wurde, mit einer anfänglichen Kapitalkosten von $973M. Die detaillierte Planung ist zu 36% abgeschlossen und $334M (33% der Capex) sind committed; bisherige Gesamtausgaben des Projekts belaufen sich auf $156M (einschließlich $110M Ausgaben und $46M Vorauszahlungen). Das Projekt ist vollständig genehmigt unter Umweltgenehmigung Nr. 20230912‑RGIGM (ausgestellt am 29. August 2025; fünf Jahre Laufzeit). Früharbeiten und Beschaffung schreiten voran; der erste Goldausstoß wird für H2 2027 angestrebt. Die Belegschaft beträgt 710 (über 80% Guyaner); der TRIFR liegt bei 0,33. Wichtige Lieferanten umfassen Wärtsilä, Komatsu, Metso und FLSmidth.

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) أعلنت أن مجلس الإدارة وافق على البناء الكامل لمشروع Oko West Gold Project المملوك بنسبة 100%، بتكلفة رأس مال ابتدائية قدرها $973M. الهندسة التفصيلية مكتملة بـ36% و$334M (33% من رأس المال المستثمر) مُلتزم به؛ الإنفاق الكلي للمشروع حتى اليوم هو $156M (بما في ذلك $110M مُنفقة و$46M دفعات مقدمة). المشروع مُرخّص بالكامل بموجب تصريح البيئة No. 20230912‑RGIGM (المصدر في 29 أغسطس 2025؛ مدة خمس سنوات). الأعمال الأولية والشراء في تقدم؛ والذهب الأول مستهدف في H2 2027. إجمالي القوة العاملة 710 (أكثر من 80% من جويانيين); TRIFR يساوي 0.33. الموردون الرئيسيون يشملون Wärtsilä و Komatsu و Metso و FLSmidth.

G Mining Ventures (TSX:GMIN, OTCQX:GMINF) 公布其董事会已批准全资拥有的 Oko West Gold Project 的完整建设,初始资本成本为 $973M。详细工程进展达到 36%,并有 $334M(占资本支出33%)已承诺;迄今为止项目总支出为 $156M(其中已花费$110M,预付款$46M)。该项目在环境许可编号 20230912‑RGIGM 下获得< b>全面许可(发证日期:2025年8月29日;有效期五年)。早期工作与采购进展中;首次产金计划在 2027年下半年。劳动力总数为 710(其中超过80%为圭亚那籍人员);TRIFR 为 0.33。主要供应商包括 Wärtsilä、Komatsu、Metso 和 FLSmidth。

Positive
  • Board approved initial capex of $973M
  • $334M committed to construction (33% of capex)
  • Total project expenditure of $156M to date
  • Environmental permit issued Aug 29, 2025 (five‑year term)
  • Detailed engineering 36% complete
  • First gold targeted in H2 2027
Negative
  • Pre‑production cost line reduced 40.6% versus FS
  • Contingency reduced to 8.8%
  • Indirect construction costs increased due to added equipment
  • Mining license not yet issued; expected in Q4 2025

BROSSARD, QC, Oct. 23, 2025 /PRNewswire/ - G Mining Ventures Corp. ("GMIN" or the "Corporation") (TSX:GMIN, OTCQX:GMINF) is pleased to announce that its Board of Directors has formally approved the commencement of full construction of its 100%-owned Oko West Gold Project ("Oko West" or the "Project") in Guyana, following the completion of permitting and financing milestones. Additionally, GMIN is excited to provide a progress update on Project construction activities, including engineering, procurement and early works activities. Unless otherwise stated, all dollar amounts in this news release are expressed in U.S. dollars.

  • The Board of Directors has approved a positive construction decision for the Oko West Gold Project, with an initial capital cost of $973 million
  • Detailed engineering is 36% complete
  • Procurement and commitments for long-lead items are progressing, with $334 million committed to date, representing 33% of the total initial capital budget
  • Early works construction activities are advancing on schedule

"The official launch of construction at Oko West marks a major milestone in GMIN's evolution into an intermediate gold producer," said Louis-Pierre Gignac, President & Chief Executive Officer. "With financing secured, we are advancing this fully permitted, world-class project using the same disciplined, self-perform approach that delivered Tocantinzinho safely, on time and on budget. Oko West will build on that success as the next cornerstone of our growth strategy, with first gold targeted for the second half of 2027".

