PowerBank (NASDAQ: SUUN) announced that its 2.1 MW Phillips Rd solar project on a closed landfill in upstate New York completed a Coordinated Electric System Interconnection Review (CESIR) and can now proceed to permitting with local authorities.

The project is expected to qualify for New York's VDER compensation with an estimated first-year average rate of US$0.0971/kWh, NY-Sun incentives, and federal Investment Tax Credits under the Inflation Reduction Act of 2022 and the One Big Beautiful Bill Act of 2025. Upon permits and financing, construction will begin and the site will operate as a community solar program serving roughly 262 homes.

PowerBank cites over 100 MW of completed projects and a development pipeline exceeding 1 GW, and notes standard development risks including permits, financing, construction, and potential changes to incentives.

Loading...
Loading translation...

Positive

  • Project size 2.1 MW community solar
  • Estimated VDER rate US$0.0971/kWh first-year average
  • Eligible for NY-Sun incentives and federal Investment Tax Credits
  • Company pipeline >b>1 GW and >100 MW completed

Negative

  • Project requires receipt of a community solar contract before proceeding
  • Progress contingent on permits and third-party financing
  • Construction carries typical build and schedule risks
  • Policy risk if government incentives are reduced or eliminated

News Market Reaction 12 Alerts

-5.17% News Effect
+10.8% Peak Tracked
-3.6% Trough Tracked
-$4M Valuation Impact
$69M Market Cap
0.8x Rel. Volume

On the day this news was published, SUUN declined 5.17%, reflecting a notable negative market reaction. Argus tracked a peak move of +10.8% during that session. Argus tracked a trough of -3.6% from its starting point during tracking. Our momentum scanner triggered 12 alerts that day, indicating notable trading interest and price volatility. This price movement removed approximately $4M from the company's valuation, bringing the market cap to $69M at that time.

Data tracked by StockTitan Argus on the day of publication.

Key Figures

VDER first-year rate US$0.0971/kWh Estimated first-year average compensation for Phillips Rd under VDER
Transaction value $41 million USD Sale and EPC for three New York community solar projects
Initial payment $4 million USD First payment received on ~$41 million Solar Advocate transaction
Gross profit growth 106% YoY Reported gross profit growth in Q1 2025
Phillips Rd capacity 2.1 MW Closed-landfill solar project in upstate New York
Homes powered 262 homes Estimated equivalent households served by Phillips Rd project
Completed projects over 100 MW PowerBank’s track record of completed projects
Development pipeline exceeding 1 GW PowerBank’s stated development pipeline

Market Reality Check

$1.67 Last Close
Volume Volume 2,536,671 is 1.63x the 20-day average of 1,552,942, indicating elevated trading activity. high
Technical Price $1.74 is trading below the 200-day MA at $1.87, reflecting a weak intermediate trend.

Peers on Argus 1 Up

SUUN fell 8.9% while key renewable peers were mixed: WAVE -1.92%, VGAS -9.39%, ELLO +8.61%, NXXT -10%, STEM -3.26%. Momentum scanner showed BNRG +12.29% with no news, suggesting stock-specific rather than broad sector pressure.

Historical Context

Date Event Sentiment Move Catalyst
Dec 26 Orbital cloud update Positive -4.5% Successful deployment of DeStarlink Genesis-1 satellite and roadmap disclosure.
Dec 24 Payment received Positive +4.2% Receipt of <b>$4M</b> initial payment on ~<b>$41M</b> solar transaction in New York.
Dec 22 Major NY transaction Positive +4.3% Announcement of ~<b>$41M</b> sale and EPC deal for three NY community solar projects.
Dec 18 Project completion Positive -2.8% 1.45 MW Calgary rooftop project reaches commercial operation under Alberta programs.
Dec 16 Project advancement Positive -7.7% 3.15 MW Buffalo solar-plus-storage project clears key zoning and permitting steps.
Pattern Detected

Recent news has often been positive but produced mixed to negative price reactions, with three divergences and two alignments.

Recent Company History

Over the past weeks, PowerBank reported multiple growth-oriented milestones, including a ~$41 million New York community solar transaction totaling 16.87 MW, initial payment of $4 million, and commercial operation of a 1.45 MW Alberta rooftop project. It also advanced a 3.15 MW Buffalo hybrid solar-plus-storage project and highlighted its role in the Orbital Cloud initiative. Today’s Phillips Rd project update continues the theme of expanding North American solar infrastructure and community solar assets.

