Silvercorp Announces Project Update for El Domo
Rhea-AI Summary
Silvercorp (TSX/NYSE American: SVM) updated the El Domo construction budget to $284 million, a $44 million increase from the prior $240 million estimate, and set production for July 1, 2027 (six-month delay). Key drivers include a VAT rate increase to 15% (+$16M), higher process-plant equipment costs (+$15M), logistics and construction increases, lowered contingency to 8% ($17M), and $44.5M spent in 2025 (~16% of new budget).
The company awarded or expects major contracts for mining, processing engineering and powerline work, ordered long-lead equipment, and reports improved metallurgical recoveries from a revised flowsheet.
Positive
- Updated budget $283.6M reflecting current cost estimates
- Production target set for July 1, 2027 (six-month delay)
- Spent $44.5M in 2025, ≈16% of the new budget showing active progress
- Mining contract structure: $35M construction and ~$63M five-year operations
- New flowsheet yields +5.4% Cu and +6.2% Au recoveries
Negative
- Budget increase of $44M (≈18% vs prior $240.5M estimate)
- VAT rise to 15% adds $16M to capex (recoverable as tax credit later)
- Contingency reduced from 20% to 8% (owner contingency $17M), lowering buffer
- Project schedule delayed by 6 months to July 1, 2027
News Market Reaction – SVM
On the day this news was published, SVM declined 9.79%, reflecting a notable negative market reaction. Argus tracked a trough of -20.0% from its starting point during tracking. Our momentum scanner triggered 22 alerts that day, indicating elevated trading interest and price volatility. This price movement removed approximately $257M from the company's valuation, bringing the market cap to $2.37B at that time.
Data tracked by StockTitan Argus on the day of publication.
Key Figures
Market Reality Check
Peers on Argus
SVM gained 7.29% while key silver peers EXK, MAG, and AG fell between roughly -0.25% and -1.96%, with TGB down -9.02%. This divergence suggests the El Domo update drove a company-specific move rather than a sector-wide reaction.
Historical Context
| Date | Event | Sentiment | Move | Catalyst |
|---|---|---|---|---|
| Feb 02 | Technical report filing | Neutral | -0.6% | Filed NI 43-101 PEA for Condor gold project with technical details. |
| Jan 27 | Acquisition closing | Positive | +0.6% | Completed acquisition of Tulkubash/Kyzyltash projects via 70% JV structure. |
| Jan 20 | Acquisition agreement | Positive | +8.2% | Agreed to acquire 70% of Chaarat ZAAV, adding major gold projects. |
| Jan 15 | Operational update | Positive | +1.3% | Q3 operational results with revenue about $126.1M, up 51% YoY. |
| Dec 22 | PEA economics | Positive | -3.1% | Condor PEA showed strong after-tax NPV and IRR but shares fell. |
Growth and project-development news generally aligned with positive price reactions, while a robust PEA in Dec 2025 saw a negative reaction, showing occasional selloffs on strong technical updates.
Over the past few months, Silvercorp has focused on growth and project advancement. In Dec 2025, it reported a robust PEA for the Condor project with strong NPV and IRR figures, yet shares fell. In Jan 2026, Q3 operational results showed revenue up 51% year-over-year and the stock rose. The company then agreed to and completed a 70% interest acquisition in the Tulkubash/Kyzyltash gold projects, again with positive price responses. The latest El Domo budget and schedule update fits this sequence of capital-intensive project development across multiple jurisdictions.
Market Pulse Summary
The stock moved -9.8% in the session following this news. A negative reaction despite project advancement would fit past instances where technically strong studies, like the Condor PEA with robust NPV and IRR, coincided with share price weakness. With the stock at $10.62, still 24.14% below its 52-week high but well above its 200-day MA at $6.05, investors could reassess higher El Domo capex, reduced contingency, and schedule slippage, alongside existing capital commitments for other growth projects.
Key Terms
vat financial
sag mill technical
qa/qc technical
rom ore shed technical
ni 43-101 regulatory
AI-generated analysis. Not financial advice.
Trading Symbol: TSX/NYSE American: SVM
The construction budget for the Project has been updated to
- The VAT: rate has been revised from
10% ( ) to$19 million 15% ( ), resulting in a$35 million increase, which represents$16 million 36% of total budget growth. The Company expects to recover this VAT as a tax credit in the first year of operations once concentrate exports commence. - Package #1 Construction:
increase due to detailed design changes, construction of two rock buttress for waste dumps (SWD and WRF1) were added.$5.1 million - The equipment and material purchases of the process plant have increased by
due to:$15 million - Some equipment was previously missing in both the April 2025 and 2021 Feasibility Studies, e.g. water recycling system from Tailing Storage Facility ("TSF"), SAG mill, regrind mill, bigger flotation cells and thickeners required to accommodate an increase in sulfur content from
9% (2021 Feasibility Study design) to25% (current design) (~ ).$11 million - Logistics costs increased by
(considering$4 million 15% of all equipment for sea freight, customs fees, storage, local transport, insurance, plus ~3.5% import tax), which was previously underestimated.
