Highland Copper Provides Update on Michigan State Grant and Other Catalyts at the Copperwood Project
Highland Copper (OTCQB: HDRSF) provided significant updates on its 100%-owned Copperwood Project in Michigan. The project is under consideration for a $50 million grant from the Michigan Economic Development Corporation, with Wakefield Township directly requesting the infrastructure grant from the Michigan legislature as an alternative path.
The company has awarded key Front-End Engineering and Design (FEED) contracts to multiple firms: DRA Global for mine and process plant engineering, Foth for water management, and Tetra Tech for the Tailings Disposal Facility. Highland plans to transition to Phase 2 engineering in Q3 2025, targeting 35% completion for main components and 85% for TDF by Q1 2026.
Additionally, preliminary metallurgical optimization results suggest potential for a mill-float-mill-float circuit configuration, with final results expected in Q3 2025. The company has also substantially completed its on-site mitigation activities, including planting 20,000 trees in newly constructed wetland areas.
Highland Copper (OTCQB: HDRSF) ha fornito aggiornamenti significativi sul suo progetto Copperwood, di cui detiene il 100%, situato nel Michigan. Il progetto è in fase di valutazione per un finanziamento di 50 milioni di dollari da parte della Michigan Economic Development Corporation, mentre il comune di Wakefield Township ha richiesto direttamente alla legislatura del Michigan il contributo per le infrastrutture come percorso alternativo.
L'azienda ha assegnato contratti chiave per l'Ingegneria e Progettazione di Front-End (FEED) a diverse società: DRA Global per l’ingegneria della miniera e dell’impianto di processo, Foth per la gestione delle acque e Tetra Tech per la struttura di smaltimento delle scorie. Highland prevede di passare alla fase 2 dell’ingegneria nel terzo trimestre del 2025, puntando a un 35% di completamento per i componenti principali e l’85% per la struttura di smaltimento delle scorie entro il primo trimestre del 2026.
Inoltre, i risultati preliminari dell’ottimizzazione metallurgica suggeriscono la possibilità di una configurazione a circuito mill-float-mill-float, con risultati definitivi attesi nel terzo trimestre del 2025. L’azienda ha inoltre quasi completato le attività di mitigazione in loco, tra cui la piantumazione di 20.000 alberi in nuove aree umide create appositamente.
Highland Copper (OTCQB: HDRSF) proporcionó actualizaciones importantes sobre su proyecto Copperwood, del cual posee el 100%, ubicado en Michigan. El proyecto está siendo considerado para una subvención de 50 millones de dólares por parte de la Michigan Economic Development Corporation, mientras que el municipio de Wakefield Township solicitó directamente a la legislatura de Michigan la subvención para infraestructura como una vía alternativa.
La compañía ha adjudicado contratos clave de Ingeniería y Diseño de Front-End (FEED) a varias firmas: DRA Global para la ingeniería de la mina y planta de procesamiento, Foth para la gestión del agua y Tetra Tech para la instalación de disposición de relaves. Highland planea pasar a la fase 2 de ingeniería en el tercer trimestre de 2025, con el objetivo de alcanzar un 35% de avance en los componentes principales y 85% en la instalación de disposición de relaves para el primer trimestre de 2026.
Además, los resultados preliminares de la optimización metalúrgica sugieren la posibilidad de una configuración de circuito molino-flotación-molino-flotación, con resultados finales esperados en el tercer trimestre de 2025. La compañía también ha completado en gran medida sus actividades de mitigación en el sitio, incluyendo la plantación de 20,000 árboles en áreas de humedales recién construidas.
Highland Copper (OTCQB: HDRSF)는 미시간에 위치한 100% 소유 Copperwood 프로젝트에 대한 중요한 업데이트를 제공했습니다. 이 프로젝트는 미시간 경제개발공사(Michigan Economic Development Corporation)로부터 5천만 달러 보조금을 받을 가능성이 검토 중이며, Wakefield 타운십은 인프라 보조금을 미시간 주 의회에 직접 요청하는 대체 경로를 모색하고 있습니다.
