HIVE Digital Technologies Ltd. builds and operates digital infrastructure for Bitcoin mining, high-performance computing, and GPU-accelerated AI workloads. Company updates center on BUZZ High Performance Computing, AI cloud deployments, Tier-I and Tier-III data center capacity, fibre and power infrastructure, and renewable-energy-backed operations in markets including Canada, Sweden, and Paraguay.
Recurring HIVE news also covers customer and technology collaborations, hashrate services, GPU procurement and deployment, exchange listings, at-the-market equity activity, and exchangeable note financing. Its disclosures connect capital actions with data center development, AI compute capacity, and the shift from ASIC-based mining capacity toward broader HPC and sovereign AI compute services.
HIVE Digital Technologies reported strong Q3 FY2025 results with total revenue of $29.2 million, including $26.7 million from digital currency mining and $2.5 million from high-performance computing (HPC). The company achieved net income of $1.3 million and Adjusted EBITDA of $17.3 million.
Key highlights include mining 322 Bitcoin during the quarter, with total holdings reaching 2,805 Bitcoin valued at $260.8 million. The company's HPC business achieved a $10 million annualized run rate. HIVE's expansion plans in Paraguay aim to increase hashrate from 6 EH/s to 25 EH/s by September 2025, with a 300 MW facility development underway.
The company raised $87.5 million through an ATM equity program, issuing 21.3 million shares at an average price of C$5.74. These funds will support equipment purchases, strategic investments, and working capital needs.
HIVE Digital Technologies has released its January 2025 production results, mining 102 BTC and maintaining a HODL portfolio of 2,657 BTC valued at $271 million (at BTC price of $102,000). The company maintained an average mining capacity of 5.7 Exahash per Second with fleet efficiency at 22 J/TH, achieving a peak BTC-equivalent hashrate of 6.4 EH/s.
A major highlight is HIVE's acquisition of a 200 MW hydro-powered Bitcoin mining facility in Paraguay from Bitfarms This strategic move is expected to increase the company's global Bitcoin mining hashrate to 25 EH/s by September 2025, representing a 317% increase. The total net cost to complete the Bitfarms site is estimated at $400,000 per MW, with total operational capacity projected to reach 430 MW by Q3 2025.
The company is focusing on fleet efficiency upgrades and has appointed Lieutenant General (Ret.) John R. Evans Jr. to its Global Strategy Advisory Committee. HIVE is targeting a blended fleet efficiency of 16.5 J/TH upon full deployment of its expansion plans.
HIVE Digital Technologies has released its January 2025 production results, mining 102 BTC and maintaining a HODL portfolio of 2,657 BTC valued at $271 million. The company's Bitcoin holdings increased 34% year-over-year but decreased month-over-month due to strategic sales for capital investments.
The company maintained an average mining capacity of 5.7 Exahash per Second with fleet efficiency at 22 J/TH, achieving a peak BTC-equivalent hashrate of 6.4 EH/s. A significant development includes the acquisition of Bitfarms' 200 MW hydro-powered Bitcoin mining facility in Paraguay, expected to increase HIVE's hashrate to 25 EH/s by September 2025, representing a 317% growth.
The total net cost to complete the Bitfarms site is estimated at $400,000 per MW, with plans to increase total operational capacity to 430 MW by Q3 2025. HIVE also appointed Lt. Gen. John R. Evans Jr. to its Global Strategy Advisory Committee.
HIVE Digital Technologies (NASDAQ: HIVE) has announced its schedule for releasing Q3 2025 financial results and hosting an earnings conference call. The company will release its financial results for the quarter ended December 31, 2024, on Tuesday, February 11, 2025 after market close.
A conference call and webcast will follow on Wednesday, February 12, 2025 at 8:30 AM EST. Participants are advised to log in or dial in approximately 5 minutes before the call begins. The earnings release and a replay of the call will be accessible through HIVE's investor relations website.
HIVE Digital Technologies (NASDAQ: HIVE) has announced it will release its Q3 2025 financial results on February 11, 2025, after market close. The company will host an earnings conference call and webcast the following day, February 12, 2025, at 8:30 AM EST.
