STOCK TITAN

TriStar Gold Updates Economics of PFS with After-Tax 40% IRR and US$603 Million NPV5 and Provides Update on Permit

Rhea-AI Impact
(Moderate)
Rhea-AI Sentiment
(Neutral)
Tags
TriStar Gold has updated the Prefeasibility Study (PFS) for its Castelo de Sonhos gold project in Brazil, revealing robust economics. At a base-case gold price of $2,200/oz, the project shows an after-tax NPV5% of $603 million and an IRR of 40%. The project requires initial capital of $296 million and features AISC of $1,111/oz with a 2-year payback period. The operation plans for a 10,000 tpd processing facility with expected 98% gold recovery. The project maintains its mineral reserves of 1.4 Moz gold at 1.1 g/t. Additionally, TriStar received positive legal opinion regarding the project's permits, confirming they remain valid despite previous inquiries about potential impacts on Indigenous lands.

TriStar Gold ha aggiornato lo Studio di Prefattibilità (PFS) per il suo progetto aurifero Castelo de Sonhos in Brasile, evidenziando solidi dati economici. Con un prezzo base dell'oro di 2.200 $/oz, il progetto presenta un VAN post-tasse al 5% di 603 milioni di dollari e un TIR del 40%. L'investimento iniziale richiesto è di 296 milioni di dollari e i costi all-in-sustaining (AISC) ammontano a 1.111 $/oz, con un periodo di recupero di 2 anni. L'impianto di lavorazione previsto ha una capacità di 10.000 tpd e un recupero aurifero stimato del 98%. Le riserve minerarie si mantengono a 1,4 Moz di oro con una concentrazione di 1,1 g/t. Inoltre, TriStar ha ricevuto un parere legale favorevole riguardo ai permessi del progetto, confermando la loro validità nonostante le precedenti indagini sugli impatti potenziali sulle terre indigene.
TriStar Gold ha actualizado el Estudio de Prefactibilidad (PFS) para su proyecto de oro Castelo de Sonhos en Brasil, mostrando una sólida economía. Con un precio base del oro de $2,200/oz, el proyecto presenta un VAN después de impuestos al 5% de $603 millones y una TIR del 40%. El proyecto requiere un capital inicial de $296 millones y cuenta con un AISC de $1,111/oz, con un periodo de recuperación de 2 años. La operación planea una planta de procesamiento de 10,000 tpd con una recuperación de oro esperada del 98%. El proyecto mantiene sus reservas minerales de 1.4 Moz de oro con una ley de 1.1 g/t. Además, TriStar recibió una opinión legal positiva sobre los permisos del proyecto, confirmando que siguen siendo válidos a pesar de las consultas previas sobre posibles impactos en tierras indígenas.
TriStar Gold는 브라질에 위치한 Castelo de Sonhos 금 프로젝트에 대한 예비 타당성 조사(PFS)를 업데이트하여 견고한 경제성을 공개했습니다. 기본 금 가격을 온스당 $2,200로 설정했을 때, 이 프로젝트는 세후 할인율 5% 기준 순현재가치(NPV)가 6억 3백만 달러이며 내부수익률(IRR)은 40%입니다. 초기 자본금은 2억 9,600만 달러가 필요하며, 전체 지속 비용(AISC)은 온스당 $1,111이고 투자 회수 기간은 2년입니다. 이 사업은 일일 처리량 10,000톤(tpd) 규모의 가공 시설을 계획하고 있으며, 예상 금 회수율은 98%입니다. 프로젝트는 1.4백만 온스(Moz) 금 매장량1.1 g/t의 등급을 유지하고 있습니다. 또한 TriStar는 프로젝트 허가에 대해 긍정적인 법률 의견을 받았으며, 이전에 원주민 토지에 대한 잠재적 영향 조사에도 불구하고 허가가 유효함을 확인했습니다.
TriStar Gold a mis à jour l'étude de préfaisabilité (PFS) pour son projet aurifère Castelo de Sonhos au Brésil, révélant une solide rentabilité. À un prix de l'or de base de 2 200 $/oz, le projet affiche une VAN après impôts à 5 % de 603 millions de dollars et un TRI de 40 %. Le projet nécessite un investissement initial de 296 millions de dollars et présente un coût tout compris (AISC) de 1 111 $/oz avec une période de récupération de 2 ans. L'exploitation prévoit une installation de traitement de 10 000 tpd avec un taux de récupération de l'or attendu de 98 %. Les réserves minérales du projet se maintiennent à 1,4 Moz d'or avec une teneur de 1,1 g/t. De plus, TriStar a reçu un avis juridique favorable concernant les permis du projet, confirmant leur validité malgré les enquêtes précédentes sur les impacts potentiels sur les terres indigènes.
TriStar Gold hat die Vorstudie (PFS) für sein Goldprojekt Castelo de Sonhos in Brasilien aktualisiert und dabei robuste wirtschaftliche Kennzahlen offengelegt. Bei einem Basis-Goldpreis von 2.200 $/oz weist das Projekt einen nach Steuern berechneten Kapitalwert (NPV) mit 5% Diskontsatz von 603 Millionen Dollar und eine interne Rendite (IRR) von 40% auf. Das Projekt erfordert eine anfängliche Investition von 296 Millionen Dollar und weist All-in Sustaining Costs (AISC) von 1.111 $/oz bei einer Amortisationszeit von 2 Jahren auf. Geplant ist eine Aufbereitungsanlage mit einer Kapazität von 10.000 Tonnen pro Tag (tpd) und einer erwarteten Goldrückgewinnung von 98%. Die Mineralreserven bleiben bei 1,4 Mio. Unzen Gold mit einem Gehalt von 1,1 g/t. Zudem erhielt TriStar eine positive rechtliche Stellungnahme zu den Projektgenehmigungen, die trotz vorheriger Prüfungen möglicher Auswirkungen auf indigene Gebiete weiterhin gültig sind.
Positive
  • Strong economics with 40% IRR and $603M NPV5 at $2,200 gold price
  • High gold recovery rate of 98%
  • Short payback period of 2 years
  • Permits remain valid and in good standing
  • Legal opinion confirms no interference with Indigenous lands
  • Significant gold price leverage with NPV5 increasing to $1,353M at $3,200 gold
Negative
  • High initial capital requirement of $296M, up from $261M in 2021 PFS
  • Increased AISC to $1,111/oz from $900/oz in 2021 PFS
  • High strip ratio of 9:1 (waste:ore)
  • After-tax NPV5% of US$1,353 million at approx. spot of US$3,200 gold price
  • After-tax NPV5% of US$603 million at US$2,200 base-case gold price
  • A compelling after-tax IRR of 72% at US$3,200 gold and 40% at US$2,200 base case gold price
  • AISC of US$1,111/oz
  • After-tax payback period of 2 years
  • The Company has received a positive legal opinion on status of the Castelo de Sonhos Permit, which remains valid and in good standing

