VIZSLA SILVER DELIVERS POSITIVE FEASIBILITY STUDY FOR THE PANUCO PROJECT
Vizsla Silver (NYSE:VZLA) announced a positive Feasibility Study for its 100%‑owned Panuco silver‑gold project (effective date Nov 4, 2025). The base case assumes US$35.50/oz Ag and US$3,100/oz Au and reports an after‑tax NPV(5%) of US$1,802M, an after‑tax IRR of 111% and a 7‑month payback. Initial costs are US$173.0M with initial capital of US$238.7M and sustaining capital of US$287.3M.
The mine plan yields LOM average 17.4 Moz AgEq/year (20.08 Moz AgEq/year in Years 1–5), LOM AISC of US$10.61/oz AgEq, and a 9.4‑year mine life targeting production in H2 2027.
Vizsla Silver (NYSE:VZLA) ha annunciato uno Studio di Fattibilità positivo per il progetto argent-o-oro Panuco, al 100% di proprietà, con data effettiva 4 novembre 2025. Lo scenario base presuppone US$35,50/oz Ag e US$3.100/oz Au e riporta un NPV(5%) post‑tasse di US$1.802 M, un IRR post‑tasse del 111% e un payback di 7 mesi. I costi iniziali sono US$173,0M con capitale iniziale US$238,7M e capitale di sostegno US$287,3M.
Il piano di miniera fornisce una media LOM di 17,4 Moz AgEq/anno (20,08 Moz AgEq/anno nei primi 5 anni), LOM AISC di US$10,61/oz AgEq, e una vita della miniera di 9,4 anni con produzione prevista nella seconda metà del 2027.
Vizsla Silver (NYSE:VZLA) anunció un estudio de factibilidad positivo para su proyecto de plata y oro Panuco, 100% propio (fecha efectiva 4 de noviembre de 2025). El escenario base asume US$35,50/oz de plata y US$3.100/oz de oro y reporta un NPV(5%) tras impuestos de US$1.802 M, un IRR tras impuestos del 111% y un payback de 7 meses. Los costos iniciales son US$173,0M con capital inicial de US$238,7M y capital de sostenimiento US$287,3M.
El plan de la mina aporta un promedio LOM de 17,4 Moz AgEq/año (20,08 Moz AgEq/año en los años 1–5), LOM AISC de US$10,61/oz AgEq, y una vida de mina de 9,4 años con producción objetivo en la H2 de 2027.
Vizsla Silver (NYSE:VZLA)은 100% 소유의 Panuco 실버-골드 프로젝트에 대한 긍정적인 타당성 연구를 발표했습니다(발효일 2025년 11월 4일). 기본 시나리오는 은 1oz당 US$35.50, 금 1oz당 US$3,100를 가정하고 세후 NPV(5%) US$1,802M, 세후 IRR 111%, 7개월 회수를 보고합니다. 초기비용은 US$173.0M이고 초기 자본은 US$238.7M, 유지자본은 US$287.3M입니다.
광구 계획은 LOM 평균 17.4 Moz AgEq/년 (1–5년은 연간 20.08 Moz AgEq), LOM AISC는 US$10.61/oz AgEq이며, 광산 수명은 9.4년으로 2027년 하반기 생산을 목표로 합니다.
Vizsla Silver (NYSE:VZLA) a annoncé une étude de faisabilité positive pour son projet argent-or Panuco, détenu à 100% (date effective 4 novembre 2025). Le scénario de base suppose US$35,50/oz Ag et US$3 100/oz Au et rapporte une VAN (après impôt) à 5% de US$1,802 M, un TIR après impôt de 111% et un délai de récupération de 7 mois. Les coûts initiaux s'élèvent à US$173,0 M avec un capital initial de US$238,7 M et un capital de maintien de US$287,3 M.
Le plan minier donne une moyenne LOM de 17,4 Moz AgEq/an (20,08 Moz AgEq/an sur les années 1–5), LOM AISC de US$10,61/oz AgEq, et une durée de vie de la mine de 9,4 ans avec production visée à partir de la seconde moitié de 2027.
Vizsla Silver (NYSE:VZLA) hat eine positive Machbarkeitsstudie für das zu 100 % im Besitz befindliche Panuco Silber-Gold-Projekt bekannt gegeben (Stichtag 4. November 2025). Das Basisszenario geht von US$35,50/oz Ag und US$3.100/oz Au aus und meldet ein nach Steuern NPV(5%) von US$1.802 M, einen nach Steuern IRR von 111% und eine Payback-Periode von 7 Monaten. Die Anfangskosten betragen US$173,0 M bei anfänglichem Kapital US$238,7 M und Erhaltungskapital US$287,3 M.
Der Minenplan ergibt eine LOM-Durchschnitt von 17,4 Moz AgEq/Jahr (1–5 Jahre 20,08 Moz AgEq/Jahr), eine LOM AISC von US$10,61/oz AgEq und eine Minenlaufzeit von 9,4 Jahren mit Produktion ab der 2. Hälfte 2027.
