STOCK TITAN

INTEGRA ANNOUNCES STRONG THIRD QUARTER 2025 GOLD PRODUCTION RESULTS FROM FLORIDA CANYON MINE AND INCREASED CASH BALANCE TO US$81.2 MILLION

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags

Integra Resources (NYSE American: ITRG) reported a strong operational update for Q3 2025, with 20,653 oz of gold produced and 20,265 oz sold in the quarter. Cash and cash equivalents rose to $81,192,000 as of September 30, 2025.

Key operational metrics include processed grade 0.20 g/t Au, gold recovery 60.7%, ore mined 2,533 kt, and total ore to leach pads 3,168 kt. Capital work included increased stripping, mining equipment refurbishment and orders for eight new 150-ton haul trucks, a loader, and a Hitachi shovel. Phase IIIb heap leach pad commissioning is expected in Q4 2025.

Integra Resources (NYSE American: ITRG) ha riportato un aggiornamento operativo forte per il Q3 2025, con 20,653 oz di oro prodotti e 20,265 oz venduti nel trimestre. Liquidità e equivalenti erano aumentati a $81,192,000 al 30 settembre 2025.

Le principali metriche operative includono grado processato 0,20 g/t Au, recupero dell'oro 60,7%, oro estratto 2,533 kt e oro totale destinato alle pale di leach 3,168 kt. Gli investimenti in capitale hanno riguardato un incremento dello stripping, la rifatturazione delle attrezzature minerarie e ordini per otto nuovi camion da trasporto da 150 tonnellate, un carrellatore e una pala Hitachi. Si prevede l'avvio della fase IIIb dei pile di heap leach nel Q4 2025.

Integra Resources (NYSE American: ITRG) informó una sólida actualización operativa para el 3T 2025, con 20,653 oz de oro producidos y 20,265 oz vendidos en el trimestre. Efectivo y equivalentes ascendió a $81,192,000 al 30 de septiembre de 2025.

Las métricas operativas clave incluyen grado procesado 0,20 g/t Au, recuperación de oro 60,7%, mineral extraído 2,533 kt y mineral total para las plataformas de lixiviación 3,168 kt. Las obras de capital incluyeron mayor estripe, reacondicionamiento de equipo minero y pedidos de ocho camiones de transporte de 150 toneladas, una cargadora y una pala Hitachi. Se espera la puesta en marcha de la fase IIIb de la pila de lixiviación en Q4 2025.

Integra Resources (NYSE American: ITRG)는 2025년 3분기에 강력한 운영 업데이트를 발표했습니다. 분기에 생산된 금은 20,653 oz, 판매된 금은 20,265 oz입니다. 2025년 9월 30일 기준 현금 및 현금성 자산은 $81,192,000으로 증가했습니다.

주요 운영 지표로는 가공 등급 0.20 g/t Au, 금 회수율 60.7%, 채굴 광석 2,533 kt, 그리고 레익 패드로의 총 광석 3,168 kt가 있습니다. 자본 작업에는 스트리핑 증가, 광산 장비 재정비 및 150톤급 트럭 8대, 로더 한 대, Hitachi 굴삭기의 주문이 포함됩니다. Phase IIIb 헵 레익 패드 가동은 2025년 4분기에 예상됩니다.

Integra Resources (NYSE American: ITRG) a publié une mise à jour opérationnelle robuste pour le T3 2025, avec 20,653 oz d'or produits et 20,265 oz vendus au cours du trimestre. Les liquidités et équivalents sont montés à $81,192,000 au 30 septembre 2025.

Les principaux indicateurs opérationnels comprennent une teneur traitée 0,20 g/t Au, un taux de récupération de l'or de 60,7%, du minerai extrait 2,533 kt et le minerai total destiné aux plates à lixiviation 3,168 kt. Les travaux d'investissement comprenaient un intensification des déblais, la remise à neuf des équipements miniers et des commandes pour huit camions de transport de 150 tonnes, un chargeur et une pelle Hitachi. La mise en service de la phase IIIb des tas de lixiviation est prévue au T4 2025.

Integra Resources (NYSE American: ITRG) meldete ein starkes operatives Update für Q3 2025, mit 20,653 oz Gold produziert und 20,265 oz im Quartal verkauft. Barmittel und Barmitteläquivalente stiegen zum 30. September 2025 auf $81,192,000.