Scottsdale, Arizona--(Newsfile Corp. - May 5, 2025) - TriStar Gold Inc. (TSXV: TSG) (OTCQB: TSGZF) ("TriStar" or the "Company), is pleased to announce a prefeasibility study ("Study") update for the Company's Castelo de Sonhos gold project in southern Pará State, Brazil by GE21 Consultoria Mineral Ltda ("GE21") of Belo Horizonte, Brazil. There was no change to the mineral resources or reserves, the focus of the update study was the cost estimate since the release of the previous PFS, as well as to incorporate changes to the gold price and exchange rates.

Nick Appleyard, TriStar's President and CEO, stated: "The updated Study is a key step in our advancement of Castelo de Sonhos, demonstrating gold price leverage and robust economics at a time of record high gold prices and a scarcity of permitted development assets."

Mr. Appleyard continued, "Tristar's Castelo de Sonhos can fill a gap in the gold development space, with the potential to create value for all stakeholders. We look forward to advancing this project to a construction decision."

The results of the Study now replace the 2021 prefeasibility study ("PFS"), originally announced in the Company's press release dated October 5, 2021. The Study has incorporated a new cost estimate for the planned development of Castelo de Sonhos compared with the 2021 original.

Table 1 below presents a side-by-side comparison of the key metrics of the latest Study and 2021 PFS.

Castelo de Sonhos Metric2025 PFS Study Update2021 Prefeasibility
Initial Capital (US$ million)$296$261
Base-Case Gold Price (US$/oz) $2,200$1,550
AISC (US$/oz)$1,111$900
Exchange Rate (1 US$: BRL)5.755.0
After-Tax NPV 5% (US$ million)$603$321
Base Case After-Tax IRR (%)40%28%

 

Table 1. Key Metrics Comparison.

