Stabilis Solutions (Nasdaq: SLNG) announced a 10-year marine bunkering agreement to supply ~50 million gallons (188,000 m3) per year of LNG at the Port of Galveston, supporting its planned Galveston LNG liquefaction project.

The contract covers roughly 40% of the planned facility, with deliveries expected to begin in Q4 2027 subject to financing and construction. Stabilis must finalize project financing by Q1 2026 and complete construction by Q2 2028. The Galveston facility is planned as a 350,000 gallon-per-day plant, increasing company liquefaction capacity from 130,000 to 480,000 gallons-per-day. A Jones Act-compliant bunkering vessel is also planned.

Stabilis Solutions (Nasdaq: SLNG) ha annunciato un accordo decennale di bunkeraggio marino per fornire ~50 milioni di galloni (188.000 m3) all'anno di LNG presso il Porto di Galveston, sostenendo il suo previsto progetto di liquefazione LNG a Galveston.

Il contratto copre circa il 40% della struttura pianificata, con le consegne previste per il quarto trimestre del 2027, soggetto a finanziamenti e costruzione. Stabilis deve finalizzare il finanziamento del progetto entro il primo trimestre del 2026 e completare la costruzione entro il secondo trimestre del 2028. L'impianto di Galveston è pianificato come uno stabilimento da 350.000 galloni al giorno, aumentando la capacità di liquefazione della società da 130.000 a 480.000 galloni al giorno. È prevista anche una nave di bunkering conforme al Jones Act.

Stabilis Solutions (Nasdaq: SLNG) anunció un acuerdo de bunkering marino de 10 años para suministrar ~50 millones de galones (188.000 m3) por año de LNG en el Puerto de Galveston, apoyando su previsto proyecto de liquefacción LNG de Galveston.

El contrato cubre aproximadamente el 40% de la instalación planificada, con entregas previstas para el cuarto trimestre de 2027 sujetas a financiación y construcción. Stabilis debe finalizar la financiación del proyecto para el primer trimestre de 2026 y completar la construcción para el segundo trimestre de 2028. La instalación de Galveston está prevista como una planta de 350,000 galones por día, aumentando la capacidad de liquefacción de la empresa de 130,000 a 480,000 galones por día. También se planea un buque de bunkering conforme a Jones Act.

Stabilis Solutions (나스닥: SLNG)은 Galveston 항에서 매년 약 5천만 갤런(188,000 m3)의 LNG를 공급하는 10년간의 해상 벙커링 계약을 발표하여 Galveston LNG 액화 프로젝트를 지원합니다.

계약은 예정 시설의 대략 40%를 다루며, 배송은 2027년 4분기에 시작될 예정이고, 재원 조달과 건설에 달려 있습니다. Stabilis는 2026년 1분기까지 프로젝트 자금 조달을 확정하고 2028년 2분기까지 건설을 완료해야 합니다. Galveston 시설은 하루 350,000갤런의 플랜트로 계획되며, 회사의 액화 용량을 130,000에서 480,000갤런/일로 증가시킵니다. Jones Act에 부합하는 벙커링 선박도 계획되어 있습니다.

Stabilis Solutions (NYSE: SLNG) a annoncé un accord de bunkering maritime de 10 ans pour fournir environ 50 millions de gallons (188 000 m3) par an de LNG au port de Galveston, soutenant son projet prévu de liquéfaction LNG à Galveston.

Le contrat couvre environ 40 % de l’installation prévue, les livraisons devant commencer au Q4 2027 sous réserve de financement et de construction. Stabilis doit finaliser le financement du projet d’ici Q1 2026 et achever la construction d’ici Q2 2028. L’installation de Galveston est prévue comme une usine de 350 000 gallons par jour, augmentant la capacité de liquéfaction de l’entreprise de 130 000 à 480 000 gallons par jour. Un navire de bunkering conforme Jones Act est également prévu.

Stabilis Solutions (Nasdaq: SLNG) kündigte eine 10-Jahres-Versorgungsvereinbarung für maritimes Bunkering an, um jährlich ca. 50 Millionen Gallonen (188.000 m3) LNG im Hafen von Galveston zu liefern und so das geplante Galveston LNG-Verflüssigungsprojekt zu unterstützen.

Der Vertrag deckt ca. 40% der geplanten Anlage ab, Lieferungen sollen in Q4 2027 beginnen und hängen von Finanzierung und Bau ab. Stabilis muss die Projektfinanzierung bis Q1 2026 abschließen und den Bau bis Q2 2028 beenden. Die Galveston-Anlage ist als eine Anlage mit 350.000 Gallonen pro Tag geplant, wodurch die Verflüssigungskapazität des Unternehmens von 130.000 auf 480.000 Gallonen pro Tag steigt. Ebenfalls geplant ist ein bunkering-Schiff, das dem Jones Act entspricht.

Stabilis Solutions (ناسداك: SLNG) أعلنت عن اتفاقية تزويد بترسانة بحرية لمدة 10 سنوات لتوفير حوالي 50 مليون جالون (188,000 م3) من LNG سنوياً في ميناء غالفستون، دعماً لمشروع التصعيد LNG في غالفستون المقرر.