Participants are advised to log in approximately 5 minutes before the call begins. The earnings release and a replay of the call will be available on HIVE's investor relations website.
HIVE Digital Technologies has announced a significant expansion through the acquisition of Bitfarms' 200 MW Bitcoin mining facility in Yguazú, Paraguay. The $56 million deal will increase HIVE's global Bitcoin mining hashrate from 6 EH/s to an anticipated 25 EH/s by September 2025.
The development will occur in two phases: Phase 1, scheduled for completion by April 1, 2025, will add 6 EH/s, while Phase 2, expected by August 31, 2025, will contribute 6.5 EH/s using hydro-cooled ASICs. The total net costs to complete the site are estimated at $400,000 per MW.
The acquisition includes a 240 MVA substation, land, and facilities. Payment terms comprise $25 million at closing in Q1 2025 and $31 million in installments over six months. HIVE will also assume $19 million in PPA deposits to ANDE and remaining construction costs.
This expansion, combined with HIVE's existing facilities in Canada and Sweden, will bring its global capacity to 430 MW by Q3 2025, operating entirely on green hydroelectric energy.
HIVE Digital Technologies has announced a binding LOI to acquire Bitfarms' 200 MW hydro-powered Bitcoin mining facility in Yguazú, Paraguay. The $56 million acquisition will boost HIVE's global Bitcoin mining hashrate from 6 EH/s to an anticipated 25 EH/s by September 2025.
The development includes two phases: Phase 1, scheduled for April 2025, will add 6 EH/s, while Phase 2, expected by August 2025, will contribute 6.5 EH/s using hydro-cooled ASICs. The total net costs to complete the site are estimated at $400,000 per MW.
The transaction terms include $25 million payable at closing in Q1 2025 and $31 million in installments over six months. HIVE will also assume $19 million in PPA deposits and remaining construction costs. The company has already secured ASICs for 15 EH/s and plans additional purchases to reach its 25 EH/s target.
HIVE Digital Technologies has announced a significant addition to its leadership team with Lieutenant General (Ret.) John R. Evans Jr. joining its Global Strategy Advisory Committee. This appointment comes at a important time as data centers are increasingly becoming a matter of national security priority.
The company, which operates sustainable data center infrastructure across nine time zones and conducts business in five languages, views this appointment as a strategic move to enhance its global operations. HIVE's focus remains on expanding its global footprint while maintaining high standards in security, sustainability, and resilience.
This announcement was made as a designated news release in connection with the Company's prospectus supplement dated October 3, 2024, to its short form base shelf prospectus dated September 11, 2024.
HIVE Digital Technologies (TSXV: HIVE) (NASDAQ: HIVE) (FSE: YO0) has announced the appointment of Lieutenant General (Ret.) John R. Evans Jr. to its Global Strategy Advisory Committee. This strategic addition comes as data centers are increasingly recognized as a national security priority.
The company, which operates sustainable data center infrastructure across nine time zones and conducts business in five languages, views this appointment as a significant step in its mission to expand its global footprint responsibly. The announcement emphasizes HIVE's commitment to maintaining high standards in security, sustainability, and operational resilience.
HIVE Digital Technologies has released its December 2024 production results, highlighting significant growth and strategic developments. The company mined 103 BTC, increasing its HODL portfolio to 2,805 BTC, representing a 64.6% year-over-year increase. The company maintained an average mining capacity of 5.5 EH/s, with fleet efficiency at 22 J/TH, reaching peak BTC hashrates of 6.0 EH/s.
Key achievements include Bitcoin holdings valued at $261.9 million as of December 31, 2024, with BTC closing at approximately $93,400. HIVE's operational hashrate grew 47% year-over-year to 6.0 EH/s, driven by fleet upgrades with Avalon machines. The company targets reaching 15.0 EH/s by end-2025, supported by a 100 MW hydroelectric-powered expansion in Paraguay.
Strategic developments include securing competitive energy pricing in Sweden and relocating headquarters from Vancouver to San Antonio, Texas. HIVE plans to transition to US GAAP reporting starting fiscal year ending March 31, 2025.