- Some equipment was previously missing in both the April 2025 and 2021 Feasibility Studies, e.g. water recycling system from Tailing Storage Facility ("TSF"), SAG mill, regrind mill, bigger flotation cells and thickeners required to accommodate an increase in sulfur content from
- The estimated construction and installation of the process plant have increased by
based on the actual construction quotes for the 5000-square-metre ROM ore shack currently under construction.$7.2 million - Bypass roads and access roads:
increase mainly due to the upgrade of the new southern access road, so that 40-foot container trucks can pass.$3.3 million - External powerline: added
for payment on behalf of the Ecuador National Power Company (CNEL)for third-party supervision and land easements.$2.3 million - Missing items such as Engineer of Record ("EoR"), and construction quality assurance and control ("QA/QC") supervision for TSF construction, site internal power distribution facilities, environment rehabilitation and protection, 4G network added another
.$10.1 million - Added
in local purchases to support local supply chains and economy.$6.6 million - Owner's Cost has increased from
to$30 million , based on the monthly burn rate and additional expenses (e.g. insurance, services, community and institutional relationship, and security) plus a six-month extension for the construction period-~$32.5 million $2.5 million increase. - Package #2 Mining and Stripping: estimated cost has decreased by
based on the winning bidder's unit prices.$4.2 million - Achieved savings of
across various other projects.$4.7 million - Contingency has been reduced from
20% ( ) to$32 million 8% ( ), a reduction of$17 million , reflecting more accurate estimates for the current budget. The contingency may account for the diesel price increase during construction (~$15 million 10% to ~15% increase in unit costs for civil works), and inherent uncertainties as engineering design work continues.
Capital Cost Estimate Details:
The table below summarizes the schedule and costs to construct the Project:
2025 April |
New Budget | |||||
Spent in 2025 | 2026 | July 1st, 2027 | Total Budget | |||
($ Million) | ($ Million) | ($ Million) | ($ Million) | ($ Million) | ||
1 | Package #1 - Site preparation /Road s/Channels / TSF/SWD | 47.5 | 22.4 | 32.5 | 2.5 | 57.4 |
2 | Package #2 - Open Pit Mining and Stripping | 39.0 | 0.0 | 23.4 | 11.3 | 35.0 |
3 | Package #3 - Processing Plant Construction and Equipment | 33.0 | 3.5 | 41.5 | 9.8 | 54.8 |
4 | Temporary and Permanent Camps | 7.0 | 1.9 | 4.7 | 0.4 | 7.0 |
Packages #4,5 -Site Infrastructure (bypass roads, powerline, standby diesel generators, water treatment plant) | 33.0 | 3.7 | 36.1 | 5.6 | 45.4 | |
Direct costs sub-total | 159.4 | 31.5 | 138.2 | 29.6 | 199.3 | |
6 | Owner's Contingency | 31.9 | 0.0 | 14.2 | 2.8 | 17.0 |
7 | Owner's Cost | 30.0 | 9.8 | 12.5 | 9.8 | 32.1 |
8 | Value added tax (VAT) | 19.1 | 3.1 | 27.1 | 5.0 | 35.2 |
Total | 240.5 | 44.5 | 191.9 | 47.2 | 283.6 | |
Based on this new budget, the El Domo Project is scheduled to be in production by July 1st, 2027, representing a six-month delay from the previous estimate of early-2027.
Progress Achieved in 2025:
2025 has been a productive year, as we focused on construction Package #1: including Site preparation, Roads, Non-contact
Water Channels, TSF, Saprolite Waste Dump ("SWD"), and proceeded with other packages. During the year, we established a new project construction team, while overcoming an exceptionally heavy and long rainy season that lasted well into June, working with different communities and government agencies to ensure a sound working environment. Through the hard work of our local team, CRCC 14 and other contractors, along with the support of communities and government authorities, the Company made significant progress at the Project.
- Spent
in 2025, representing approximately$44.5 million 16% of the total new budget. - Successfully cleared 1,040 of the total 1,109 archaeological units, completing archaeological clearance in full compliance with permit conditions to start earth-moving activities.
- Over 2.6 million cubic metres of material were moved (including topsoil, saprolite and andesite material) for site preparation of Process plant, roads, TSF, SWD, and other site preparation.
