NextDecade Announces Positive Final Investment Decision and Financial Close on Train 4 at Rio Grande LNG
NextDecade (NASDAQ: NEXT) has announced a positive final investment decision (FID) and financial close on Train 4 at Rio Grande LNG.
Sentiment and the balance of points
Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.
Positive final investment decision achieved and full notice to proceed issued to Bechtel for Train 4 on September 9, 2025
Train 4 fully funded with no impact to NextDecade common shares outstanding
“We are pleased to announce today that we have made a positive FID on Train 4 and issued full notice to proceed to Bechtel,” said Matt Schatzman, NextDecade’s Chairman and Chief Executive Officer. “The global call for additional natural gas infrastructure continues to be strong, and we are well positioned to meet this growing demand for cleaner energy, with approximately 24 million tonnes per annum (MTPA) of expected LNG production capacity currently under construction, Train 5 nearing a positive FID, and significant additional expansion capacity under development at the Rio Grande LNG site. I’d like to thank the NextDecade team, our equity partners, our Train 4 LNG customers, Bechtel, our financing partners, and our local stakeholders for their ongoing support and contributions toward the continued success and growth of Rio Grande LNG.”
Positive FID Achieved on Train 4
On September 9, 2025, NextDecade made a positive FID and issued full notice to proceed to Bechtel under the Company’s lump-sum, turnkey engineering, procurement, and construction (EPC) contract for Train 4 and related infrastructure. Train 4 has expected LNG production capacity of approximately 6 MTPA, bringing the total expected LNG production capacity under construction at Rio Grande LNG to approximately 24 MTPA.
Train 4 is commercially supported by 4.6 MTPA of 20-year LNG Sale and Purchase Agreements (SPAs) with ADNOC, TotalEnergies, and Aramco. The guaranteed substantial completion date for Train 4, as well as the date of first commercial delivery (DFCD) under the Train 4 LNG SPAs, is anticipated in the second half of 2030.
Project costs for Train 4 and related infrastructure are expected to total approximately
To fully fund the expected costs for Train 4 and related infrastructure, the Company successfully closed on approximately
-
term loan facility at Rio Grande LNG Train 4, LLC;$3.85 billion -
in equity commitments from NextDecade; and$1.13 billion -
in equity commitments from partners Global Infrastructure Partners, a part of BlackRock; GIC; Mubadala Investment Company (together, the Financial Investors); and TotalEnergies.$1.70 billion
NextDecade received
NextDecade has an initial economic interest of
NextDecade Train 4 Equity Commitment Financed with No Impact to Common Shares Outstanding
NextDecade entered into a total of
The FinCo Loan is a
The SuperFinCo Loan is a
Positive FID on Train 5 Expected in Fourth Quarter 2025
Train 5 commercialization is complete, and Train 5 is commercially supported by a total of 4.5 MTPA of 20-year LNG SPAs with JERA, EQT Corporation, and ConocoPhillips.
In June 2025, the Company entered into a lump-sum, turnkey EPC contract with Bechtel for Train 5 and related infrastructure. In September 2025, the Company extended the pricing validity period under the Train 5 EPC contract through November 15, 2025, to accommodate the Company’s current expected timeline for achieving a positive FID on Train 5.
Project costs for Train 5 and related infrastructure are expected to total approximately
The Company expects to finance construction of Train 5 using approximately
The Company expects to achieve a positive FID on Train 5 and related infrastructure, subject to obtaining adequate financing, in the fourth quarter of 2025. Based on this timing, the guaranteed substantial completion date for Train 5, as well as DFCD under the Train 5 SPAs, is anticipated in the first half of 2031.
1 Each expansion train will be obligated to make a payment, at its applicable start-up date, to the trains in commercial operation at such date for such expansion train’s proportionate share of the capital costs of the common facilities that such expansion train will access, net of the capital cost of any common facilities constructed under the EPC agreement for the applicable expansion train project, if any. The Train 4 and Train 5 expected project costs presented in this press release include estimates of these “true up” payments.
About NextDecade Corporation
NextDecade is committed to providing the world access to reliable, lower carbon energy. We are focused on delivering secure, low-cost, and sustainable energy solutions through the safe and efficient development and operation of natural gas liquefaction and carbon capture and storage infrastructure. Through our subsidiaries, we are developing and constructing the Rio Grande LNG natural gas liquefaction and export facility near
Forward-Looking Statements
This press release contains forward-looking statements within the meaning of
View source version on businesswire.com: https://www.businesswire.com/news/home/20250909997789/en/