يغطي العقد نحو حوالي 40% من المنشأة المخطط لها، مع توقع بدء التسليم في الربع الرابع من 2027 رهناً بالتمويل والبناء. يجب على ستابيليس إنهاء تمويل المشروع بحلول الربع الأول من 2026 واستكمال البناء بحلول الربع الثاني من 2028. من المقرر أن تكون منشأة غالفستون بمعدل 350,000 جالون يومياً، مما يزيد قدرة التليين للشركة من 130,000 إلى 480,000 جالون يومياً. كما يُخطّط لوجود سفينة bunkering متوافقة مع Jones Act.

Stabilis Solutions (纳斯达克: SLNG) 宣布了一项为期10年的海上加注燃料协议,每年在加尔维斯顿港供应约50,000,000 加仑 (188,000 立方米) 的 LNG,以支持其在加尔维斯顿的 LNG 液化项目。

该合同大致覆盖< b>计划设施的40%,预计在< b>2027年第四季度开始交付,需融资和建设。Stabilis 必须在< b>2026年第一季度前完成项目融资,并在< b>2028年第二季度前完成建设。加尔维斯顿设施规划为日产< b>350,000 加仑的工厂,将公司的液化能力从< b>130,000 提升至 480,000 加仑/日。还计划建造一艘符合 Jones Act 的加注船。

Positive
  • 10-year anchor contract for ~50 million gallons/year
  • Contract secures ~40% of Galveston facility capacity
  • Planned liquefaction capacity rising to 480,000 gallons/day
  • Deliveries targeted to begin in Q4 2027 (subject to conditions)
  • Identified site and completed front-end engineering
Negative
  • Project financing required by Q1 2026 to meet timelines
  • Construction completion deadline is Q2 2028, subject to risk
  • Deliveries contingent on successful financing and construction

Insights

Ten-year, 40%‑anchoring bunkering contract materially improves project bankability if financing and construction milestones are met.

The agreement secures supply commitments for approximately 40% of the planned Galveston liquefaction facility and specifies annual volumes of about 50 million gallons. The contract sets clear commercial anchors and links project deliverables to concrete timelines, including finalizing project financing by Q1 2026 and completing construction by Q2 2028.

Execution risk centres on the stated financing and construction conditions; deliveries only begin in Q4 2027 subject to those items. Key monitorables are attainment of Q1 2026 financing, construction start timing, and any definitive financing terms from Evercore or partners.

HOUSTON, TEXAS / ACCESS Newswire / October 9, 2025 / Stabilis Solutions, Inc., ("Stabilis" or the "Company") (Nasdaq:SLNG), a leading provider of clean energy production, storage, and delivery solutions, today announced that it has entered into a 10-year agreement with a leading investment-grade global marine operator to supply Liquefied Natural Gas ("LNG") for their marine bunkering operations at the Port of Galveston.

The long-term agreement marks the Company's first marine bunkering contract for liquefaction supply from its planned expansion along the Texas Gulf Coast. This milestone enables the Company to advance development of a new flagship waterfront LNG liquefaction facility, together with related marine logistics infrastructure, in Galveston, Texas.

NEW LONG-TERM MARINE BUNKERING AGREEMENT

Stabilis has executed a 10-year bunkering agreement, to supply approximately 50 million gallons (or 188,000 cubic meters) per year of LNG for marine bunkering operations in the Port of Galveston. Deliveries under the agreement are expected to commence in the fourth quarter of 2027, subject to the successful financing and construction of the Galveston LNG facility and other conditions precedent.

Under the terms of the agreement, Stabilis is required, among other things, to finalize project financing by the first quarter 2026 and complete construction on the Galveston LNG facility by the second quarter 2028.

GALVESTON LNG LIQUEFACTION PROJECT

The proposed Galveston LNG facility is expected to be a 350,000 gallon-per-day waterfront LNG liquefaction facility. Upon completion, the facility is anticipated to increase Stabilis' liquefaction capacity from 130,000 gallons-per-day from its two existing liquefaction facilities to 480,000 gallons-per-day. The new facility will be strategically located to continue to serve Stabilis' cruise customers as well as additional marine end markets such as container ships, car carriers, tankers, and bulk carriers in the Port of Galveston, Port of Houston, and surrounding Gulf Coast markets. The bunkering agreement represents approximately 40% of the Galveston LNG facility's planned capacity and provides a key anchor contract to advance the project.

With the construction of its new LNG facility, Stabilis also plans to commission a dedicated Jones Act-compliant LNG bunkering vessel to serve the Port of Galveston. This vessel will transport LNG from the facility directly to waterborne customer vessels. Together, the new LNG facility and bunkering vessel are expected to create a fully integrated, last-mile LNG delivery solution for customers.

The Company has identified a site for the new facility and has completed initial front-end-engineering and design activities. The Company expects to complete the necessary financing and begin construction of the plant in early 2026.

Evercore is serving as financial advisor to Stabilis in the financing and structuring of this transaction.