The Prefeasibility Study Update
The prefeasibility study update of economic parameters was conducted by GE21 Consultoria Mineral Ltda ("GE21") of Belo Horizonte, Brazil, who are independent of TriStar.

Key parameters of the Study include:

  • Review and update all project operating costs.
  • Review and update all project capital costs.
  • Economic analyses were carried out based on the resources and reserves that are still considered current.
  • Update economics with a base case long-term gold price of US$2,200/oz and a foreign exchange rate of US$1 = BRL5.75. The economics include the effect of the project royalties, including NSR royalties totaling 3.5% and Brazilian federal gross royalty of 1.5%.

Project Description
The Castelo de Sonhos operation will include an open pit gold mine and processing facilities with a nominal milling rate of 10,000 tpd (3.6Mtpa). Power will be supplied by a 26 km, 138 kV transmission line from a substation adjacent to Highway 163 near the town of Castelo de Sonhos. At closure, all buildings will be removed, disturbed lands rehabilitated, and the property returned to otherwise functional use according to future approved reclamation plans and accepted practices at the time of closure. The Study incorporates all costs associated with undertaking these measures and is reflected in the project economics.

Mining will be based on conventional open pit methods (drill-blast-load-haul), which are suited to the Project location, orebody and local site conditions.

The process flowsheet remains unchanged with whole-ore agitation leaching as the preferred process flowsheet for project development. The plant will be designed to treat 10,000 tpd through crushing, grinding, hybrid cyanidation and carbon in leach, carbon acid wash, pressure stripping, and thermal regeneration. Electrowinning sludge will be dried and smelted to produce doré bars for shipment to third party refiners. Based on the test work conducted this flowsheet is anticipated to result in a metallurgical recovery of 98% of the gold delivered to the plant.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4509/250756_tristarfigure1_550.jpg

Figure 1. Castelo de Sonhos Project Prefeasibility Proposed Layout.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4509/250756_tristarfigure1.jpg

Economic Results
The results of the Study are shown below in Table 2. A base case gold price of US$2,200 has been used and a fixed exchange ratio of BRL5.75 (5.75 Brazilian Reals) to US$1.

ParameterUnitPre-taxPost-tax
Cash flowUS$ millions1,123934
IRR%4640
NPV 5%US$ millions736603
NPV 10%US$ millions491393
Cash CostUS$/oz1,080
AISCUS$/oz1,111
Initial CapitalUS$ millions296
Life of mine productionMoz gold1.33
Average annual productionoz gold121,000
Payback period (Mine life)Years2.0

 

Table 2. Summary of Economic Results of the Study.

Notes: Estimated All In Sustaining Costs per ounce of gold produced is a Non-GAAP measure that is equal the total of site mining costs, site and corporate G&A costs, royalties and production taxes, realized gains/losses on hedging transactions, community and permitting costs relating to current operations, refining costs, site based non-cash remuneration, inventory write-downs, stripping costs, byproduct credits, reclamation costs, and sustaining costs related to exploration and studies, capital exploration, capitalized stripping and underground mine development, and capital expenditures, divided by the estimated total ounces of gold produced during the life of the mine.

Economic Sensitivities

The figures and tables below show the sensitivity of after-tax NPV and IRR to changes in the US dollar gold price.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4509/250756_tristarfigure2_550.jpg

Figure 2. Sensitivity of after-tax NPV10% (Millions) to gold price, base case highlighted in blue.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4509/250756_tristarfigure2.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4509/250756_tristarfigure3_550.jpg

Figure 3. Sensitivity of after-tax IRR% to gold price, base case highlighted in blue. 

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/4509/250756_tristarfigure3.jpg

Capital Cost Estimate

The Study outlines an initial capital cost estimate of US$296 million, including a 20% contingency.

Table 3 below summarizes the initial capital cost estimate for the Project.

DESCRIPTIONUS$ MILLIONS
Mine
37.3
Power transmission line
10.8
Plant
187.2
Tailings storage facility
11.2
Contingency (20%)
49.3
Total
295.8

 

Table 3. Summary of major components of initial capital estimate.