Wichtige operative Kennzahlen umfassen aufbereiteten Gehalt 0,20 g/t Au, Goldausbeute 60,7%, Erz abgebaut 2,533 kt und Gesamt­erz zu Leach-Pads 3,168 kt. Kapitalarbeiten umfassten verstärktes Abtragen von Material, Aufarbeitung der Bergbaubetriebsgeräte und Bestellungen für acht neue 150-Tonnen-Transport-Lkws, einen Lader und eine Hitachi-Schaufel. Die Inbetriebnahme der Phase IIIb Heap-Leach-Pads wird voraussichtlich im Q4 2025 erfolgen.

Integra Resources (NYSE American: ITRG) أعلنت عن تحديث تشغيلي قوي للربع الثالث من 2025، مع 20,653 أوقية من الذهب مُنتجة و 20,265 أوقية مباعة في الربع. ارتفعت السيولة وما يعادلها إلى $81,192,000 حتى 30 سبتمبر 2025.

تشمل المؤشرات التشغيلية الرئيسية معدل المعالجة 0,20 جم/طن من ذهب، نسبة استرداد الذهب 60.7%، خام مستخرج 2,533 ألف طن، وإجمالي خام إلى ألواح الترشيد 3,168 ألف طن. تضمنت الأعمال الرأسمالية زيادة الحفر، إعادة تأهيل معدات التعدين وطلبات لثمانية شاحنات جديدة سعة 150 طن، ورافعة ومجرفة Hitachi. من المتوقع تشغيل مقطع Phase IIIb من أحواض التبخر في الربع الرابع من 2025.

Integra Resources (NYSE American: ITRG) 在2025年第三季度发布了强劲的运营更新,季度生产黄金 20,653 oz,销售 20,265 oz。截至2025年9月30日,现金及现金等价物增至 $81,192,000

关键运营指标包括加工品位 0.20 g/t Au、黄金回收率 60.7%、开采矿石量 2,533 kt,用于浸出堆的总矿石 3,168 kt。资本性工作包括增加剥离、矿山设备翻新以及订购八辆新型150吨运输卡车、一台装载机和一台日立挖掘机。Phase IIIb 浸出堆场调试预计在 2025 年第四季度完成。

Positive
  • Q3 gold production of 20,653 oz
  • Cash balance increased to $81.192M at Sept 30, 2025
  • YTD gold produced 58,063 oz
  • Ordered 8 new 150-ton haul trucks to reduce rental costs
  • Phase IIIb heap leach pad commissioning expected Q4 2025
Negative
  • Processed grade was low at 0.20 g/t Au
  • Gold recovery rate of 60.7% limits recoverable ounces
  • Strip ratio increased to 1.34 in Q3, raising waste movement

Insights

Strong Q3 production and a cash balance of $81.2 million support near‑term operations and planned capacity expansion.

Florida Canyon produced 20,653 oz of gold in Q3 2025 and sold 20,265 oz, with a processed grade of 0.20 g/t and a recovery of 60.7%. These metrics, together with the reported $81.2 million cash balance, indicate the operation generated meaningful operating cash flow while funding capitalized stripping, equipment refresh, and leach pad expansion.

Outcomes depend on a few operational items: the higher strip ratio of 1.34 was driven by intentional capitalized waste stripping and a temporary water shortage that has been resolved; continued recovery performance relies on Phase IIIa/IIIb pad commissioning and maintained solution flow rates. The fleet revitalization—arrival and commissioning of a new Hitachi shovel, and delivery of eight new 150‑ton haul trucks starting in Q4 2025 into Q1 2026—should reduce rental reliance and aim to lower mining cost per ton once fully integrated.

Watch for three near‑term, monitorable items: the full third quarter financial release and call on November 12–13, 2025; commissioning and ramp timing for the Phase IIIb heap leach pad in Q4 2025; and incremental impacts from the new fleet on operating cost and productivity through Q1 2026. These items will clarify whether the reported cash strength and production are durable.

TSXV: ITR; NYSE American: ITRG

www.integraresources.com

VANCOUVER, BC, Oct. 23, 2025 /PRNewswire/ - Integra Resources Corp. ("Integra" or the "Company") (TSXV: ITR) (NYSE American: ITRG) is pleased to provide an interim operational update for the third quarter ended September 30, 2025 (the "third quarter 2025" or "Q3 2025"). The Company plans to release its third quarter 2025 financial results after market close on Wednesday, November 12, 2025, followed by a conference call hosted by senior management on Thursday, November 13, 2025 at 11:00 AM Eastern Time / 8:00 AM Pacific Time.

