Namib Minerals – Production and Operational Update
Namib Minerals (Nasdaq: NAMM) provided a Nov 10, 2025 operational update with 2025 guidance and a multi‑asset restart plan.
- 2025 guidance: production 24,000–25,000 oz; Adjusted EBITDA US$22–26m; AISC US$/oz 2,700–2,800.
- Growth path: WSP mandated to deliver SK‑1300 compliant feasibility studies at Redwing and Mazowe over 12–18 months.
- Near‑term work: dewatering at Redwing to begin during the study and take ~8 months; surface and power upgrades planned.
- Funding need: preliminary CAPEX estimate US$300–400m; company plans a mix of project debt, partnerships and internal cash.
Namib Minerals (Nasdaq: NAMM) ha fornito un aggiornamento operativo del 10 novembre 2025 con le previsioni per il 2025 e un piano di riavvio multi‑asset.
- Guidance 2025: produzione 24.000–25.000 once; EBITDA rettificato US$22–26m; AISC US$/oz 2.700–2.800.
- Percorso di crescita: WSP incaricata di fornire studi di fattibilità conformi SK‑1300 su Redwing e Mazowe entro 12–18 mesi.
- Lavori a breve termine: dewatering su Redwing da avviare durante lo studio e richiederà ~8 mesi; piani per miglioramenti di superficie e fornitura di energia.
- Esigenza di finanziamento: stima preliminare di CAPEX US$300–400m; la società prevede un mix di debito di progetto, partnership e cassa interna.
Namib Minerals (Nasdaq: NAMM) proporcionó una actualización operativa del 10 de noviembre de 2025 con las proyecciones para 2025 y un plan de reinicio multiactivo.
- Guía para 2025: producción 24,000–25,000 oz; EBITDA ajustado US$22–26m; AISC US$/oz 2,700–2,800.
- Ruta de crecimiento: WSP encargado de entregar estudios de viabilidad conforme SK‑1300 en Redwing y Mazowe en 12–18 meses.
- Trabajos a corto plazo: desagüe en Redwing para comenzar durante el estudio y tomar ~8 meses; mejoras en superficie y suministro de energía planificadas.
- Necesidad de financiación: estimación preliminar de CAPEX US$300–400m; la empresa planea una mezcla de deuda de proyecto, asociaciones y caja interna.
Namib Minerals (Nasdaq: NAMM) 은 2025년 11월 10일의 운영 업데이트와 2025년 가이던스 및 다중 자산 재가동 계획을 제공했습니다.
- 2025년 가이던스: 생산 24,000–25,000 oz; 조정 EBITDA US$22–26m; AISC US$/oz 2,700–2,800.
- 성장 경로: Redwing 및 Mazowe에서 SK‑1300 준수 타당성 조사를 12–18개월 안에 제시하도록 WSP에 의뢰.
- 단기 작업: 연구 중에 Redwing의 탈수화를 시작하고 약 8개월 소요; 표면 및 전력 업그레이드 계획.
- 자금 필요: 예비 CAPEX 추정 US$300–400m; 회사는 프로젝트 채무, 파트너십 및 내부 현금을 혼합할 계획.
Namib Minerals (Nasdaq: NAMM) a fourni une mise à jour opérationnelle du 10 novembre 2025 avec les prévisions pour 2025 et un plan de redémarrage multi-actifs.
- Prévisions 2025 : production 24 000–25 000 oz; EBITDA ajusté US$22–26m; AISC US$/oz 2 700–2 800.
- Trajectoire de croissance : WSP mandatée pour réaliser des études de faisabilité conformes SK‑1300 à Redwing et Mazowe sur une période de 12–18 mois.
- Travaux à court terme : épuisement des eaux à Redwing à démarrer pendant l’étude et durer ~8 mois; améliorations de surface et d’alimentation électrique prévues.
- Besoin de financement : estimation préliminaire du CAPEX US$300–400m; l’entreprise prévoit une combinaison de dette de projet, de partenariats et de trésorerie interne.
Namib Minerals (Nasdaq: NAMM) legte am 10. November 2025 ein operatives Update mit Guidance für 2025 und einem mehrwertigen Neustart-Plan vor.
