Seabridge Gold's KSM Tunnel Authorizations Face Third Legal Challenge from Tudor Gold
Seabridge Gold (NYSE: SA) said Tudor Gold filed a Petition in British Columbia Supreme Court on October 7, 2025 seeking judicial review of a September 2024 Licence of Occupation (the 2024 LoO) that authorizes construction and operation of the KSM Project's Mitchell Treaty Tunnels (MTT).
The MTT are two 23 km parallel tunnels, with about 12.5 km passing through Tudor's Treaty Project mineral claims. Tudor asks the court to sever the 2024 LoO rights over those claims and to quash WLRS's decision, alleging procedural unfairness and claiming the MTT would destroy the Treaty Creek Project's economic viability. Seabridge says the 2024 LoO replaces a 2014 licence, protects Tudor's mineral rights for spoil storage, and remains in effect unless successfully overturned.
Seabridge Gold (NYSE: SA) ha dichiarato che Tudor Gold ha depositato una petizione presso la Corte Suprema della British Columbia il 7 ottobre 2025 richiedendo un riesame giudiziario di una licenza di occupazione del settembre 2024 (la LoO 2024) che autorizza la costruzione e l'operatività dei Mitchell Treaty Tunnels (MTT) del progetto KSM.
I MTT sono due tunnel paralleli di 23 km, di cui circa 12,5 km attraversano le rivendicazioni mineralistiche del Progetto Treaty di Tudor. Tudor chiede al tribunale di separare i diritti della LoO 2024 su tali rivendicazioni e di annullare la decisione di WLRS, sostenendo irregolarità procedurali e affermando che i MTT distruggerebbero la redditività economica del Treaty Creek Project. Seabridge afferma che la LoO 2024 sostituisce una licenza del 2014, protegge i diritti minerari di Tudor per lo stoccaggio di materiale di scarto, e rimane in vigore a meno che non venga annullata con successo.
Seabridge Gold (NYSE: SA) dijo que Tudor Gold presentó una petición ante la Corte Suprema de British Columbia el 7 de octubre de 2025 para la revisión judicial de una Licencia de Ocupación de septiembre de 2024 (la LoO 2024) que autoriza la construcción y operación de los Mitchell Treaty Tunnels (MTT) del Proyecto KSM.
Los MTT son dos túneles paralelos de 23 km, con unos 12,5 km que atraviesan las reclamaciones minerales del Proyecto Treaty de Tudor. Tudor solicita al tribunal separar los derechos de la LoO 2024 sobre esas reclamaciones y anular la decisión de WLRS, alegando irregularidades procesales y sosteniendo que los MTT destruirían la viabilidad económica del Proyecto Treaty Creek. Seabridge dice que la LoO 2024 reemplaza una licencia de 2014, protege los derechos mineros de Tudor para el almacenamiento de desechos, y permanece en vigor a menos que sea revocada con éxito.
Seabridge Gold (NYSE: SA)는 Tudor Gold가 2025년 10월 7일에 브리티시컬럼비아주 최고법원에 소장을 제출하여 2024년 9월의 점유사용허가 (LoO 2024)에 대한 재판적 심사를 청구했다고 밝혔다. 이는 KSM 프로젝트의 Mitchell Treaty Tunnels (MTT) 건설 및 운영을 허가한다.
MTT는 23km의 두 평행 터널로 구성되며, 약 12.5km가 Tudor의 Treaty Project 광권 명세를 지나간다. Tudor는 법원에 해당 주장들에 대한 2024 LoO 권리를 분리하고 WLRS의 결정을 취소해 달라고 요청하며, 절차상 불공정을 제시하고 MTT가 Treaty Creek 프로젝트의 경제적 타당성을 파괴할 것이라고 주장한다. Seabridge는 2024 LoO가 2014년 라이선스를 대체하고 Tudor의 광권 보관을 위한 파편저장 권리를 보호하며, 성공적으로 취소되지 않는 한 효력을 유지한다고 말한다.
Seabridge Gold (NYSE: SA) a déclaré que Tudor Gold a déposé une pétition devant la Cour suprême de la Colombie-Britannique le 7 octobre 2025 demandant un contrôle judiciaire d'une Licence d'occupation (LoO) de septembre 2024 (la LoO 2024) qui autorise la construction et l'exploitation des Mitchell Treaty Tunnels (MTT) du projet KSM.
Les MTT sont deux tunnels parallèles de 23 km, dont environ 12,5 km traversent les revendications minières du projet Treaty de Tudor. Tudor demande au tribunal de séparer les droits de la LoO 2024 sur ces revendications et d'annuler la décision de WLRS, en avançant des irrégularités procédurales et en soutenant que les MTT détruiraient la viabilité économique du projet Treaty Creek. Seabridge affirme que la LoO 2024 remplace une licence de 2014, protège les droits miniers de Tudor pour le stockage des déblais, et reste en vigueur sauf si elle est annulée avec succès.