Vizsla Silver (NYSE:VZLA) أعلنت عن دراسة جدوى إيجابية لمشروع الفضة-الذهب Panuco المملوك بنسبة 100% (تاريخ النفاذ 4 نوفمبر 2025). تفترض الحالة الأساسية US$35.50/أونصة فضة وUS$3,100/أونصة ذهب وتورد صافي القيمة الحالية بعد الضريبة (5%) قدرها US$1,802M، ومعدل العائد الداخلي بعد الضريبة 111% وفترة استرداد قدرها 7 أشهر. التكاليف الأولية US$173.0M مع رأس مال ابتدائي US$238.7M ورأس مال تشغيلي US$287.3M.
يؤدي خطة المنجم إلى متوسط LOM 17.4 Moz AgEq/سنة (20.08 Moz AgEq/سنة في السنوات 1–5)، وLOM AISC قدره US$10.61/oz AgEq، وعمر منجم قدره 9.4 سنوات باستهداف الإنتاج في النصف الثاني من 2027.
- After‑tax NPV(5%) US$1,802M
- After‑tax IRR 111% and 7‑month payback
- Average annual production 17.38 koz AgEq (17.4 Moz AgEq/year) LOM; 20.08 Moz AgEq/year (Years 1–5)
- LOM AISC US$10.61/oz payable AgEq
- Initial capital US$238.7M (Preproduction Initial Costs US$173.0M)
- Sustaining capital US$287.3M over life of mine
- Mine life relatively short at 9.4 years (LOM)
Insights
Feasibility study shows a highly attractive, low‑CAPEX underground silver‑gold project with rapid payback and strong economics.
The study models a 3,300–4,000 tpd underground operation producing an average of 17.4 million oz AgEq per year and LOM AISC of
Key dependencies and risks include metal price sensitivity and the usual execution items for underground builds: permitting, financing and contractor performance. The study explicitly uses Mineral Reserves only, excludes inferred resources, and tests sensitivities showing NPV and IRR remain positive down to
NYSE: VZLA TSX: VZLA
After-Tax NPV (
The Feasibility Study, completed by Ausenco Engineering Canada ULC ("Ausenco"), supported by Mining Plus Canada Consulting Ltd. ("Mining Plus") and SGS Canada Inc. ("SGS"), provides a robust case for developing the
"The strength of the Feasibility Study reflects the technical excellence and commitment of the Vizsla Silver team and all of our consultants," stated Simon Cmrlec, COO of Vizsla Silver. "The engineering and procurement for the project was significantly advanced during the Feasibility Study, which coupled with the actual performance of the ongoing test mine provides confidence in the results of the study. Project CAPEX and OPEX remain in line with the PEA, and the study demonstrates the project will produce more than 20 million silver equivalent ounces annually over the first five years, averaging 17.4 million ounces over the life of the project, significantly exceeding the production profile outlined in the PEA."
"We are very pleased to deliver a robust Feasibility Study on the
Feasibility Study Webcast
Vizsla Silver will be hosting a webcast to discuss the Panuco Project Feasibility Study at 10:00 am PT (1:00 pm ET) on November 24th. To register, please click here.
Feasibility Study Highlights (Base Case)
-
3,300 tonnes per day ("tpd") production rate for the first three years, expanding to 4,000 tpd in year 4, producing silver-gold doré with an initial mine life of 9.4 years
-
High-grade underground mine with Proven and Probable Mineral Reserves1 averaging
US /t NSR value (diluted) comprising:$337 -
Copala deposit with 7.90 Mt averaging 318 g/t Ag and 2.05 g/t Au -
Napoleon deposit with 4.91 Mt averaging 139 g/t Ag and 1.95 g/t Au
-
-
Life of mine ("LOM") average annual payable production of 17,383 koz AgEq2 per year (10,130 koz Ag per year and 83 koz Au per year)
-
Years 1-5 average annual payable production of 20,078 koz AgEq per year (12,067 koz Ag per year and 92 koz Au per year)
-
LOM cash costs3 of
US /oz payable AgEq on a co-product basis, LOM all-in sustaining costs (AISC4) of$8.56 US /oz payable AgEq on a co-product basis$10.61 -
Pre-production capital expenditures ("CAPEX") of
US $238.7M -
After-tax NPV(
5% ) ofUS and$1,802 million 111% IRR atUS /oz Au and$3,100 US /oz Ag$35.50 -
After-tax payback period of 7 months
|
1. |
Underground Proven and Probable Mineral Reserve Estimate contains only Measured and Indicated Resources |
|
2. |
AgEq oz = Ag oz + Au oz x ( |
|
3. |
Total cash costs consist of operating cash costs plus royalties and offsite (refining & transport) charges |
|
4. |
AISC consist of total cash costs plus sustaining capital and closure costs |
Feasibility Study Overview
The 2025 Panuco Feasibility Study considers two contiguous underground mines, the Copala Mine and the Napoleon Mine, with on-site treatment of the mined material processed through a 3-stage crushing-grinding circuit, along with a leach and Merrill Crowe circuit to produce silver-gold doré bars. The mines will be contractor-operated, utilizing ramp-access and a combination of long-hole stoping and drift-and-fill mining methods.
