South Star Announces Re-Start of Santa Cruz Plant Ahead of Schedule

(Neutral)
Tags

South Star Battery Metals (OTCQB: STSBF) restarted the Santa Cruz plant on April 7, 2026, beginning no-load testing that will move to load conditions after positive results. Major upgrades installed include the scrubber/trommel, discharge pump and tank, electrical systems, drying system and filter press feed pump.

Management said the re-start is nearly three months ahead of schedule, with recent heavy rainfall only slightly affecting installations. A qualified person, Marc Leduc P.Eng, reviewed the technical information.

Loading...
Loading translation...

Positive

  • Plant re-started on April 7, 2026
  • Re-start delivered nearly three months ahead of schedule
  • Major plant upgrades installed: scrubber/trommel, drying system, pumps

Negative

  • Plant currently in no-load testing; load conditions pending positive results

News Market Reaction – STSBF

+2.58%
+2.58% Session close to close

In the Apr 8 session, STSBF gained 2.58%, reflecting a moderate positive market reaction.

Data tracked by StockTitan Argus on the day of publication.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google

VANCOUVER, British Columbia, April 08, 2026 (GLOBE NEWSWIRE) -- South Star Battery Metals Corp. (“South Star” or the “Company”) (TSXV: STS) (OTCQB: STSBF) is pleased to announce that the Santa Cruz plant was re-started yesterday, April 7, 2026. Initially, the plant will be tested under no-load conditions which will transition to load conditions following positive results. This re-start is a significant milestone in the progress of this plant toward commissioning.

Santa Cruz Project Re-Start:
As previously reported (news release dated March 10, 2026), the scrubber/trommel installation was among the largest components involved in the plant feed system. Other items that were recently installed included the discharge pump and tank, electrical installations, material discharge chutes, piping, drying system (burner and cyclone), filter press feed pump and a host of associated components. All these plant upgrades are the result of operational experience gained from work with the plant in early 2025 and that allowed our experience to engineer and implement the improvements. Periods of heavy rainfall slightly impacted these installations without materially hampering progress.

Tiago Cunha, Interim CEO, states, “We are pleased to announce this plant re-start. The Santa Cruz team continues to deliver, and these efforts have placed the re-start nearly three months ahead of schedule. While Brazilians are accustomed to the annual rainy season, these rains can impede work, especially when electrical systems are involved. We look forward to more progress reports soon.”

Qualified person statement
The technical and scientific information in this news release has been reviewed and approved by Marc Leduc, P.Eng, Director, a qualified person as defined under National Instrument 43-101, Standards of Disclosure for Mineral Projects.

ABOUT SOUTH STAR BATTERY METALS CORP.

South Star is a Canadian battery metals project developer focused on the selective acquisition and development of near-term production projects in the Americas. South Star’s Santa Cruz graphite project, located in southern Bahia, Brazil, is the first of a series of industrial and battery metals projects that is anticipated to be put into production. Brazil is the second largest graphite producing region in the world with more than 80 years of continuous mining. With excellent infrastructure and logistics, Santa Cruz is slated to be the newest graphite producer in the Americas. South Star trades on the TSX Venture Exchange under the symbol STS, and on the OTCQB under the symbol STSBF. South Star is committed to a corporate culture, project execution plan and safe operations that embrace the highest standards of ESG principles, based on transparency, stakeholder engagement, ongoing education, and stewardship. To learn more, please visit the Company website at southstarbatterymetals.com.

For additional information:
South Star Investor Relations
Email : invest@southstarbatterymetals.com
Phone : +1 (303) 519-5149

This press release contains “forward-looking statements” within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be “forward-looking statements”. Forward-looking statements in this press release include, but are not limited to, statements regarding production and scaling of operations at Santa Cruz, and the Company’s plans and expectations.

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.


FAQ

When did South Star (STSBF) restart the Santa Cruz plant?

The Santa Cruz plant was restarted on April 7, 2026, initiating no-load testing. According to the company, the re-start occurred nearly three months ahead of schedule and will progress to load conditions after successful tests.

What components were installed during the Santa Cruz plant upgrade by South Star (STSBF)?

Installed components include the scrubber/trommel, discharge pump and tank, electrical systems, drying system and filter press feed pump. According to the company, these upgrades came from operational experience gained during early 2025 work.

What does no-load testing at the Santa Cruz plant mean for STSBF shareholders?

No-load testing means equipment runs without processing material while systems are checked for safety and function. According to the company, successful no-load results will lead to load testing and further steps toward full commissioning.

How did weather affect the Santa Cruz plant re-start announced by South Star (STSBF)?

Heavy rainfall slightly affected some installations but did not materially hamper progress. According to the company, seasonal rains can impede electrical work, yet the team kept the project nearly three months ahead of schedule.

Who verified the technical information about the Santa Cruz re-start for STSBF?

Marc Leduc, P.Eng, Director, reviewed and approved the technical and scientific information as a qualified person under NI 43-101. According to the company, this provides independent technical oversight for the project disclosures.