회사는 주요 프론트엔드 엔지니어링 및 설계(FEED) 계약을 여러 업체에 수주했습니다: 광산 및 처리 공장 엔지니어링은 DRA Global, 수자원 관리는 Foth, 폐석 처리 시설은 Tetra Tech가 맡았습니다. Highland는 2025년 3분기에 2단계 엔지니어링으로 전환할 계획이며, 2026년 1분기까지 주요 구성 요소 35%, 폐석 처리 시설 85% 완성을 목표로 하고 있습니다.
또한, 예비 야금 최적화 결과는 밀-플로트-밀-플로트 회로 구성이 가능함을 시사하며, 최종 결과는 2025년 3분기에 나올 예정입니다. 회사는 현장 완화 활동도 상당 부분 완료했으며, 새로 조성된 습지 지역에 20,000그루의 나무를 심었습니다.
Highland Copper (OTCQB : HDRSF) a fourni des mises à jour importantes concernant son projet Copperwood, dont il détient 100 %, situé dans le Michigan. Le projet est en cours d’examen pour une aide financière de 50 millions de dollars de la Michigan Economic Development Corporation, tandis que la municipalité de Wakefield Township a directement sollicité cette subvention pour les infrastructures auprès de la législature du Michigan comme voie alternative.
L’entreprise a attribué des contrats clés de Front-End Engineering and Design (FEED) à plusieurs sociétés : DRA Global pour l’ingénierie de la mine et de l’usine de traitement, Foth pour la gestion de l’eau, et Tetra Tech pour l’installation de stockage des résidus. Highland prévoit de passer à la phase 2 de l’ingénierie au troisième trimestre 2025, visant un achèvement de 35 % des composants principaux et de 85 % pour l’installation de stockage des résidus d’ici le premier trimestre 2026.
De plus, les résultats préliminaires de l’optimisation métallurgique suggèrent la possibilité d’une configuration en circuit moulin-flottation-moulin-flottation, les résultats définitifs étant attendus au troisième trimestre 2025. La société a également largement achevé ses activités d’atténuation sur site, notamment la plantation de 20 000 arbres dans de nouvelles zones humides créées.
Highland Copper (OTCQB: HDRSF) gab bedeutende Updates zu seinem zu 100 % im Besitz befindlichen Copperwood-Projekt in Michigan bekannt. Das Projekt wird für einen 50-Millionen-Dollar-Zuschuss von der Michigan Economic Development Corporation in Betracht gezogen, wobei Wakefield Township direkt bei der Michigan-Legislative den Infrastrukturzuschuss als alternativen Weg beantragt hat.
Das Unternehmen hat wichtige Front-End Engineering und Design (FEED)-Verträge an mehrere Firmen vergeben: DRA Global für Bergbau- und Anlagenplanung, Foth für Wassermanagement und Tetra Tech für die Ablagerungseinrichtung für Tailings. Highland plant, im dritten Quartal 2025 in die Phase 2 der Planung überzugehen und strebt bis zum ersten Quartal 2026 eine 35% Fertigstellung der Hauptkomponenten und 85% der Tailings-Entsorgungseinrichtung an.
Zusätzlich deuten vorläufige metallurgische Optimierungsergebnisse auf eine mögliche Mill-Float-Mill-Float-Schaltung hin, wobei die endgültigen Ergebnisse im dritten Quartal 2025 erwartet werden. Das Unternehmen hat außerdem seine vor Ort durchgeführten Minderungsmaßnahmen weitgehend abgeschlossen, darunter die Pflanzung von 20.000 Bäumen in neu angelegten Feuchtgebieten.