Operating Costs

Operating costs by phase for the LOM are provided in Table 4 below.

ParameterUnit
Process ratet/day10,000
Average head gradeg/t1.1
Phase 1 head gradeg/t1.3
Phase 2 head gradeg/t0.8
Gold Recovery%98
Mine operating cost (owner operator)US$/t moved2.01
Process operating cost US$/t processed11.10
G&AUS$/ processed1.70
LOM strip ratioWaste t : process t9 : 1

 

Table 4. Life of mine summary of operating parameters and costs.

Mineral Resource Estimate
This mineral resource estimate remains unchanged as per the Company press release dated Oct 5, 2021 "TriStar Gold Announces Positive PFS with 1.4 Moz Gold Reserves and pre-tax 33% IRR and $400 million NPV."

Results are shown in Table 5 below.

RegionClassificationTonnage
(Mt)
Grade
(g/t Au)
Metal Content
(Moz Au)
Esperança SouthIndicated29.01.31.2
Inferred10.01.20.4
Esperança EastIndicated5.00.80.1
Inferred12.80.70.3
Esperança CenterIndicated19.10.70.4
Inferred3.30.90.1
Project TotalIndicated53.11.01.8
Inferred26.00.90.7

 

Table 5. Mineral resource estimate1 for the Castelo de Sonhos gold project (with an effective date of October 4, 2021) above a reporting cutoff grade of 0.26 g/t Au.

1Project totals may appear not to sum correctly since all numbers have been rounded to reflect the precision of Inferred and Indicated mineral resource estimates.
2These are mineral resources and not reserves and as such do not have demonstrated economic viability.
3The metal content estimates reflect gold in situ, and do not include factors such as external dilution, mining losses and process recovery losses.
4TriStar is not aware of any environmental, permitting, legal, title, taxation, socio-economic, marketing or political factors that might materially affect these mineral resource estimates.

Mineral Reserve Estimate
The Mineral Reserves, which also remain unchanged, for Castelo de Sonhos are a subset of the Indicated Mineral Resources as shown in Table 5 above. Probable Mineral Reserves are modified from Indicated Mineral Resources and are summarized in Table 6. Inferred Mineral Resources are set to waste. This mineral reserve estimate remains unchanged as per the Company press release dated Oct 5, 2021 "TriStar Gold Announces Positive PFS with 1.4 Moz Gold Reserves and pre-tax 33% IRR and $400 million NPV."

RegionClassificationTonnage
(Mt)
Grade
(g/t Au)
Metal Content
(Moz Au)
Esperança SouthProbable24.21.280.99
Esperança EastProbable3.10.820.08
Esperança CenterProbable11.40.780.29
Project TotalProbable38.71.11.4

 

Table 6. The Mineral Reserve estimates were prepared by Guilherme Gomides Ferreira, P.Eng., a GE21, and have an effective date of October 4, 2021.
Mineral Reserves are reported using the 2014 CIM Definition Standards and are estimated in accordance with the 2019 CIM Best Practices Guidelines. Mineral Reserves are based on the PFS LOM plan.
Mineral Reserves are mined tonnes and grade; and includes consideration for modifying factors such as loss and dilution.
Mineral Reserves are reported at a cut-off of 0.26 g/t gold.
Numbers have been rounded as required by reporting guidelines. There are no other known factors or issues that materially affect the Mineral Reserve estimate other than which is disclosed above, and normal risks faced by mining projects in the jurisdiction in terms of environmental, permitting, taxation, socio-economic, marketing, and political factors and additional risk factors as listed in the "Cautionary Note Regarding Forward-Looking Information" section below.

Legal Opinion on Requests Related to Castelo de Sonhos
TriStar is also pleased to provide the results of an independent legal opinion on the civil inquiry started by a Federal Public Prosecutor (MPF) to government regulators to investigate the potential impacts of the Company's Castelo de Sonhos gold project on Indigenous lands; please see TriStar press release from October 1, 2024 for details. The Company also notes that the permit remains valid and in good standing, according to SEMAS, the main regulatory permitting authority in Para State.

TriStar's independent legal advice suggests that the Company has demonstrated that the Castelo de Sonhos project does not have the potential to interfere with Indigenous lands named in the Prosecutor's case. The legal opinion also notes that it does not see the preparation of an Indigenous Component Study and/or the completion of a Free, Prior, and Informed Consultation as justified; both items were recommended by the MPF.