(All amounts in United States ("U.S.") dollars as at September 30, 2025, unless otherwise stated)

George Salamis, President, CEO and Director of Integra commented: "Florida Canyon continues to deliver on expectations, generating meaningful cash flow to fund crucial reinvestment into the mine, while also supporting the Company's broader growth strategy. During the quarter, significant capital was deployed at Florida Canyon in the areas of capitalized stripping, mining equipment enhancements, and leach pad expansion. Excellent production results from Florida Canyon combined with the strong gold price environment have allowed Integra to significantly increase its quarter-over-quarter cash balance to ~$81 million, marking the Company's strongest ever financial position."

Third Quarter 2025 Florida Canyon Mine Operational Update



Three months ended
September 30,

Nine months ended
September 30,


Unit (1)

2025

2025

Ore mined

kt

2,533

8,629

Waste mined

kt

3,399

8,164

Strip ratio

waste/ore

1.34

0.95

Ore direct to leach pads

kt

1,165

3,638

Ore crushed

kt

2,003

5,649

Total ore to leach pads

kt

3,168

9,287

Processed grade

g/t Au

0.20

0.22

Gold recovery rate

%

60.7 %

60.5 %

Gold produced

oz

20,653

58,063

Gold sold

oz

20,265

57,999

Silver produced

oz

12,929

44,373

Silver sold

oz

12,215

43,949

(1)

Unit abbreviations: kt = 1,000 metric tonnes, g/t = grams per tonne, Au = gold, oz = troy ounce

(2)

Ore milled includes material from stockpiles and ore mined.

The Florida Canyon Mine ("Florida Canyon") produced 20,653 ounces of gold and sold 20,265 ounces of gold during the third quarter 2025, which is in-line with the Company's expectations. Strong gold production continues to be supported by the recovery of gold ounces recently placed on the Phase IIIa heap leach pad and by residual ounces recovered from Phases I and II leach pads. Gold production levels were further supported by increased solution flow rates through the leach pads and the new carbon-in-column circuit commissioned late in 2024. The Company expects to meet its gold production guidance for 2025.

The increased strip ratio at Florida Canyon during the third quarter 2025 is a result of the Company's stated commitment of reinvestment through increased capitalized waste stripping and ramping up new mining areas. Waste movement also increased during the third quarter 2025 due to a provisional adjustment of the mine sequence to overcome dust suppression challenges caused by a temporary water shortage in the dry summer months. The temporary water shortage was caused by a problematic historic water well, which has since been successfully replaced.

During the third quarter 2025, construction of the Phase IIIb heap leach pad at Florida Canyon continued with commissioning expected in the fourth quarter 2025. Florida Canyon is also currently undergoing a revitalization of its mining fleet. As part of this effort, refurbishment is underway on haul trucks and loaders currently on site and orders have been placed for several new key pieces of equipment, including eight new 150 ton Caterpillar haul trucks, a new Caterpillar loader, and a new Hitachi mining shovel. The mining shovel has arrived on site and will be assembled, commissioned, and put into operation in the fourth quarter 2025. Delivery of the new haul trucks will commence in the fourth quarter 2025 and continue into the first quarter 2026. The refurbished existing fleet and key new pieces of equipment are expected to reduce reliance on expensive rental equipment, increase mining productivity, and lower mining cost per ton over the next several years at Florida Canyon.

Third Quarter 2025 Financial Position

Financial Position

Unit (1)

September 30, 2025

Cash and cash equivalents

$000s

$                                                                       81,192

(1)

Unit abbreviations: $000s = thousands of U.S. dollars

Complete financial results for the third quarter 2025 will be reported and filed on Integra's profile on SEDAR+ at www.sedarplus.ca and EDGAR profile at www.sec.gov on Wednesday, November 12, 2025

Third Quarter 2025 Conference Call

Integra will host a conference call and webcast on Thursday, November 13, 2025, at 11:00 AM Eastern Time / 8:00 AM Pacific Time, to discuss the third quarter 2025 results. Details for the conference call and webcast are included below.

Dial-In Numbers / Webcast:

Conference ID: 2435675
Toll Free: (800) 715-9871
Toll: +1 (646) 307-1963
Webcast:  https://events.q4inc.com/attendee/154141836

About Integra Resources Corp.

Integra is a growing precious metals producer in the Great Basin of the Western United States. Integra is focused on demonstrating profitability and operational excellence at its principal operating asset, the Florida Canyon Mine, located in Nevada. In addition, Integra is committed to advancing its flagship development-stage heap leach projects: the past producing DeLamar Project located in southwestern Idaho and the Nevada North Project located in western Nevada. Integra creates sustainable value for shareholders, stakeholders, and local communities through successful mining operations, efficient project development, disciplined capital allocation, and strategic M&A, while upholding the highest industry standards for environmental, social, and governance practices.