- Built 8.1 km of internal haul roads, providing comprehensive access across the site, and upgraded and repaired 23.1 km of external roads, allowing 40-feet haul truck access. Additionally, 2.1 km of non-contact water channels were excavated as part of a robust water management system.
- Completed and commissioned the Construction Camp with a capacity of over 600 beds.
- Blasted at an on-site quarry and from Process plant Site Preparation to generate fresh non-acid generating rock for roads and the construction of the starter dam of the TSF, plus laid the foundation for a 5000 square metre ROM Ore Shed, which will serve as a warehouse initially during the construction period.
- Yantai Jinpeng Mining Machinery Co.,Ltd has finalized the detailed process flowsheet, equipment selection and cost estimates for the processing plant construction and equipment. The improved process flowsheet introduced a standalone sequential flotation of copper-gold into copper concentrates first; all other parts of the flowsheet follow the previous design. The new metallurgical recovery test results for the sequential flotation of copper-gold into copper concentrates first show a
5.4% increase in copper recovery and a6.2% increase in gold recovery, enhancing the Project's projected economics. - Ordered most of the long-lead time major equipment for the process plant and Diesel Power Generator Sets providing backup power for the entire site; paid a down payment of
towards a total contract price of$7.2 million .$16.9 million - Continuously engaged with different communities and stakeholders for support.
- Built an effective, integrated construction team, collaborating among team members at the El Domo construction site,
Quito ,Vancouver andBeijing . - Strong and improving safety culture and management at site, with more than 960,000 hours worked with no major incidents.
- Implemented and complied with the Environmental Management Plan during construction activities.
Bidding for the Package #2 - Open Pit Mining and Stripping
After a competitive bidding process and several months of negotiation, the Company is expected to execute the mining contract for the construction and operation of the Project with China Railway 19th Bureau Group Co., Ltd. ("CRCC 19") on a "Unit Cost" basis, that is, the cost of drilling, blasting, hauling and dumping or compacting each cubic metre of rock over a certain distance. The fixed unit rate contract is structured into two primary phases: 1) the Construction Phase, valued at
Package #3 - Processing plant construction and equipment
Yantai Jinpeng Mining Machinery Co.,Ltd is expected to complete the detailed engineering design of the processing plant based on the new flowsheet by early April 2026. This will serve as the cost base to initiate the bidding process for construction. With most equipment already ordered, the primary budget variables for Package #3 would be the construction cost and materials
Packages #4 - External Powerline and standby diesel generators
The total distance of the external powerline is 61.3 km. The northern section (27.5 km) and three substations, with a
Qualified Person
Guoliang Ma, P. Geo., Manager of Exploration and Resource of the Company, is the Qualified Person for Silvercorp for the purposes of National Instrument 43-101 – Standards of Disclosure for Mineral Projects (''NI 43-101'') and has reviewed and approved the technical information contained in this news release.
About Silvercorp
Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company's strategy is to create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.
For further information
Silvercorp Metals Inc.
Lon Shaver
President
Phone: (604) 669-9397
Toll Free 1(888) 224-1881
Email: investor@silvercorp.ca
Website: www.silvercorpmetals.com
CAUTIONARY DISCLAIMER - FORWARD-LOOKING STATEMENTS
This news release includes "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and "forward-looking information" within the meaning of applicable securities laws relating to, among other things statements regarding the recovery of the VAT as a tax credit, the construction schedule, duration, and costs for the development of the Project, date which the Project is scheduled to be in production; timing of execution of mining contract and mobilization of personnel and equipment to the Project, timing of completion of detailed engineering design, delivery of diesel generators, and completion of powerline. By their very nature, forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Forward-looking information may in some cases be identified by words such as "will", "anticipates", "expects", "intends" and similar expressions suggesting future events or future performance.
We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including fluctuating commodity prices; recent market events and condition; activities of anti-mining groups; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in
A comprehensive discussion of other risks that impact Silvercorp can also be found in their public reports and filings which are available under its profile at www.sedarplus.ca.
View original content to download multimedia:https://www.prnewswire.com/news-releases/silvercorp-announces-project-update-for-el-domo-302679520.html
SOURCE Silvercorp Metals Inc.
FAQ
What is the new El Domo construction budget for Silvercorp (SVM) as of February 4, 2026?
When does Silvercorp (SVM) now expect El Domo to reach production and how much was the delay?
How much did Silvercorp (SVM) spend on El Domo in 2025 and what percent of the budget does that represent?
What major contracts and equipment orders has Silvercorp (SVM) secured for El Domo?
How did the VAT and contingency changes affect El Domo's capital estimate for Silvercorp (SVM)?
