ORVANA PROVIDES UPDATE ON TRANSPORT AND LOGISTICS DISRUPTIONS IN BOLIVIA AND IMPACT ON THE DON MARIO OXIDE STOCKPILE PROJECT
Rhea-AI Summary
Orvana Minerals (OTCQX: ORVMF) reports that nationwide civil unrest in Bolivia, including strikes and road blockades, is disrupting logistics and delaying the Oxide Stockpile Project at the Don Mario operation.
EMIPA completed Au–Ag circuit verification, producing 959 gold ounces and 1,079 silver ounces, but oxide ore processing start-up is now postponed with no revised date, and guidance will be reassessed.
Positive
- Don Mario Au–Ag circuit verification completed with 959 gold oz and 1,079 silver oz produced
- Commissioning of copper leaching, solvent extraction and electrowinning circuits has advanced to final testing
- Company is evaluating alternative and in-country sourcing options to mitigate supply disruptions
Negative
- Nationwide strikes and road blockades in Bolivia are materially impacting logistics and supply chains
- Commencement of oxide ore processing at Don Mario delayed beyond previously communicated timeline
- Company cannot currently provide a revised start-up date for the Oxide Stockpile Project
- EMIPA’s guidance will be reassessed due to uncertain duration and impact of current disruptions
News Market Reaction – ORVMF
In the May 26 session, ORVMF declined 10.19%, reflecting a significant negative market reaction.
Data tracked by StockTitan Argus on the day of publication.
AI-generated analysis. How Rhea-AI works. Not financial advice.
TSX: ORV
OTCQX: ORVMF
#14-2026
The situation remains fluid and unresolved as of the date of this news release. The Company is monitoring developments on a continuous basis.
Impact on the Oxide Stockpile Project
As previously reported in its Management's Discussion & Analysis for the three and six months ended march 31, 2026, dated May 12, 2026, EMIPA successfully completed the verification phase of the Don Mario plant's Au–Ag circuit during the quarter ended march 31, 2026, producing 959 gold ounces and 1,079 silver ounces of doré from the processing of legacy sulphide ore. Following completion of the Au–Ag testing phase, EMIPA advanced the commissioning and integration of the copper leaching, solvent extraction and electro–winning circuits, with the expanded plant undergoing final testing and operational readiness verification.
The commencement of oxide ore processing at Don Mario is being directly impacted by constraints on the supply of required materials, driven by ongoing supply chain and logistical disruptions.
EMIPA continues to take all available steps to advance the OSP, including evaluating alternative and in–country sourcing options where feasible. Personnel safety and security at the Don Mario site remain a priority, and the Company continues to monitor conditions closely.
Outlook
The Company will provide further updates as the situation in
As a result of the previously described conditions, the commencement of oxide ore processing will be delayed beyond the previously communicated timeline. The Company is not in a position to provide a revised start–up date at this time. Orvana will update the market when sufficient clarity becomes available.
The Company will reassess EMIPA's guidance once greater visibility is available regarding the duration and operational impact of the current disruptions.
Orvana's primary focus at this time remains the safety of its personnel at Don Mario, together with continued engagement with Bolivian authorities on operational matters.
ABOUT ORVANA – Orvana is a multi-mine gold-copper-silver company. Orvana's assets consist of the producing Orovalle operation in northern
Cautionary Statements – Forward-Looking Information
Certain statements in this news release constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws ("forward-looking statements"). Forward-looking information includes, without limitation: statements regarding the expected timing, if any, of commencement of oxide ore processing at Don Mario under the OSP; EMIPA's ability to obtain the required import authorizations for OSP materials; the Company's ability to manage EMIPA's liquidity and meet its debt and financing obligations during the current period; and statements regarding the Company's continued engagement with Bolivian authorities on operational matters and its evaluation of near-term financing alternatives.
Forward-looking statements are not statements of historical fact and are generally identified by words or phrases such as "believes", "expects", "plans", "estimates", "intends", "anticipates", "may", "could", "would", "might" or "will", or similar expressions, and include statements regarding future events and performance.
Forward-looking statements involve significant known and unknown risks, uncertainties and assumptions. The forward-looking statements in this news release are based on assumptions including, without limitation: that the current civil unrest in
Actual results could differ materially from those expressed or implied in forward-looking statements due to a variety of factors, many beyond the Company's control, including: the continuation or further escalation of civil unrest and road blockades in
Orvana does not undertake any obligation to update forward-looking statements, except as required by law. Readers are cautioned not to place undue reliance on forward-looking statements.
View original content to download multimedia:https://www.prnewswire.com/news-releases/orvana-provides-update-on-transport-and-logistics-disruptions-in-bolivia-and-impact-on-the-don-mario-oxide-stockpile-project-302781251.html
SOURCE Orvana Minerals Corp.