ON BEHALF OF THE BOARD OF DIRECTORS

George Salamis
President, CEO and Director

Qualified Person 

The scientific and technical information contained in this news release has been reviewed and approved by Gregory Robinson (P.E., SME Registered Member), Integra's General Manager of the Florida Canyon Mine. Mr. Robinson is a "qualified person" as defined in National Instrument 43- 101 – Standards of Disclosure for Mineral Projects ("NI 43-101").

Forward Looking Statements

Certain information set forth in this news release contains "forward‐looking statements" and "forward‐looking information" within the meaning of applicable Canadian securities legislation and in applicable United States securities law (referred to herein as forward‐looking statements). Except for statements of historical fact, certain information contained herein constitutes forward‐looking statements which includes, but is not limited to, statements with respect to: timing of the third quarter 2025 financial results and conference call, plans and expectations for Florida Canyon, the future financial or operating performance of the Company and the Wildcat and Mountain View deposits (the "Nevada North Project"), the Florida Mountain and DeLamar deposits (the "DeLamar Project") and Florida Canyon. Forward-looking statements are often identified by the use of words such as "may", "will", "could", "would", "anticipate", 'believe", "expect", "intend", "potential", "estimate", "budget", "scheduled", "plans", "planned", "forecasts", "goals" and similar expressions.

Forward-looking statements are based on a number of factors and assumptions made by management and considered reasonable at the time such statement was made. Forward‐looking statements necessarily involve known and unknown risks and uncertainties, which may cause actual performance and financial results in future periods to differ materially from any projections of future performance or result expressed or implied by such forward‐looking statements, including but not limited to those risk factors disclosed in Integra's Annual Information Form dated March 26, 2025 for the fiscal year ended December 31, 2024, which is available on the SEDAR+ issuer profile for the Company at www.sedarplus.ca and available as Exhibit 99.1 to Integra's Form 40-F, which is available on the EDGAR profile for the Company at www.sec.gov.

Investors are cautioned not to put undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date of this news release and, accordingly, are subject to change after such date. The Company disclaims any intent or obligation to update publicly or otherwise revise any forward-looking statements or the foregoing list of assumptions or factors, whether as a result of new information, future events or otherwise, except in accordance with applicable securities laws. Investors are urged to read the Company's filings with Canadian securities regulatory agencies, which can be viewed online under the Company's profile on SEDAR+ at www.sedarplus.ca.

Cautionary Note for U.S. Investors Concerning Mineral Resources and Reserves

NI 43-101 is a rule of the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Technical disclosure contained in this news release has been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Classification System. These standards differ from the requirements of the U.S. Securities and Exchange Commission ("SEC") and resource information contained in this news release may not be comparable to similar information disclosed by domestic United States companies subject to the SEC's reporting and disclosure requirements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/integra-announces-strong-third-quarter-2025-gold-production-results-from-florida-canyon-mine-and-increased-cash-balance-to-us81-2-million-302592328.html

SOURCE Integra Resources Corp.

FAQ

How much gold did Integra Resources (ITRG) produce in Q3 2025?

Florida Canyon produced 20,653 ounces of gold in Q3 2025.

What was Integra's cash balance (ITRG) as of September 30, 2025?

Cash and cash equivalents were reported at $81,192,000 on Sept 30, 2025.

Will Integra (ITRG) meet its 2025 gold production guidance?

The company stated it expects to meet its 2025 gold production guidance.

When is the Phase IIIb heap leach pad at Florida Canyon expected to commission?

Commissioning of the Phase IIIb heap leach pad is expected in Q4 2025.

What fleet upgrades did Integra (ITRG) announce for Florida Canyon in Q3 2025?

Orders placed for 8 new 150-ton Caterpillar haul trucks, a loader, and a Hitachi shovel; shovel arrived on site.

How did the strip ratio and ore mined change for Florida Canyon in Q3 2025?

Q3 strip ratio increased to 1.34; ore mined was 2,533 kt in Q3 2025.
Integra Resource

NYSE:ITRG

ITRG Rankings

ITRG Latest News

ITRG Latest SEC Filings

ITRG Stock Data

473.21M
153.67M
9.09%
32.92%
0.63%
Other Precious Metals & Mining
Basic Materials
Link
Canada
Vancouver