Project Update (as of September 30, 2025)

Project Cost

  • $110M has been spent, with an additional $46M in prepayments, for a total expenditure of $156M
  • Total commitments for project construction now stand at $334M (including amounts spent), representing 33% of the total initial capital cost estimate of $973M

Safety Record & Workforce

  • Total workforce of 710 of which 520 are employees and 190 are contractors
  • Over 80% of workforce are Guyanese nationals
  • 596,551 hours worked to date with one recordable incident to date, resulting in a Total Recordable Incident Rate (TRIFR) of 0.33
  • Completed a technical training program in partnership with the Ministry of Labour of Guyana, benefiting 200 residents from region 7, the administrative region hosting the Project.

Sustainability & Permitting

  • Permitting: Fully permitted under Environmental Permit No. 20230912-RGIGM, issued by the Environmental Protection Agency ("EPA") on August 29, 2025. The permit is valid for five years and authorizes both construction and operational activities
  • Licensing: The Mining License application has been submitted to the Guyana Geology and Mines Commission ("GGMC") and is expected to be issued in Q4 2025
  • Environmental and Social Management: The Corporation is advancing the implementation of a comprehensive Environmental and Social Management System ("ESMS") addressing biodiversity conservation, water quality, waste management, air and noise control
  • Community Engagement: A Community Development Committee has been established in Region 7 to guide social investment initiatives in education, healthcare, and infrastructure

Engineering & Procurement

  • Detailed Engineering: Approximately 36% complete
  • Procurement: Long-lead items have been ordered, securing pricing for key equipment from reputable high-quality suppliers, including:
    • Power Plant: Supplied by Wärtsilä
    • Mining Equipment: Primary open pit and support equipment from Komatsu, with the first mining shovel scheduled for commissioning in Q4 2025
    • Processing Equipment: Grinding mills, gyratory crusher, apron feeders, and pre-leach thickener from Metso. Gravity circuit, intensive leach reactor, and gold room supplied by FLSmidth, with additional mechanical packages sourced from other suppliers

Early Works Construction

  • Camp facility: Expansion of the exploration camp to a capacity of 425 beds; first two permanent dorms due in October; barge landing satellite camp completed
  • Site clearing: 15 % completed
  • Access: 12 km external road operational, reducing travel time by three hours on return trip
  • Mass excavation: 100% complete at permanent camp; 93% at barge landing
  • Concrete: 2,815 m3 poured to date, 6% of the project
  • Tailings storage facility: Coffer dam completed; foundation prep and dam construction underway

Approved Initial Capital Cost

  • Board approved initial capex: $973M, in line with the Feasibility Study ("FS") estimate
  • Indirect costs: Increased due to additional construction equipment purchases
  • Pre-production revenue: 30,000 ounces ("oz") at $3,200/oz vs $2,500/oz in FS
    Contingency (incl. pre-production revenue): 8.8%

Table 1- Initial Capital Cost

Initial Capital Cost Estimate

(US$ 000s)

Feasibility
Study

Approved
Initial CAPEX

Variance

% Variance

Infrastructure

105,889

105,976

87

0.1 %

Power & Electrical

110,797

108,553

(2,244)

-2.0 %

Water Management

22,882

23,663

782

3.4 %

Surface Operations

41,051

44,579

3,528

8.6 %

Mining

104,078

105,216

1,138

1.1 %

Process Plant

191,639

192,774

1,135

0.6 %

Construction Indirect

134,534

146,102

11,568

8.6 %

General Services & Owner's Costs

137,385

143,963

6,577

4.8 %

Pre-Production

39,157

23,246

(15,912)

-40.6 %

Contingency

84,962

78,598

(6,364)

-7.5 %

Total

972,374

972,669

295

0.0 %

Total excluding Pre-Production Revenue

1,041,389

1,061,071

19,682

1.9 %

Pre-Production Revenue

(69,016)

(88,402)

(19,386)

28.1 %

About G Mining Ventures Corp.

