STOCK TITAN

Canadian Critical Minerals Updates Its Permit Application to Restart the Bull River Mine and Mill

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Canadian Critical Minerals (CCMI) has updated its permit application strategy for restarting the Bull River Mine (BRM) project near Cranbrook, BC. The company is now combining two phases into a single application to simultaneously restart underground mining and milling operations. CCMI has engaged Moose Mountain Technical Services for underground mine planning (expected completion: August 2025) and ALS Metallurgical Services for humidity cell testing on tailings.

The company has been selling preconcentrated copper, gold, and silver material to New Afton under an Ore Purchase Agreement, having shipped approximately 7,900 tonnes with an additional 2,100 tonnes expected by August 2025. The remaining 170,000 tonnes of mineralized fines will provide initial mill feed for about eight months post-restart. The BRM project features over $100 million of usable infrastructure and 22,000 metres of accessible underground workings.

Canadian Critical Minerals (CCMI) ha aggiornato la strategia per la richiesta di permessi relativi al riavvio del progetto Bull River Mine (BRM) vicino a Cranbrook, BC. L'azienda sta ora unificando due fasi in un'unica domanda per riavviare contemporaneamente le operazioni di estrazione sotterranea e di lavorazione. CCMI ha incaricato Moose Mountain Technical Services per la pianificazione della miniera sotterranea (completamento previsto: agosto 2025) e ALS Metallurgical Services per i test di umidità sulle scorie.

L'azienda ha venduto materiale preconcentrato di rame, oro e argento a New Afton tramite un Accordo di Acquisto Minerale, avendo spedito circa 7.900 tonnellate con ulteriori 2.100 tonnellate previste entro agosto 2025. Le restanti 170.000 tonnellate di fini mineralizzati costituiranno il primo carico di alimentazione del mulino per circa otto mesi dopo il riavvio. Il progetto BRM dispone di oltre 100 milioni di dollari in infrastrutture utilizzabili e 22.000 metri di gallerie sotterranee accessibili.

Canadian Critical Minerals (CCMI) ha actualizado su estrategia para la solicitud de permisos para reiniciar el proyecto Bull River Mine (BRM) cerca de Cranbrook, BC. La compañía está combinando dos fases en una sola aplicación para reiniciar simultáneamente las operaciones de minería subterránea y procesamiento. CCMI ha contratado a Moose Mountain Technical Services para la planificación de la mina subterránea (finalización prevista: agosto 2025) y a ALS Metallurgical Services para pruebas de celda de humedad en relaves.

La empresa ha estado vendiendo material preconcentrado de cobre, oro y plata a New Afton bajo un Acuerdo de Compra de Mineral, habiendo enviado aproximadamente 7.900 toneladas y se esperan otras 2.100 toneladas para agosto de 2025. Las restantes 170.000 toneladas de finos mineralizados proporcionarán el suministro inicial para el molino durante unos ocho meses después del reinicio. El proyecto BRM cuenta con más de 100 millones de dólares en infraestructura utilizable y 22.000 metros de galerías subterráneas accesibles.

Canadian Critical Minerals (CCMI)는 브리티시컬럼비아 주 크랜브룩 근처의 Bull River Mine (BRM) 프로젝트 재가동을 위한 허가 신청 전략을 업데이트했습니다. 회사는 지하 광산 작업과 제련 작업을 동시에 재개하기 위해 두 단계를 하나의 신청서로 통합하고 있습니다. CCMI는 지하 광산 계획을 위해 Moose Mountain Technical Services를 고용했으며(완료 예상: 2025년 8월), 광미 슬러지에 대한 습도 셀 테스트는 ALS Metallurgical Services가 담당합니다.

회사는 광석 구매 계약에 따라 New Afton에 구리, 금, 은이 함유된 선농축 물질을 판매해 왔으며, 약 7,900톤을 선적했고 2025년 8월까지 추가 2,100톤을 선적할 예정입니다. 남은 170,000톤의 광물화된 미분은 재가동 후 약 8개월간 초기 제련 원료로 사용됩니다. BRM 프로젝트는 1억 달러 이상의 사용 가능한 인프라와 22,000미터의 접근 가능한 지하 작업장을 보유하고 있습니다.