Market Pulse Summary

The stock moved -5.2% in the session following this news. A negative reaction despite constructive project news fits a recent pattern where positive milestones, including a ~$41 million New York transaction and multiple MW-scale projects, coincided with mixed or negative moves after several announcements. The Phillips Rd update adds another 2.1 MW community solar asset with VDER-backed revenues, but market focus may remain on execution, permitting, financing dependencies, and evolving incentive regimes noted in company disclosures.

Key Terms

coordinated electric system interconnection review (cesir) technical
"received positive results through its Coordinated Electric System Interconnection Review (CESIR)"
A coordinated electric system interconnection review is a joint technical assessment used to evaluate requests to connect new power plants or transmission lines to the electric grid, checking how the addition would affect reliability, what upgrades are needed, and how costs and schedules should be shared across neighboring areas. For investors it acts like a building inspection and permit: passing the review determines whether a project can actually deliver power, what extra work and expense are required, and how long before the asset can start earning revenue.
value of distributed energy resources (vder) regulatory
"qualify for New York's Value of Distributed Energy Resources (VDER) compensation mechanism"
Value of Distributed Energy Resources (VDER) is a structured way utilities or regulators calculate what rooftop solar, batteries and other small local energy systems are worth to the electric grid. It breaks the total benefit into pieces—like energy produced, capacity provided, pollution avoided and grid congestion relief—so owners and investors know the payment they can expect, similar to a price sheet that shows how each service is compensated. For investors, VDER determines revenue streams, project economics and incentives, so it directly affects returns, project size and financing decisions.
investment tax credits financial
"expected to qualify for incentives under NYSERDA's NY-Sun program and federal Investment Tax Credits"
Investment tax credits are government discounts on an investor’s tax bill tied to putting money into certain projects or assets, effectively returning a portion of the upfront cost as a tax saving. They matter to investors because they improve after-tax returns and can make otherwise marginal projects more profitable—like a manufacturer offering a coupon that lowers the net price of a major purchase—so they influence valuation, cash flow forecasts and investment decisions.
inflation reduction act of 2022 regulatory
"federal Investment Tax Credits under the Inflation Reduction Act of 2022"
A federal law that reshaped government funding, tax incentives and spending rules to lower certain consumer costs, support clean energy and change tax treatment for businesses. For investors it matters because it alters the financial incentives and costs across industries—like changing traffic signals on where capital flows—creating new opportunities for some companies, raising compliance or tax costs for others, and shifting long‑term sector profitability.
community solar technical
"project set to operate as a community solar initiative"
Community solar is a shared solar power system that allows multiple people or businesses to benefit from a single solar installation, often located off their property. Participants typically buy or lease a portion of the solar energy generated, which helps reduce their electricity bills and supports renewable energy efforts. For investors, community solar represents an opportunity to support sustainable projects while earning stable returns from a growing clean energy market.

AI-generated analysis. Not financial advice.

Project to Power Equivalent of Approximately 262 Homes

TORONTO, Dec. 30, 2025 /PRNewswire/ - PowerBank Corporation (NASDAQ: SUUN) (Cboe CA: SUNN) (FSE: 103) ("PowerBank" or the "Company"), a North American energy infrastructure developer and asset owner, is pleased to announce a new 2.1 MW solar project located on a closed landfill in upstate New York, known as Phillips Rd (the "Project"). 

The Company secured site control on the Project in the form of a land lease and received positive results through its Coordinated Electric System Interconnection Review (CESIR) and now can proceed to permitting with local authorities. 

The Phillips Rd project is poised to qualify for New York's Value of Distributed Energy Resources (VDER) compensation mechanism under Case 15-E-0751, with an estimated first-year average rate of US$0.0971/kWh. This VDER rate ensures fair compensation for clean energy delivered to the grid, reinforcing the project's financial and environmental viability.

The Project is also expected to qualify for incentives under NYSERDA's NY-Sun program and federal Investment Tax Credits under the Inflation Reduction Act of 2022 and the One Big Beautiful Bill Act of 2025.