- Potential $50 million state infrastructure grant with strong local support
- Progress in FEED contracts with multiple engineering firms advancing toward construction decision
- Successful preliminary metallurgical optimization results with potential for enhanced grade-recovery
- Substantial completion of environmental mitigation activities, demonstrating project advancement
- On track for construction decision in 2026
- State grant still requires final approval from Senate Appropriations Committee
- Project still requires significant engineering work to reach completion targets
- Final metallurgical test results pending until Q3 2025
VANCOUVER, British Columbia, July 02, 2025 (GLOBE NEWSWIRE) -- Highland Copper Company Inc. (TSXV: HI; OTCQB: HDRSF) (“Highland” or the “Company”) is pleased to provide an update on its
Michigan State Grant: As previously announced, the Copperwood project is under consideration for a
In parallel, Wakefield Township, where the Copperwood project resides, has taken the proactive step of directly requesting a
The proposed grant has the potential to unlock important economic development in Gogebic County, aimed at upgrading local roads, power, and telecommunications, infrastructure that will also support the development of the Copperwood project. The grant is in the form of a state budget request for Wakefield township, sponsored by Representative Greg Markkanen, and is viewed by the local community as a generational opportunity to attract much-needed jobs and opportunities in the Western Upper Peninsula.
"The people of Wakefield Township and the Western Upper Peninsula are squarely behind the Copperwood Project. It will create jobs and opportunities while balancing the environment," stated Wakefield Township Supervisor Mandy Lake. This direct appeal from Wakefield township highlights the project's broad support, which also extends to state and federal leaders. This includes federal Congressman Jack Bergman and all key Upper Peninsula state legislators who emphasize Copperwood's critical role in domestic copper production, national security, and creating sustainable American jobs while upholding stringent environmental safeguards.
Detailed Engineering: Following the announcement that Highland awarded the Front-End Engineering and Design (“FEED”) contracts for mine engineering and process plant engineering to DRA Global, the company has now finalized the resourcing for its other engineering workstreams. Specifically, Highland awarded the FEED contract for overall site water management to Foth Infrastructure and Environment LLC (“Foth”) and the FEED contract for the Tailings Disposal Facility (“TDF”) to Tetra Tech. Each engineering team has completed a comprehensive review of all historical project data and is progressing toward finalizing the engineering design criteria by Q3 2025. Concurrently, several opportunities to de-risk and optimize the project are being evaluated through trade-off studies. Further updates will be provided as the trade-offs studies are concluded.
Highland plans to transition into Phase 2 of its engineering program during Q3 2025. The objectives for Phase 2 include advancing mine engineering, process plant engineering, and water management engineering to approximately
Metallurgical Test Work: In May 2025, Highland announced the successful completion of its metallurgical drill program, with 400 kilograms of core samples sent to Base Metallurgical Laboratories Ltd. As the samples were collected from the same locations as the 2018 SGS test work campaign, the initial objective was to produce rougher kinetic results within the same confidence interval as the 2018 results, which has been successfully achieved. This outcome provided confidence to proceed with the metallurgical and reagent optimization phase.
Preliminary optimization results suggest potential for a mill-float-mill-float (MF2) circuit configuration combined with a simplified reagent scheme. The next steps include evaluating ultrafine flotation technology for both rougher and cleaner applications, followed by lock-cycle variability testing on the finalized circuit configuration. The key purpose of evaluating ultrafine flotation is to determine the potential to enhance the grade-recovery curve, a significant driver of project economics. This technology is also capable of delivering cost savings by reducing the physical footprint of the processing plant and further minimizing the project’s environmental impact. Highland remains on track to announce the final metallurgical test results in Q3 2025.
2025 Site Work: The primary objective of Highland’s 2025 construction season is to fulfill its remaining obligations related to mitigation activities under the Wetlands and Streams Permit. The Company is pleased to announce the substantial completion of on-site mitigation construction, marked by the successful planting of nearly 20,000 trees in the newly constructed wetland and streams areas. The work has been subject to numerous visits from Michigan’s environmental authorities. The mitigation project will now transition into the monitoring phase.
Additionally, the off-site stream mitigation project, undertaken in partnership with a local road commission, remains on track to replace several undersized culverts with a 50-foot-span bridge. This initiative is designed to enhance fish habitat across many miles upstream and is progressing within both budget and schedule parameters. Similar to the wetland project, construction of this bridge meets our mitigation obligations to offset site impacts. These efforts reinforce Highland’s operational presence, demonstrate its commitment to environmental stewardship, and strengthen relationships with local authorities and stakeholders. The 2025 work program represents the final site activities required before a construction decision.