Canadian Critical Minerals (CCMI) a mis à jour sa stratégie de demande de permis pour relancer le projet Bull River Mine (BRM) près de Cranbrook, en Colombie-Britannique. La société regroupe désormais deux phases en une seule demande afin de redémarrer simultanément l'exploitation minière souterraine et les opérations de traitement. CCMI a fait appel à Moose Mountain Technical Services pour la planification de la mine souterraine (achèvement prévu : août 2025) et à ALS Metallurgical Services pour les tests en cellule d'humidité sur les résidus.

L'entreprise vend du matériau préconcentré de cuivre, or et argent à New Afton dans le cadre d'un accord d'achat de minerai, ayant expédié environ 7 900 tonnes et prévoit 2 100 tonnes supplémentaires d'ici août 2025. Les 170 000 tonnes restantes de fines minéralisées fourniront l'alimentation initiale du moulin pendant environ huit mois après le redémarrage. Le projet BRM dispose de plus de 100 millions de dollars d'infrastructures utilisables et de 22 000 mètres de galeries souterraines accessibles.

Canadian Critical Minerals (CCMI) hat seine Genehmigungsstrategie für den Neustart des Projekts Bull River Mine (BRM) in der Nähe von Cranbrook, BC, aktualisiert. Das Unternehmen fasst nun zwei Phasen in einem einzigen Antrag zusammen, um den unterirdischen Bergbau und die Verarbeitungsanlagen gleichzeitig wieder in Betrieb zu nehmen. CCMI hat Moose Mountain Technical Services für die Planung des Untertagebergwerks beauftragt (voraussichtliche Fertigstellung: August 2025) und ALS Metallurgical Services mit Feuchtigkeitszellentests an Tailings.

Das Unternehmen verkauft vorangereichertes Kupfer-, Gold- und Silbermaterial an New Afton im Rahmen eines Erz-Kaufvertrags und hat etwa 7.900 Tonnen geliefert, weitere 2.100 Tonnen werden bis August 2025 erwartet. Die verbleibenden 170.000 Tonnen mineralisierter Feinanteile werden nach dem Neustart als erste Mahlgutversorgung für etwa acht Monate dienen. Das BRM-Projekt verfügt über mehr als 100 Millionen Dollar an nutzbarer Infrastruktur und 22.000 Meter zugängliche unterirdische Stollen.

Positive
  • Revenue from Ore Purchase Agreement has improved financial position without shareholder dilution
  • Existing infrastructure worth over $100 million, including grid power and all-weather roads
  • 22,000 metres of readily accessible underground workings
  • 170,000 tonnes of mineralized material available for initial mill feed
  • Project is one of the most advanced non-producing mining projects in British Columbia
Negative
  • Permit application process delayed until Q1 2026
  • Additional engineering studies and testing required before final permit submission

Calgary, Alberta--(Newsfile Corp. - May 23, 2025) - Canadian Critical Minerals Inc. (TSXV: CCMI) (OTCQB: RIINF) ("CCMI" or the "Company") is pleased to provide an update on its application to restart the Bull River Mine ("BRM") project near Cranbrook, BC.

Further to discussion with the Major Mines Permitting Office of the Ministry of Mining and Critical Minerals of British Columbia ("MMCM"), the Company has decided to modify its current application to restart the BRM project by combining project phases into one application. If approved, this will allow the Company to restart underground mining and milling operations at the same time. To-date the Company has advanced its application to restart the BRM project in a phased approach in order to reduce the costs associated with completion of all detailed engineering studies in support of the application.

The Company is currently working with consultants to complete its application to restart the BRM mine and mill. Moose Mountain Technical Services has been engaged to provide a detailed underground mine plan with estimated completion by early August 2025. ALS Metallurgical Services has been engaged to conduct humidity cell testing on tailings that are planned to be produced from milling operations. This is follow-up work from a previous humidity cell testing program already completed. Humidity cell testing in a laboratory environment simulates the expected metal leaching from a tailings storage facility over time. Previously, the Company completed a detailed design of its proposed filtered tailings facility using Stantec Engineering. Once all engineering reports are complete, the Company plans to incorporate them into a Final Permit Application and make its submission to MMCM in Q1 2026.

Originally, under phase one of the restart, the Company sought permission to restart the past-producing BRM project by processing a large 180,000 tonne surface stockpile of mineralized material through its existing 700 tonne per day conventional mill and deposit tailings on surface in a dry stack or filtered tailings facility. Under phase two, the Company plans to seek permission to restart underground mining, continue to use the 700 tonne per day mill and begin sending filtered tailings back to the underground as cemented backfill.