Seabridge Gold (NYSE: SA) sagte, Tudor Gold habe am 7. Oktober 2025 eine Petition vor dem Obersten Gerichtshof von British Columbia eingereicht, um eine gerichtliche Überprüfung einer Lizenz zur Nutzung (Licence of Occupation) vom September 2024 (die LoO 2024) zu beantragen, die den Bau und Betrieb der Mitchell Treaty Tunnels (MTT) des KSM-Projekts erlaubt.
Die MTT sind zwei parallele Tunnel von 23 km, von denen ca. 12,5 km durch Tudor's Treaty Project Minenansprüche verlaufen. Tudor bittet das Gericht, die Rechte aus der LoO 2024 auf diese Ansprüche abzutrennen und die WLRS-Entscheidung aufzuheben, und führt prozessuale Unfairness an und behauptet, dass die MTT die wirtschaftliche Rentabilität des Treaty Creek Project zerstören würden. Seabridge erklärt, die LoO 2024 ersetze eine Lizenz von 2014, schütze Tudors Bergbaurechte für Abraumlagerung und bleibe in Kraft, solange sie nicht erfolgreich außer Kraft gesetzt wird.
Seabridge Gold (NYSE: SA) قالت إن Tudor Gold قد قدمت عريضة أمام المحكمة العليا في كولومبيا البريطانية في 7 أكتوبر 2025 تطلب مراجعة قضائية لرخصة احتلال (Licence of Occupation) من سبتمبر 2024 (المعروفة بـ LoO 2024) التي تسمح بالبناء والتشغيل لأنفاق Mitchell Treaty Tunnels (MTT) ضمن مشروع KSM.
MTT هما نفقان متوازيان بطول 23 كم، يمران تقريباً عبر 12.5 كم من مطالب Tudor Project Treaty المعدنية. Tudor تطلب من المحكمة فصل حقوق LoO 2024 على هذه المطالب وإلغاء قرار WLRS، مدعية ظلمًا إجرائيًا وتقول إن MTT ستدمر الجدوى الاقتصادية لمشروع Treaty Creek. تقول Seabridge إن LoO 2024 تحل محل ترخيص 2014، تحمي الحقوق المعدنية لـ Tudor لتخزين المخلفات، وتبقى سارية المفعول ما لم يتم إلغاؤها بنجاح.
Seabridge Gold (NYSE: SA) 表示 Tudor Gold 已于 2025年10月7日 在不列颠哥伦比亚省高等法院提交请愿,就一份 2024年9月 的占用许可(LoO 2024)进行司法复审,该许可授权了 KSM 项目 Mitchell Treaty 隧道(MTT)的建设和运营。
MTT 是两条 23 公里 的平行隧道,其中约 12.5 公里 穿过 Tudor 的 Treaty Project 矿权索赔区域。Tudor 要求法院将这些索赔上的 2024 LoO 权利剥离,并撤销 WLRS 的决定,声称程序不公,并称 MTT 将摧毁 Treaty Creek 项目的经济可行性。Seabridge 表示 2024 LoO 取代了 2014 年的许可,保护 Tudor 的矿权用于废料存储,并且在未被成功推翻前仍然有效。
- MTT plan: two 23 km parallel tunnels
- Approximately 12.5 km of MTT route crosses Treaty Project claims
- 2024 LoO replaces earlier 2014 licence and remains in force pending court outcome
- KSM holds environmental assessment approvals and a pre-feasibility study
- Tudor filed a Petition on October 7, 2025 seeking to quash the 2024 LoO
- Tudor asserts MTT would destroy Treaty Creek Project economic viability
- This is Tudor's third separate legal action challenging MTT authorizations
Insights
Seabridge faces a material procedural legal challenge to a key tunnel licence that could affect construction access through mineral-claimed land.
Seabridge, its subsidiary KSM Mining ULC, the Province (WLRS) and Tudor Gold are in litigation over the 2024 Licence of Occupation that authorizes construction of the Mitchell Treaty Tunnels (MTT). Tudor seeks declarations that the licence cannot interfere with a mineral claims holder, asks that rights across Tudor’s Treaty Project Claims be severed, and asks the court to quash WLRS’s decision; Tudor alleges procedural unfairness or unreasonableness. The 2024 LoO replaced a 2014 LoO and covers a narrow corridor where roughly 12.5 km of the planned two 23 km parallel tunnels would cross Treaty Project Claims.
The business mechanism at stake is statutory land authorization versus mineral-claim rights: WLRS granted a provincial occupation licence to permit infrastructure across Crown land that overlies mineral claims; Tudor contends that such a licence cannot lawfully impair a mineral claims holder’s rights. The Province’s decision remains in effect while the petition proceeds. Seabridge states the LoO terms protect Tudor’s mineral rights and frames the LoO as routine infrastructure authorization, noting the KSM Project has environmental assessment approvals, pre-feasibility work, and various construction permits.
