Panamint Capital Breaks Ground on Historic 1.2 GW Solar Project at Texas Energy Site
Rhea-AI Summary
Panamint Capital has begun construction on Big Rooter Power, a $1.7 billion, 1.2 GWdc solar PV project at its Twin Oaks power station in Robertson County, Texas, described as the largest solar project at an existing coal mining site in North America.
The first phase, Big Rooter West (491 MWdc), is under construction and targeted for commercial operation in August 2028. The second phase, Big Rooter East (658 MWdc), is expected to start construction in December 2026 and begin operations in August 2029. Panamint expects the projects to create over 800 construction jobs and contribute more than $66 million to the local economy over Big Rooter West’s lifetime.
SOLV Energy (NASDAQ: MWH) will provide EPC services; First Solar (NASDAQ: FSLR) will supply about 2 million modules; and Nextpower (NASDAQ: NXT) will furnish NX Horizon tracker systems and software. The project will use over 34,000 tons of domestically manufactured steel and is backed by a long-term power purchase agreement with a large U.S. company, according to Panamint Capital.
Positive
- $1.7 billion investment in 1.2 GWdc Big Rooter Power project
- Two-phase buildout: 491 MWdc West by 2028, 658 MWdc East by 2029
- Over 800 construction jobs and $66 million lifetime local economic impact expected
- First Solar to supply about 2 million solar panels for both phases
- Project to use over 34,000 tons of domestically manufactured steel
Negative
- None.
News Market Reaction – NXT
In the Jul 23 session, NXT declined 0.45%, reflecting a mild negative market reaction. Our momentum scanner triggered 7 alerts that day, indicating moderate trading interest and price volatility.
Data tracked by StockTitan Argus on the day of publication.
Key Figures
Historical Context
| Date | Event | Sentiment | 24h Move | Catalyst |
|---|---|---|---|---|
| Jul 20 | Acquisition completion | Positive | -2.0% | Completed Prevalon acquisition added storage capabilities and employee equity awards. |
| Jul 09 | Earnings scheduling | Neutral | -1.1% | Scheduled Q1 fiscal 2027 results announcement and conference call after market close. |
| Jun 22 | Acquisition agreement | Positive | +2.8% | Announced Zimmermann acquisition with cash-and-stock consideration and projected revenue contribution. |
| Jun 17 | Product portfolio expansion | Positive | -1.8% | Expanded international solar portfolio with new tracker and foundation solutions. |
| Jun 01 | Patent dispute | Negative | +5.0% | Faced patent infringement allegations while stating it would defend the claims. |
24h Move is the share-price change in the day after each event; other market factors may also have contributed.
Recent announcements more often diverged from subsequent 24-hour price reactions than aligned, with acquisition-related events showing both outcomes.
Key Terms
solar pv technical
EPC services technical
solar tracker systems technical
power purchase agreement financial
AI-generated analysis. How Rhea-AI works. Not financial advice.
Construction is now underway on Big Rooter West, the 491 MWdc first phase that will enter commercial operation in August 2028. Big Rooter East, the 658 MWdc second phase, is expected to begin construction in December 2026 and enter commercial operation in August 2029. The projects will create over 800 construction jobs.
"Big Rooter Power represents our vision for getting more out of America's energy infrastructure and ensuring America's energy dominance," said Apolka Totth, Panamint's Chief Executive Officer. "When Big Rooter is complete, the Twin Oaks complex will have 1.5 GW of operating thermal and renewable power, in addition to over 20 miles of new 345 kV transmission, 1.6 GWh of battery energy storage and 790 MW of Batch Zero data center capacity under development across our 10,000-acre site."
The project represents the transformation of a historic
Big Rooter West project will continue Twin Oaks's 30-year legacy of empowering the local community. With a strong emphasis on local hiring and regional vendor selection, Big Rooter West is expected to contribute over
To deliver the project, Panamint selected leading
SOLV Energy (NASDAQ: MWH), a leading provider of utility-scale energy infrastructure solutions, will provide EPC services for the project, including solar, substation and transmission infrastructure. "Big Rooter is a landmark project that reflects the scale of investment being made in America's energy future," said George Hershman, SOLV Energy CEO. "We are proud to partner with Panamint on this important project and help bring their vision to life. From project delivery through long-term asset performance, our focus is on creating lasting value for communities, customers and stakeholders."
First Solar (NASDAQ: FSLR) will manufacture approximately 2 million solar panels at facilities in
"We are proud to use domestically manufactured equipment made by American companies and installed by American workers," said Mr. Stanton, Managing Director of Development. "Our long-term power purchase agreement with one of country's largest companies will ensure the electricity we generate at Big Rooter will power job creation in the American economy into the 2050s."
About Panamint Capital LLC
Panamint Capital is a woman-led energy investment firm, minority-owned by Global Atlantic Financial Group, a wholly owned subsidiary of KKR, and headquartered in
Contact
View original content:https://www.prnewswire.com/news-releases/panamint-capital-breaks-ground-on-historic-1-2-gw-solar-project-at-texas-energy-site-302833535.html