MANAGEMENT COMMENTARY

"Our new 10-year bunkering agreement marks a transformational milestone for Stabilis, one that secures the commercial scale required to advance our investment in liquefaction capacity on the Gulf Coast," stated Casey Crenshaw, Executive Chairman and Interim President & Chief Executive Officer. "Once the Galveston LNG facility comes online, anticipated in late 2027, it will become our largest liquefaction plant by capacity, significantly increasing our market presence within the Gulf Coast while meeting growing customer demand for reliable, clean marine LNG fueling solutions."

"In addition to our newly contracted bunkering agreement, Stabilis is also in advanced discussions and negotiations with a diverse base of customers seeking to source LNG from our Galveston LNG facility," continued Crenshaw. "Importantly, this long-term bunkering agreement secures 40% of the planned capacity at the Galveston LNG facility, and we remain in active discussions to contract the remaining capacity."

"As we advance toward FID on the Galveston LNG facility, we intend to maintain our balance sheet discipline and return-driven approach toward capital allocation," continued Crenshaw. "To that end, we are actively engaged with our advisors in finalizing the optimal structure to support this important expansionary phase for Stabilis, consistent with our long-term focus on value creation for both our customers and shareholders."

ABOUT STABILIS SOLUTIONS

Stabilis Solutions (Nasdaq:SLNG) is a leading provider of clean energy production, storage, and delivery solutions to multiple end markets. To learn more, visit www.stabilis-solutions.com.

CAUTIONARY STATEMENTS REGARDING FORWARD-LOOKING STATEMENTS

This press release includes "forward-looking statements" within the meaning of the safe harbor provisions of the U.S. Private Securities Litigation Reform Act of 1995 and within the meaning of Section 27a of the Securities Act of 1933, as amended, and Section 21e of the Securities Exchange Act of 1934, as amended. Any actual results may differ from expectations, estimates and projections presented or implied and, consequently, you should not rely on these forward-looking statements as predictions of future events. Words such as "can," "believes," "feels," "anticipates," "expects," "could," "will," "plan," "may," "should," "predicts," "potential," "outlook" and similar expressions are intended to identify such forward-looking statements.

Such forward-looking statements relate to future events or future performance, but reflect our current beliefs, based on information currently available. Most of these factors are outside our control and are difficult to predict. A number of factors could cause actual events, performance or results to differ materially from the events, performance and results discussed in the forward-looking statements. Factors that may cause such differences include, among other things: the future performance of Stabilis, future demand for and price of LNG, availability and price of natural gas, unexpected costs, availability of financing, ability to achieve the conditions precedent to the bunkering agreement, ability to achieve additional offtake necessary for FID, construction delays or cost overruns, regulatory or other legal impediments, and general economic conditions.

The foregoing list of factors is not exclusive. Additional information concerning these and other risk factors is contained in the Risk Factors in Item 1A of our Annual Report on Form 10-K filed with the Securities and Exchange Commission on February 25, 2025 which is available on the SEC's website at www.sec.gov or on the Investors section of our website at www.stabilis-solutions.com. All subsequent written and oral forward-looking statements concerning Stabilis, or other matters attributable to Stabilis, or any person acting on its behalf are expressly qualified in their entirety by the cautionary statements above. Readers are cautioned not to place undue reliance upon any forward-looking statements, which speak only as of the date made.

Stabilis does not undertake or accept any obligation or undertaking to release publicly any updates or revisions to any forward-looking statement to reflect any change in their expectations or any change in events, conditions or circumstances on which any such statement is based, except as required by law.

CORPORATE CONTACT

Andrew Puhala
Chief Financial Officer
ir@stabilis-solutions.com

SOURCE: Stabilis Solutions



View the original press release on ACCESS Newswire

FAQ

What did Stabilis (SLNG) announce on October 9, 2025?

Stabilis announced a 10-year marine bunkering agreement to supply ~50 million gallons/year of LNG at the Port of Galveston.

When will SLNG deliveries from the Galveston project begin?

Deliveries are expected to commence in Q4 2027, subject to successful financing and construction.

How much capacity will the Galveston LNG facility add for SLNG?

The planned Galveston facility is 350,000 gallons/day, increasing total liquefaction capacity from 130,000 to 480,000 gallons/day.

What financing milestone must SLNG meet for the Galveston project?

Stabilis must finalize project financing by Q1 2026 under the agreement's terms.

What portion of the Galveston facility is covered by the bunkering agreement?

The bunkering agreement represents approximately 40% of the planned Galveston LNG facility capacity.

Will Stabilis operate a bunkering vessel for the Galveston project?

Yes, Stabilis plans to commission a Jones Act-compliant LNG bunkering vessel to serve the Port of Galveston.
Stabilis Solutions

NASDAQ:SLNG

SLNG Rankings

SLNG Latest News

SLNG Latest SEC Filings

SLNG Stock Data

94.84M
3.32M
82.17%
5.47%
0.01%
Oil & Gas Integrated
Natural Gas Distribution
Link
United States
HOUSTON