Key dependencies and risks hinge on the court’s legal interpretation and outcome. If the court finds the LoO invalid or severs provisions, the MTT corridor rights across the Treaty Project Claims could be lost or narrowed, which would materially constrain construction plans for the MTT segment that traverses Tudor’s claims. Conversely, if WLRS and Seabridge successfully defend the LoO, the licence will remain operative. Tudor currently pursues three separate legal actions aimed at MTT authorizations; that fact increases litigation risk and parallel legal exposure for the project.
Watch for the court’s rulings on the petition, any orders affecting the 2024 LoO, and the status of Tudor’s other lawsuits; these items will directly determine near-term construction rights for the MTT. The presence of existing environmental assessment approvals and multiple permits for portions of the MTT is relevant factual context to monitor alongside judicial outcomes.
It Seeks to Void Licence of Occupation
Toronto, Ontario--(Newsfile Corp. - October 7, 2025) - Seabridge Gold Inc. (TSX: SEA) (NYSE: SA) (the "Company") announced today that Tudor Gold Corp. ("Tudor") has filed a Petition in the British Columbia Supreme Court against the British Columbia Ministry of Water, Land and Resource Stewardship ("WLRS") and the Company and the Company's wholly-owned subsidiary that owns
The 2024 LoO provides Seabridge with the right to occupy a narrow corridor in which it proposes to construct and operate the MTT. The 2024 LoO was a replacement of a prior Licence of Occupation that had been issued to Seabridge in 2014 over the same land. The MTT are two 23 km long parallel tunnels planned to connect the east and west sides of the KSM Project Mine Site. Approximately 12.5 km of the MTT route pass through the Treaty Project Claims.
In its Petition, Tudor is seeking declarations that: (1) a Licence of Occupation cannot interfere with the rights of a mineral claims holder; (2) all provisions of the 2024 LoO that grant Seabridge rights across the Treaty Project Claims are severed from the 2024 LoO; and, (3) an order quashing WLRS's decision to grant the 2024 LoO. The Petition includes an allegation that WLRS's decision to grant the 2024 LoO was procedurally unfair or unreasonable. The Petition also asserts that construction of the MTT requires Seabridge to have a right to the Treaty Project Claims since, according to Tudor: "If constructed according to its current plan, the MTT will destroy the economic viability of the Treaty Creek Project and remove all reasonable uses of Tudor's property."
As a mineral claims holder, Tudor owns the rights to the minerals within the area of its mineral claims. However, the land that the Treaty Project Claims covers is land owned by the Province of British Columbia. The terms of the 2024 LoO are designed to protect Tudor's rights to the minerals within its claims; requiring Seabridge to store the small amount of material excavated during MTT construction within the Treaty Project Claims under Tudor's ownership. Construction of the MTT is similar to construction of roads, pipelines, railways, or other infrastructure across public land. In its Petition, Tudor is essentially asserting that the Province can't authorize the construction of infrastructure through land owned by the Province if there is a mineral claim covering it. If true, that would render large portions of British Columbia unavailable for construction of infrastructure without the consent of mineral claims holders. The statutory regime is not set up that way.
"In granting the 2024 LoO, WLRS has exercised its discretion to support the KSM Project, which has its environmental assessment approvals, a pre-feasibility study demonstrating economic viability, substantial investments in early construction and many permits for construction of infrastructure, including portions of the MTT. KSM has therefore been determined to be in the interests of British Columbia. Considering that the Treaty Creek Project not only does not have environmental assessment approvals or a preliminary economic assessment, but has not even articulated a comprehensive project development plan, I am confident that WLRS has acted appropriately in authorizing Seabridge to use Provincial land for the MTT," said Seabridge's Chair and CEO, Rudi Fronk. He added: "We have attempted to find terms to avoid a conflict like this with Tudor, but their demands have been unreasonable. Tudor now has three concurrent, separate legal actions all directed at voiding authorizations for the MTT. In our view, if Tudor thinks it must bring three separate legal actions, it probably lacks confidence in the success of any one of them."
For reference, here are our news releases of July 14, 2025 and October 3, 2025 responding to Tudor's previous MTT challenges.
The 2024 LoO is currently unaffected by the filing of the Petition and will remain in place if the Province and the Company successfully defend the 2024 LoO.
About Seabridge Gold
Seabridge holds a
Neither the Toronto Stock Exchange, New York Stock Exchange, nor their Regulation Services Providers accepts responsibility for the adequacy or accuracy of this release.
ON BEHALF OF THE BOARD
"Rudi Fronk"
Chair & C.E.O.
For further information please contact:
Rudi P. Fronk, Chair and C.E.O.
Tel: (416) 367-9292 • Fax: (416) 367-2711
Email: info@seabridgegold.com
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/269423