- Guidance 2025: Produktion 24.000–25.000 oz; adjustiertes EBITDA US$22–26m; AISC US$/oz 2.700–2.800.
- Wachstumsweg: WSP beauftragt, bis zu 12–18 Monaten Machbarkeitsstudien gemäß SK‑1300 für Redwing und Mazowe zu liefern.
- Kurzfristige Arbeiten: Entwässerung bei Redwing beginnt während der Studie und dauert ca. 8 Monate; Oberflächen- und Stromversorgungs-Upgrades geplant.
- Finanzierungsbedarf: vorläufige CAPEX-Schätzung US$300–400m; das Unternehmen plant eine Mischung aus Projektfinanzierung, Partnerschaften und eigenen Mitteln.
Namib Minerals (Nasdaq: NAMM) قدمت تحديثاً تشغيلياً في 10 نوفمبر 2025 مع توجيهات 2025 وخطة لإعادة تشغيل متعددة الأصول.
- توجيهات 2025: الإنتاج 24,000–25,000 أوقية؛ EBITDA المعدلة US$22–26 مليون؛ AISC US$/أوقية 2,700–2,800.
- مسار النمو: تكليف WSP بتقديم دراسات جدوى متوافقة مع SK‑1300 في Redwing وMazowe خلال 12–18 شهراً.
- الأعمال القريبة: إزالة المياه من Redwing لتبدأ أثناء الدراسة وتستغرق ~8 أشهر؛ مخططات للتحسينات السطحية وتزويد الكهرباء.
- احتياج التمويل: تقدير CAPEX مبدئي US$300–400 مليون؛ تخطط الشركة لمزيج من تمويل المشروع، والشراكات، والسيولة الداخلية.
- 2025 production guidance: 24,000–25,000 oz
- 2025 Adjusted EBITDA range: US$22–26m
- WSP mandated for 12–18 month SK‑1300 feasibility studies
- Preliminary expansion funding plan: US$300–400m estimate
- High reported unit cost: AISC US$2,700–2,800/oz
- Expansion funding need US$300–400m may require external capital
- Dewatering at Redwing estimated to take ~8 months, adding schedule risk
- Forward‑looking risks include possible inability to maintain Nasdaq listing
Insights
Operational update outlines stabilisation at How Mine, SK-1300 feasibility work for two restarts, and a preliminary
Namib Minerals plans to consolidate grades and complete throughput-capacity work at How Mine while running SK-1300 feasibility studies for Redwing and Mazowe with WSP. The feasibility phase is set for
The plan depends on completion of technical studies, permit and reserve conversion, and securing funds. The company flags risks including market conditions, internal control weaknesses, listing risk, and political/social risks in Zimbabwe and the DRC. Key monitorables are the
HARARE, Zimbabwe, Nov. 10, 2025 (GLOBE NEWSWIRE) -- Namib Minerals (Nasdaq: NAMM) (“Namib Minerals” or the “Company”) today provided an operational update, including production guidance for 2025 and an overview of its mandate to WSP Global Inc. (“WSP”).
2025 Operational Guidance
The Company expects 2025 to continue as a year of grade consolidation and optimization at its flagship How Mine operation. Based on current mine plans and market conditions, the Company anticipates the following ranges:
| Metric | 2025 Guidance Range |
| Production (oz) | 24,000 – 25,000 |
| Adjusted EBITDA (US$ millions) | 22 – 26 |
| All-in Sustaining Cost (AISC US$/oz) | 2,700 – 2,800 |
The 2025 focus at How Mine remains on stabilizing grade performance and completing throughput-capacity improvements. These improvements are expected to yield geared production and grades in the upcoming year. Furthermore, the Company continues advancing early-stage restart preparation work at Redwing Mine and Mazowe Mine.
Pathway to Resource and Production Expansion
Namib Minerals is pursuing a phased, technically driven growth plan designed to transform the Company from a single-asset producer into a multi-asset operator. The Company has in the past informed investors of its objective to recommence operations at Mazowe Mine and Redwing Mine. These restarts represent the first phase of the Company’s pathway to expansion and have commenced with the appointment of WSP. WSP has been appointed to begin feasibility studies at both mines simultaneously.