Upon securing permits and financing, PowerBank will commence construction, with the project set to operate as a community solar initiative. This innovative model enables renters, businesses, and homeowners to subscribe to the solar farm, receiving bill credits and savings without installing on-site equipment. By feeding clean energy directly into the local grid, the Project offers an accessible pathway for New Yorkers to embrace the clean energy transition.

PowerBank's proven expertise, with over 100 MW of completed projects and a development pipeline exceeding 1 GW, underpins the projects' execution. Strategic partnerships and institutional-grade development capabilities position PowerBank to deliver reliable, high-impact renewable energy solutions.

The Phillips Rd project advances New York's path to 10 GW of solar by 2030. The State leads the United States in community solar capacity, having achieved the New York State Climate Act 6 GW solar goal in the fall of 2024.

There are several risks associated with the development of the Project. The development of any project is subject to receipt of a community solar contract, receipt of required permits, the availability of third-party financing arrangements for the Company and the risks associated with the construction of a solar power project. In addition, governments may revise, reduce or eliminate incentives and policy support schemes for solar power, which could result in future projects no longer being economic. Please refer to "Forward-Looking Statements" for additional discussion of the assumptions and risk factors associated with the Projects and statements made in this press release.

About PowerBank Corporation

PowerBank Corporation is an independent renewable and clean energy project developer and owner focusing on distributed and community solar projects in Canada and the USA. The Company develops solar, Battery Energy Storage System (BESS) and EV Charging projects that sell electricity to utilities, commercial, industrial, municipal and residential off-takers. The Company maximizes returns via a diverse portfolio of projects across multiple leading North America markets including projects with utilities, host off-takers, community solar, and virtual net metering projects. The Company has a potential development pipeline of over one gigawatt and has developed renewable and clean energy projects with a combined capacity of over 100 megawatts built. To learn more about PowerBank, please visit www.PowerBankcorp.com.

FORWARD-LOOKING STATEMENTS

This news release contains forward-looking statements and forward-looking information ‎within the meaning of Canadian securities legislation (collectively, "forward-looking ‎statements") that relate to the Company's current expectations and views of future events. ‎Any statements that express, or involve discussions as to, expectations, beliefs, plans, ‎objectives, assumptions or future events or performance (often, but not always, through the ‎use of words or phrases such as "will likely result", "are expected to", "expects", "will ‎continue", "is anticipated", "anticipates", "believes", "estimated", "intends", "plans", "forecast", ‎‎"projection", "strategy", "objective" and "outlook") are not historical facts and may be ‎forward-looking statements and may involve estimates, assumptions and uncertainties ‎which could cause actual results or outcomes to differ materially from those expressed in ‎such forward-looking statements. In particular and without limitation, this news release ‎contains forward-looking statements pertaining to the Company's expectations regarding its industry trends and overall market growth; the Company's growth strategies the expected energy production from the solar power projects mentioned in this press release; the number of homes expected to be powered; the timeline for construction; the expected savings for local residents; expected revenues and benefits of the Project to the Company;  the receipt of permits and financing to be able to construct the Projects; the receipt of incentives for the Projects; and the size of the Company's development pipeline. No assurance ‎can be given that these expectations will prove to be correct and such forward-looking ‎statements included in this news release should not be unduly relied upon. These ‎statements speak only as of the date of this news release.‎

Forward-looking statements are based on certain assumptions and analyses made by the Company in light of the experience and perception of historical trends, current conditions and expected future developments and other factors it believes are appropriate, and are subject to risks and uncertainties. In making the forward looking statements included in this news release, the Company has made various material assumptions, including but not limited to: obtaining the necessary regulatory approvals; that regulatory requirements will be maintained; general business and economic conditions; the Company's ability to successfully execute its plans and intentions; the availability of financing on reasonable terms; the Company's ability to attract and retain skilled staff; market competition; the products and services offered by the Company's competitors; that the Company's current good relationships with its service providers and other third parties will be maintained; and government subsidies and funding for renewable energy will continue as currently contemplated. Although the Company believes that the assumptions underlying these statements are reasonable, they may prove to be incorrect, and the Company cannot assure that actual results will be consistent with these forward-looking statements. Given these risks, uncertainties and assumptions, investors should not place undue reliance on these forward-looking statements.

