Talisker Initiates Milling at Nicola’s Craigmont Mill
Talisker Resources (OTCQX:TSKFF) has initiated milling operations at Nicola Mining's Craigmont Mill in Merritt, British Columbia. The company has transported 3,100 tonnes of material from its Mustang Mine for processing, following Nicola's successful completion of the gravity circuit installation in June.
The company is actively developing multiple levels (1060, 1075, 1105, and 1120) with in-vein development on the BK vein and BK9870 veins. Long-hole drilling is in progress for the first stope extraction from the Alhambra vein, with blasting expected later this week.
Talisker Resources (OTCQX:TSKFF) ha avviato le operazioni di macinazione presso il Craigmont Mill di Nicola Mining a Merritt, British Columbia. L'azienda ha trasportato 3.100 tonnellate di materiale dalla sua miniera Mustang per la lavorazione, a seguito del completamento con successo dell'installazione del circuito di gravità da parte di Nicola a giugno.
La società sta sviluppando attivamente più livelli (1060, 1075, 1105 e 1120) con sviluppo in vena sui filoni BK e BK9870. È in corso la perforazione a lunga distanza per la prima estrazione della stope dal filone Alhambra, con esplosioni previste per la fine di questa settimana.
Talisker Resources (OTCQX:TSKFF) ha iniciado operaciones de molienda en el Craigmont Mill de Nicola Mining en Merritt, Columbia Británica. La compañía ha transportado 3,100 toneladas de material desde su mina Mustang para su procesamiento, tras la exitosa finalización de la instalación del circuito de gravedad por parte de Nicola en junio.
La empresa está desarrollando activamente varios niveles (1060, 1075, 1105 y 1120) con desarrollo en veta en las vetas BK y BK9870. Se está realizando perforación de largo alcance para la primera extracción de la cámara en la veta Alhambra, con voladuras previstas para finales de esta semana.
Talisker Resources (OTCQX:TSKFF)는 브리티시컬럼비아 주 메릿에 위치한 Nicola Mining의 Craigmont Mill에서 제분 작업을 시작했습니다. 회사는 Nicola가 6월에 중력 회로 설치를 성공적으로 완료한 후 Mustang 광산에서 3,100톤의 물질을 운송하여 가공하고 있습니다.
회사는 BK 정맥과 BK9870 정맥에서 정맥 내 개발과 함께 여러 층(1060, 1075, 1105, 1120)을 적극적으로 개발 중입니다. Alhambra 정맥에서 첫 스톱 추출을 위한 장공 천공이 진행 중이며, 이번 주 후반에 발파가 예정되어 있습니다.
Talisker Resources (OTCQX:TSKFF) a lancé les opérations de broyage à l'usine Craigmont de Nicola Mining à Merritt, en Colombie-Britannique. L'entreprise a transporté 3 100 tonnes de matériaux depuis sa mine Mustang pour le traitement, suite à l'achèvement réussi de l'installation du circuit de gravité par Nicola en juin.
L'entreprise développe activement plusieurs niveaux (1060, 1075, 1105 et 1120) avec un développement en veine sur les veines BK et BK9870. Un forage à longue distance est en cours pour la première extraction de la stope de la veine Alhambra, avec des tirs prévus plus tard cette semaine.
Talisker Resources (OTCQX:TSKFF) hat die Mahlbetriebe in der Craigmont-Mühle von Nicola Mining in Merritt, British Columbia, aufgenommen. Das Unternehmen hat 3.100 Tonnen Material aus seiner Mustang-Mine zum Aufbereitungsprozess transportiert, nachdem Nicola im Juni die Installation des Schwerkraftkreislaufs erfolgreich abgeschlossen hatte.
Das Unternehmen entwickelt aktiv mehrere Ebenen (1060, 1075, 1105 und 1120) mit Stollenentwicklung an den BK- und BK9870-Erzgängen. Die Langlochbohrungen für die erste Strossenentnahme aus dem Alhambra-Erzgänge sind im Gange, Sprengungen werden für Ende dieser Woche erwartet.
- Successful commencement of milling operations at Nicola's Craigmont Mill
- 3,100 tonnes of material already transported for processing
- Multiple active development fronts across different mine levels
- First production stope blasting imminent
- None.
TORONTO, July 07, 2025 (GLOBE NEWSWIRE) -- Talisker Resources Ltd. (“Talisker” or the “Company”) (TSX: TSK, OTCQX: TSKFF) is pleased to announce that the Company has commenced milling and processing of run of mine material from Talisker’s Mustang Mine (“Mustang”) at Nicola Mining Company’s (“Nicola”) Craigmont Mill (“Craigmont”) located in Merritt, British Columbia. Nicola successfully completed the installation of the gravity circuit as planned in June and following comprehensive process testing commenced milling Talisker’s material late last week.
To date, a total of 3,100 tonnes of material has been transported from Mustang to Craigmont for processing. Talisker continues to develop on the 1060, 1075, 1105 and 1120 levels with in-vein development active on the BK vein on the 1075 level and both the BK and BK9870 veins on the 1105 level. Long-hole drilling in preparation for the mining and extraction of the first stope is underway targeting the 3264 stope from the Alhambra vein located between the 1060 and 1075 levels. Blasting and extraction of the first stope is expected to occur later this week.
Terry Harbort, CEO of Talisker stated, “We are excited to be processing our first run of mine material with our milling partner Nicola, a major milestone for the Company. In addition, the advance of simultaneous development on the Alhambra, BK and BK9870 veins provides Talisker various working fronts on multiple levels. We eagerly look forward to the blasting of our first production stope this week.”
For further information, please contact:
Terry Harbort
President and CEO
terry.harbort@taliskerresources.com
+1 416 357 0227
About Talisker Resources Ltd.
Talisker (taliskerresources.com) is a junior resource company involved in the exploration and development of gold projects in British Columbia, Canada. Talisker’s flagship asset is the high-grade, fully permitted Bralorne Gold Project where the Company is currently transitioning into underground production at the Mustang Mine. Talisker projects also include the Ladner Gold Project, an advanced stage project with significant exploration potential from an historical high-grade producing gold mine and the Spences Bridge Project where the Company holds ~
Caution Regarding Forward Looking Statements
Certain statements contained in this press release constitute forward-looking information. These statements relate to future events or future performance. The use of any of the words “could”, “intend”, “expect”, “believe”, “will”, “projected”, “estimated” and similar expressions and statements relating to matters that are not historical facts are intended to identify forward-looking information and are based on Talisker’s current belief or assumptions as to the outcome and timing of such future events. Various assumptions or factors are typically applied in drawing conclusions or making the forecasts or projections set out in forward-looking information. Those assumptions and factors are based on information currently available to Talisker. Although such statements are based on reasonable assumptions of Talisker’s management, there can be no assurance that any conclusions or forecasts will prove to be accurate.
Forward looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such factors include risks inherent in the exploration and development of mineral deposits, including risks relating to changes in project parameters as plans continue to be redefined, risks relating to variations in grade or recovery rates, risks relating to changes in mineral prices and the worldwide demand for and supply of minerals, risks related to increased competition and current global financial conditions, access and supply risks, reliance on key personnel, operational risks regulatory risks, including risks relating to the acquisition of the necessary licenses and permits, financing, capitalization and liquidity risks, title and environmental risks and risks relating to the failure to receive all requisite shareholder and regulatory approvals.
The forward-looking information contained in this release is made as of the date hereof, and Talisker is not obligated to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, except as required by applicable securities laws. Because of the risks, uncertainties and assumptions contained herein, investors should not place undue reliance on forward-looking information. The foregoing statements expressly qualify any forward-looking information contained herein.