The Company appointed WSP not only for its expertise but also the firm’s understanding and familiarity with the Company’s assets. The Company’s objective is to align the future production levels of Redwing Mine and Mazowe Mine with their respective resource sizes therein increasing their production capacities.
WSP have been mandated to verify the Company’s ability to meet this strategic objective. WSP have been mandated to execute a SK-1300 compliant feasibility study on the following terms, amongst others -
Feasibility Studies — 12 to 18 Months
- These studies will validate our exploration program to increase, convert and upgrade these resources.
- The program is expected to be completed over 12 to 18 months and will provide the technical foundation for reserve conversion, permitting, and financing discussions.
In conjunction with the feasibility studies, the Company shall execute on phase two, namely the following strategic objectives –
Dewatering and Infrastructure Preparation
- Dewatering at Redwing is scheduled to commence during the Feasibility-study phase and is expected to take approximately eight months to reach the targeted mining levels.
- Concurrently, surface-infrastructure and power-supply upgrades will be planned to align with the restart timeline.
The third phase of the Company’s expansion will be to proceed with financing of its CAPEX –
CAPEX Financing
- Upon completion of the Feasibility Studies, Namib Minerals intends to initiate the procurement process for major equipment and plant components required for the restart of the Redwing and Mazowe Mines.
- The Company’s preliminary estimate is that the total funding requirement for the expansion program is expected to fall within a range of US
$300 million to$400 million , with the majority allocated to the Redwing Mine. However, such estimate is preliminary and subject to the completion of the feasibility studies and final engineering outcomes as well as a number of assumptions, risks and uncertainties, including the timing of the completion of the feasibility studies, market conditions, and the cost of equipment and construction, many of which are beyond the Company’s control and subject to change. - The Company plans to pursue a balanced funding mix that may include project debt, strategic partnerships, and internally-generated cash flows to help minimize shareholder dilution.
Forward-Looking Statements
This update includes forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. All statements other than statements of historical facts contained in this update are forward-looking statements. Any statements that refer to estimates, forecasts or other characterizations of future events or circumstances, including any underlying assumptions, are also forward-looking statements. Forward-looking statements include, without limitation, our management teams’ expectations concerning future operational and cost performance, the anticipate timeline and costs of the restart of the Mazowe and Redwing Mines, and related assumptions. The forward-looking statements are based on our current expectations and are inherently subject to uncertainties and changes in circumstance and their potential effects and speak only as of the date of such statement. There can be no assurance that future developments will be those that have been anticipated. These forward-looking statements involve a number of risks and uncertainties which include, but are not limited to, (i) market risks, including the price of gold; (ii) the inability to maintain the listing of Namib Minerals’ securities on Nasdaq; (iii) the inability to remediate the identified material weaknesses in the Company’s internal control over financial reporting, which, if not corrected, could adversely affect the reliability of Namib Minerals’ financial reporting; (iv) the risk that the Company may not be able to successfully develop its assets, including expanding the How mine, restarting and expanding the Redwing and Mazowe Mines; (v) the risk that Namib Minerals will be unable to raise additional capital to execute its business plan, which may not be available on acceptable terms or at all; and (vi) political and social risks of operating in Zimbabwe and the DRC. The foregoing list is not exhaustive. You should carefully consider the foregoing factors, any other factors discussed in this press release and the other risks and uncertainties described in the filings we make with Securities and Exchange Commission (the “SEC”). We caution you against placing undue reliance on forward-looking statements, which reflect current beliefs and are based on information currently available as of the date a forward-looking statement is made.
Non-IFRS Information
References to non-IFRS financial measures, including Adjusted EBITDA and AISC, are presented as supplementary information and should not be considered substitutes for IFRS results. Definitions and reconciliations are available in the Company’s public filings with the SEC.
Contacts:
Investor Relations:
IR@namibminerals.com
Lamiaa Maniar:
VP of Communications
lmaniar@namibminerals.com