Whether actual results, performance or achievements will conform to the Company's expectations and predictions is subject to a number of known and unknown risks, uncertainties, assumptions and other factors, including those listed under "Forward-‎Looking Statements" and "Risk ‎Factors" in the Company's most recently completed Annual Information Form, and other public filings of the Company, which include: the Company may be adversely affected by volatile solar power market and industry conditions; the execution of the Company's growth strategy depends upon the continued availability of third-party financing arrangements; the Company's future success depends partly on its ability to expand the pipeline of its energy business in several key markets; governments may revise, reduce or eliminate incentives and policy support schemes for solar and battery storage power; general global economic conditions may have an adverse impact on our operating performance and results of operations; the Company's project development and construction activities may not be successful; developing and operating solar projects exposes the Company to various risks; the Company faces a number of risks involving Power Purchase Agreements ("PPAs") and project-level financing arrangements; any changes to the laws, regulations and policies that the Company is subject to may present technical, regulatory and economic barriers to the purchase and use of solar power; the markets in which the Company competes are highly competitive and evolving quickly; an anti-circumvention investigation could adversely affect the Company by potentially raising the prices of key supplies for the construction of solar power projects; foreign exchange rate fluctuations; a change in the Company's effective tax rate can have a significant adverse impact on its business; seasonal variations in demand linked to construction cycles and weather conditions may influence the Company's results of operations; the Company may be unable to generate sufficient cash flows or have access to external financing; the Company may incur substantial additional indebtedness in the future; the Company is subject to risks from supply chain issues; risks related to inflation and tariffs; unexpected warranty expenses that may not be adequately covered by the Company's insurance policies; if the Company is unable to attract and retain key personnel, it may not be able to compete effectively in the renewable energy market; there are a limited number of purchasers of utility-scale quantities of electricity; compliance with environmental laws and regulations can be expensive; corporate responsibility may adversely impose additional costs; the future impact of any global pandemic on the Company is unknown at this time; the Company has limited insurance coverage; the Company will be reliant on information technology systems and may be subject to damaging cyberattacks; the Company may become subject to litigation; there is no guarantee on how the Company will use its available funds; the Company will continue to sell securities for cash to fund operations, capital expansion, mergers and acquisitions that will dilute the current shareholders; and future dilution as a result of financings.

The Company undertakes no obligation to update or revise any ‎forward-looking statements, whether as a result of new information, future events or ‎otherwise, except as may be required by law. New factors emerge from time to time, and it ‎is not possible for the Company to predict all of them, or assess the impact of each such ‎factor or the extent to which any factor, or combination of factors, may cause results to ‎differ materially from those contained in any forward-looking statement. Any forward-‎looking statements contained in this news release are expressly qualified in their entirety by ‎this cautionary statement.‎

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/powerbanks-2-1-mw-phillips-rd-project-successfully-completes-major-interconnection-study-on-path-to-permitting-302650337.html

SOURCE PowerBank Corporation

FAQ

What is the size and expected output of PowerBank's Phillips Rd project (SUUN)?

The Phillips Rd project is a 2.1 MW solar farm estimated to power approximately 262 homes.

What compensation rate will SUUN's Phillips Rd project receive under New York VDER?

The project is expected to qualify for VDER with an estimated first-year average rate of US$0.0971/kWh.

Which incentives will PowerBank (SUUN) seek for the Phillips Rd community solar project?

The project is expected to qualify for NY-Sun incentives and federal Investment Tax Credits under the Inflation Reduction Act and the One Big Beautiful Bill Act of 2025.

What development milestones must SUUN clear before building Phillips Rd?

PowerBank must secure a community solar contract, obtain required permits, and finalize third-party financing before construction.

When will construction start for PowerBank's Phillips Rd project (SUUN)?

Construction will begin upon securing permits and financing; no specific start date was provided.

How does the Phillips Rd project fit into PowerBank's overall portfolio (SUUN)?

PowerBank reports over 100 MW completed and a development pipeline exceeding 1 GW, with Phillips Rd adding a 2.1 MW community solar asset.
PowerBank

NASDAQ:SUUN

SUUN Rankings

SUUN Latest News

SUUN Latest SEC Filings

SUUN Stock Data

71.08M
26.90M
26.49%
0.53%
1.6%
Utilities - Renewable
Utilities
Link
Canada
Toronto