In April 2024, the Company began selling preconcentrated copper, gold and silver mineralized material that has been upgraded through an ore sorter to New Afton under an Ore Purchase Agreement ("OPA"). To-date the Company has crushed and screened the entire surface stockpile and trucked approximately 7,900 tonnes of pre-concentrated mineralized material to New Afton. The Company expects to send an additional 2,100 tonnes of mineralized material to New Afton by the end of August 2025. The remaining 170,000 tonnes of mineralized fines and rejects from the crushing, screening and sorting of the surface stockpile will remain at the BRM and will provide an initial feed to the BRM mill for approximately eight months following restart of operations.

Revenues from the OPA have allowed the Company to significantly reduce payables, offset the costs of care and maintenance and pay for the additional costs associated with the permit applications without incurring additional dilution to shareholders. With the Company's improved financial position, all remaining engineering studies can be completed in a more sequential and expedited manner. The BRM project has over $100 million of usable infrastructure and is already connected to grid power and all-weather roads. The BRM is being maintained in a dewatered condition with over 22,000 metres of underground workings readily accessible from surface to a depth of 350 metres.

Ian Berzins, President and CEO of CCMI commented, "Revenues generated from the sale of a portion of our stockpiled mineralized material have improved the Company's ability to advance the permitting process in a more expedited manner. The provincial government has stated the importance of bringing on new projects in the critical minerals space. The past-producing BRM project is one of the most advanced mining projects in British Columbia currently not in production. Combining both phases under one application should result in better use of resources by First Nations and regulators in the consultation, engagement and review process."

About Canadian Critical Minerals Inc.

CCMI is a mining company primarily focused on copper production assets in Canada. CCMI's main asset is the 100% owned Bull River Mine project (150 million lbs of copper) near Cranbrook, British Columbia which has a Mineral Resource containing copper, gold and silver. CCMI also owns a 10% interest in XXIX Metal Corp. which holds a 100% interest in the Thierry copper project near Pickle Lake, Ontario and a 100% interest in the Opemiska copper project near Chapais-Chibougamau, Quebec.

Contact Information
Canadian Critical Minerals Inc.
Ian Berzins
President & Chief Executive Officer
M: +1-403-512-8202
E: iberzins@canadiancriticalmineralsinc.com
Website: www.canadiancriticalmineralsinc.com

Caution Regarding Forward-Looking Information

This news release includes certain information that may constitute "forward-looking information" under applicable Canadian securities legislation. Forward-looking information includes, but is not limited to, statements about strategic plans, future work programs and objectives and expected results from such work programs. Forward-looking information necessarily involve known and unknown risks, including, without limitation, risks associated with general economic conditions; inability to access sufficient capital from internal and external sources, and/or inability to access sufficient capital on favourable terms; and other risks.

Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking information and the risks identified in the Company's continuous disclosure record. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. All forward-looking information contained in this news release is given as of the date hereof and is based upon the opinions and estimates of management and information available to management as at the date hereof. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, except as required by law.

Neither the TSX Venture Exchange nor its Regulation Service Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this new release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/253333

FAQ

When will Canadian Critical Minerals (RIINF) submit its final permit application for Bull River Mine?

The company plans to submit its Final Permit Application to the Ministry of Mining and Critical Minerals of British Columbia in Q1 2026, after completing all required engineering reports.

How much mineralized material has RIINF shipped to New Afton under the Ore Purchase Agreement?

The company has shipped approximately 7,900 tonnes of pre-concentrated mineralized material to New Afton, with an additional 2,100 tonnes expected by August 2025.

What is the processing capacity of Bull River Mine's existing mill?

The Bull River Mine has an existing conventional mill with a capacity of 700 tonnes per day.

How much infrastructure value does the Bull River Mine project have?

The Bull River Mine project has over $100 million of usable infrastructure, including grid power connection and all-weather roads.

How much initial mill feed material does RIINF have available at Bull River Mine?

The company has 170,000 tonnes of mineralized fines and rejects that will provide approximately eight months of initial feed for the mill after operations restart.
Canadian Critical Minerals Inc

OTC:RIINF

RIINF Rankings

RIINF Latest News

RIINF Stock Data

7.16M
271.79M
7.92%
0%
Other Precious Metals & Mining
Basic Materials
Link
Canada
Calgary