G Mining Ventures Corp. is a mining company engaged in the acquisition, exploration and development of precious metal projects to capitalize on the value uplift from successful mine development. GMIN is well-positioned to grow into the next mid-tier precious metals producer by leveraging strong access to capital and proven development expertise. GMIN is currently anchored by the Tocantinzinho Mine in Brazil, supported by the Gurupi Project in Brazil and the Oko West Project in Guyana — all with significant exploration upside and located in mining-friendly jurisdictions. GMIN trades on the TSX under the symbol "GMIN".

Cautionary Statement on Forward-Looking Information

All statements, other than statements of historical fact, contained in this press release constitute "forward-looking information" and "forward-looking statements" within the meaning of certain securities laws and are based on expectations and projections as of the date of this press release. Forward-looking statements contained in this press release include, without limitation, those related to (i) the construction and operation of Oko West creating about 1,270 jobs over the life of mine; (ii) the initial equipment deliveries being expected in Q3-2025 and enabling GMIN to start earthworks on site; (iii) and (iv) in general, the section entitled "About G Mining Ventures Corp."; as well as the quoted comments of GMIN's President & Chief Executive Officer.

Forward-looking statements are based on expectations, estimates and projections as of the time of this press release. Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by the Corporation as of the time of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. These estimates and assumptions may prove to be incorrect. Such assumptions include, without limitation, those relating to the price of gold and currency exchange rates, and those underlying the items listed in the above section entitled "About G Mining Ventures Corp.".

Many of these uncertainties and contingencies can directly or indirectly affect, and could cause, actual results to differ materially from those expressed or implied in any forward-looking statements. There can be no assurance that, notably but without limitation, (i) a formal construction for Oko West will be made in H2-2025, or at all; (ii) Oko West will progress in alignment with the highest environmental and social standards; (iii) Guyana's regulatory environment will ensure timely decision-making allowing GMIN to achieve project milestones; (iv) Guyana will remain attractive for mining investment; (v) Oko West will advance responsibly and on schedule; (vi) GMIN will achieve its stated objectives for Oko West; or (vii) TZ and Oko West will grow GMIN into the next intermediate producer, as future events could differ materially from what is currently anticipated by the Corporation. In addition, there can be no assurance that Brazil and/or Guyana will remain mining friendly and prospective jurisdictions.

By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. Forward-looking statements are provided for the purpose of providing information about management's expectations and plans relating to the future. Readers are cautioned not to place undue reliance on these forward-looking statements as a number of important risk factors and future events could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates, assumptions and intentions expressed in such forward-looking statements. All of the forward-looking statements made in this press release are qualified by these cautionary statements and those made in the Corporation's other filings with the securities regulators of Canada including, but not limited to, the cautionary statements made in the relevant sections of the Corporation's (i) Annual Information Form dated March 27, 2025, for the financial year ended December 31, 2024, and (ii) Management Discussion & Analysis. The Corporation cautions that the foregoing list of factors that may affect future results is not exhaustive, and new, unforeseeable risks may arise from time to time. The Corporation disclaims any intention or obligation to update or revise any forward-looking statements or to explain any material difference between subsequent actual events and such forward-looking statements, except to the extent required by applicable law.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/g-mining-ventures-announces-formal-construction-decision-for-the-oko-west-gold-project-and-provides-project-development-update-302592599.html

SOURCE G Mining Ventures Corp

FAQ

What is the approved initial capital cost for Oko West (GMINF)?

The Board approved an initial capital cost of $973 million for Oko West.

When does G Mining (GMINF) expect first gold from Oko West?

G Mining targets first gold in the second half of 2027.

How much has G Mining (GMINF) committed and spent on Oko West to date?

Total commitments are $334M (33% of capex) and total expenditure is $156M including prepayments.

Has Oko West received environmental permitting for construction and operations?

Yes — Environmental Permit No. 20230912‑RGIGM was issued on Aug 29, 2025 and is valid for five years.

Which major equipment suppliers are contracted for Oko West (GMINF)?

Key suppliers named include Wärtsilä (power), Komatsu (mining equipment), Metso and FLSmidth (processing).

What workforce and safety metrics has G Mining reported for Oko West?

Workforce is 710 (520 employees, 190 contractors), >80% Guyanese, with a TRIFR of 0.33.
G Mining Ventures Corp.

OTC:GMINF

GMINF Rankings

GMINF Latest News

GMINF Stock Data

3.90B
60.91M
22.12%
41.88%
Other Precious Metals & Mining
Basic Materials
Link
Canada
Québec