Legal counsel also noted that the EIA for Castelo de Sonhos is complete, robust and adequate. The opinion highlights the solid technical and legal defenses presented by TriStar following the MPF's recommendation. The Lawyers also note the non-binding nature of the MPF recommendations and the non-acceptance by SEMAS, TriStar's principal regulator, of these recommendations. SEMAS as well as environmental authority SEMMA have provided responses criticizing the MPF's position. Based on the legal opinion, evidence does not support the concerns raised by the MPF as there is no impact, direct or indirect, not even holistic or cosmological, on the ways of life and customs of the indigenous peoples.

Qualified Person

Porfirio Cabaleiro Rodriguez (FAIG #3708), Director of GE21, is the Qualified Person, as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects, for the Preliminary Feasibility Study presented in this press release, is independent of the Company and has approved the technical disclosure in this press release.

About TriStar

TriStar Gold is an exploration and development company focused on precious metals properties in the Americas that have the potential to become significant producing mines. The Company's current flagship property is the Castelo de Sonhos gold project in Pará State, Brazil. TriStar has completed a pre-feasibility study and is now working to advance the project towards a feasibility study while evaluating optimization options. The Company's shares trade on the TSX Venture Exchange under the symbol TSG and on the OTCQB under the symbol TSGZF. Further information is available at www.tristargold.com.

On behalf of the board of directors of the Company:

Nick Appleyard
President and CEO

For further information, please contact:

TriStar Gold Inc.
Nick Appleyard
President and CEO
480-794-1244
info@tristargold.com

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.

Forward-Looking Statements

Certain statements contained in this press release may constitute forward-looking statements under Canadian securities legislation which are not historical facts and are made pursuant to the "safe harbour" provisions under the United States Private Securities Litigation Reform Act of 1995. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "expects" or "it is expected", or variations of such words and phrases or statements that certain actions, events or results "will" occur. Forward-looking statements in this press release include all estimates from the Study such as the cash flow, IRR, NPVs, cash cost, AISC, initial capital, life of mine production, average annual production and payback period time. Such forward-looking statements are based upon the Company's reasonable expectations and business plan at the date hereof, which are subject to change depending on economic, political and competitive circumstances and contingencies. Readers are cautioned that such forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause a change in such assumptions and the actual outcomes and estimates to be materially different from those estimated or anticipated future results, achievements or position expressed or implied by those forward-looking statements. Risks, uncertainties and other factors that could cause the Company's plans to change include changes in demand for and price of gold and other commodities (such as fuel and electricity) and currencies; changes or disruptions in the securities markets; legislative, political or economic developments in Brazil; the need to obtain permits and comply with laws and regulations and other regulatory requirements; the possibility that actual results of work may differ from projections/expectations or may not realize the perceived potential of the Company's projects; risks of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in development programs; operating or technical difficulties in connection with exploration, mining or development activities; the speculative nature of gold exploration and development, including the risks of diminishing quantities of grades of reserves and resources; and the risks involved in the exploration, development and mining business. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable securities laws.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/250756

FAQ

What is the new NPV and IRR for TriStar Gold's (TSGZF) Castelo de Sonhos project?

The updated PFS shows an after-tax NPV5% of $603 million and IRR of 40% at a base-case gold price of $2,200/oz.

How much initial capital is required for the Castelo de Sonhos gold project?

The initial capital requirement is $296 million, including a 20% contingency.

What is the expected gold production and recovery rate at Castelo de Sonhos?

The project expects average annual production of 121,000 oz gold with a 98% gold recovery rate from a 10,000 tpd processing facility.

What are the current mineral reserves for TriStar Gold's Castelo de Sonhos?

The project has probable mineral reserves of 38.7 Mt at 1.1 g/t gold, containing 1.4 Moz of gold.

What is the status of TriStar Gold's permits for the Castelo de Sonhos project?

The permits remain valid and in good standing, with legal opinion confirming no interference with Indigenous lands.
Tristar Gold

OTC:TSGZF

TSGZF Rankings

TSGZF Latest News

TSGZF Stock Data

42.57M
235.22M
18.15%
18.63%
Gold
Basic Materials
Link
United States
Scottsdale