Barry O’Shea, President and CEO of Highland Copper, commented: "Highland is focused on key work programs that should enable a construction decision for Copperwood in 2026. This includes early site work to prepare for construction, progress on detailed engineering and metallurgical optimization, and continued advancement on state and federal funding opportunities. I am pleased that we are making significant progress in all of these areas, providing increased visibility to a construction decision. We are particularly pleased with the support demonstrated by the Wakefield township regarding the state grant, a powerful testament to this project's transformational potential for the region. At the same time, we are advancing discussions regarding potential financial support at the federal level”.
The below photos show the ongoing environmental mitigation work both on-site and off-site:
Figure 1: Gipsy wetland showing excellent plant growth – in view here are Water Plantain, rushes, bullrushes, sedges, and cattail
Figure 2: Off site stream mitigation project to replace 5 small culverts with a 50’ span bridge in cooperation with the Ontonagon County Road Commission.
Qualified Person Statement
The technical information in this news release has been reviewed and approved by Dr. Wynand van Dyk, a qualified person as defined by National Instrument 43-101, Standards of Disclosure for Mineral Projects. Dr van Dyk is employed by Copperwood Resources Inc, a wholly owned subsidiary of Highland Copper, in the role as Project Director.
About Highland Copper Company
Highland Copper Company Inc. is a Canadian company focused on exploring and developing copper projects in the Upper Peninsula of Michigan, U.S.A. The Company owns the Copperwood deposit through long-term mineral leases and
More information about the Company is available on the Company’s website at www.highlandcopper.com and on SEDAR+ at www.sedarplus.com.
Cautionary Note Regarding Forward-Looking Information
This news release contains “forward-looking statements” and “forward-looking information” (collectively “forward-looking statements”) within the meaning of applicable Canadian securities legislation. These statements include, without limitation, statements with respect to: (a) anticipated completion of 2025 early site work program at Copperwood and anticipated benefits thereof, including the resulting maintenance of the Wetland and Streams Permit (b) the potential approval of the Michigan Strategic Fund grant (c) the potential to advance engineering studies and project optimization at Copperwood, and the anticipated benefits thereof. The forward-looking statements are subject to a number of assumptions, including those set out in the technical reports entitled “Feasibility Study Update Copperwood Project Michigan, USA” and the Company’s annual information form for the year ended June 30, 2024 (the “AIF”). These underlying assumptions may prove to be incorrect. Important factors that could materially impact the Company's expectations include: changes in project parameters as plans continue to be refined; availability of services, materials and skilled labour to complete work programs, testing and drilling; effects of regulation by governmental agencies; the fact that permit extensions, renewals and amendments are subject to regulatory approvals, which may be conditioned, delayed or denied; there is no assurance that the Michigan State legislature will approve the Michigan State Strategic Funds grant, and any such approval may be subject to conditions; advancement to a construction decision at Copperwood is subject to additional studies, for which the Company will require additional funds, which may not be available on a timely basis and accordingly could delay a construction decision; the Company will be required to repay the loan facility from Kinterra in July, 2026, or will have its interest at White Pine diluted; unexpected cost increases, which could include significant increases in estimated capital and operating costs and the effects of inflation; fluctuations in metal prices and currency exchange rates; general market and industry conditions, the results of baseline studies and test work may result in unforeseen issues which could delay or hamper advancement of the projects, the results of drill programs may not result in identification or confirmation of resources, the results of work programs at White Pine may not warrant progressing to a feasibility study, and the other risks set out in the Company’s public disclosure documents, including the AIF, filed on SEDARPlus. Although the Company believes that the assumptions and factors used in preparing the forward-looking statements in this news release are reasonable, undue reliance should not be placed on forward looking statements. All forward-looking statements in this press release are based on information available to the Company as of the date hereof, and the Company undertakes no obligation to update forward-looking statements except as required by law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
For further information or media requests, please contact:
Barry O’Shea, CEO
Email: info@highlandcopper.com
Website: www.highlandcopper.com
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/9627cb77-bb8c-401d-b34e-f6e1a1bfe2cd
https://www.globenewswire.com/NewsRoom/AttachmentNg/3bb1f293-a5e2-43b4-81eb-11c63518bb38