The processing throughput capacity of 3,300 tonnes per day for the first 3 years, expanding to 4,000 tonnes per day in year 4, results in an initial mine life of 9.4 years. The Feasibility Study leverages the
The Feasibility Study is derived using the Company's updated NI 43-101 Mineral Resource Estimate (dated February 20, 2025). The effective date of the Feasibility Study is November 4th, 2025, and an NI 43-101 compliant technical report on the Feasibility Study (the "Technical Report") will be filed on the Company's website and SEDAR+ within 45 days of this disclosure.
|
General |
LOM Total / Avg. |
|
Gold Price (US$/oz) |
3,100 |
|
Silver Price (US$/oz) |
35.50 |
|
Mine Life (Years) |
9.4 |
|
Total Processed Feed Tonnes (kt) |
12,809 |
|
Total Waste Tonnes (kt) |
6,284 |
|
Production |
LOM Total / Avg. |
|
Head Grade – Ag (g/t) |
249 |
|
Head Grade – Au (g/t) |
2.01 |
|
Recovery Rate – Ag (%) to doré |
92.3 |
|
Recovery Rate – Au (%) to doré |
93.8 |
|
Total Metal Payable – Ag (koz) |
94,725 |
|
Total Metal Payable – Au (koz) |
776 |
|
Average Annual Payable Production – Ag (koz) |
10,130 |
|
Average Annual Payable Production – Au (koz) |
83 |
|
Average Annual Payable Production – AgEq. (koz) |
17,382 |
|
Average Annual Payable Production (Yrs 1-5) – AgEq. (koz) |
20,078 |
|
Operating Costs |
LOM Total / Avg. |
|
Mining Cost (US$/t Processed) |
53.31 |
|
Processing Cost (US$/t Processed) (incl. TSF) |
24.84 |
|
G&A Cost (US$/t Processed) |
6.96 |
|
Total Operating Costs (US$/t Processed) |
85.11 |
|
Cash Costs1 (Co-Product Basis) (US$/oz AgEq2) |
8.56 |
|
AISC3(Co-Product Basis) (US$/oz AgEq2) |
10.61 |
|
Capital Costs |
LOM Total / Avg. |
|
Initial Capital (US$M) |
238.7 |
|
Preproduction Revenue (US$M)4 |
-127.7 |
|
Preproduction Costs (US$M)5 |
62.0 |
|
Initial Costs (Initial Capital + Preproduction Revenue & Costs) (US$M) |
173.0 |
|
Sustaining Capital (US$M) |
287.3 |
|
Closure Capital (US$M) |
37.5 |
|
Salvage Value (US$M) |
-9.6 |
|
Financials |
Pre-Tax |
|
NPV ( |
2,842 |
|
IRR (%) |
159 |
|
Payback (Years) |
0.4 |
|
Financials |
Post-Tax |
|
NPV ( |
1,802 |
|
IRR (%) |
111 |
|
Payback (Years) |
0.6 |
|
Post-Tax NPV/Initial Capital |
7.5 |
Table 1: Panuco Feasibility Study Detailed Parameters and Outputs
|
1. |
Total cash costs consist of operating cash costs plus royalties and offsite (refining & transport) charges |
|
2. |
AgEq oz = Ag oz + Au oz x ( |
|
3. |
AISC consist of total cash costs plus sustaining capital and closure costs |
|
4. |
Preproduction revenue includes revenue until the start of commercial production, which is defined as 60 days after mill start |
|
5. |
Preproduction costs include: mining, processing and G&A operating costs, offsite charges, and royalties until the start of commercial production, which is defined as 60 days after mill start |
The economic analysis assumes metal prices of
The Feasibility Study demonstrates strong economic resilience, with post-tax NPV(
|
Inputs |
Post-Tax Sensitivity to Metal Prices |
|||||
|
|
(50.0 %) |
(25.0 %) |
Base Case |
25.0 % |
50.0 % |
|
|
Ag (US$/oz) |
|
|
|
|
|
|
|
Au (US$/oz) |
|
|
|
|
|
|
|
Post-Tax NPV( |
|
|
|
|
|
|
|
Post-Tax IRR (%) |
42.4 % |
79.4 % |
111.1 % |
139.7 % |
165.4 % |
|
Table 2: Sensitivity Summary Post Tax NPV
|
Inputs |
Sensitivity Summary Post-Tax NPV |
|||||
|
|
(20.0 %) |
(10.0 %) |
Base Case |
10.0 % |
20.0 % |
|
|
Head Grade (+/-%) |
|
|
|
|
|
|
|
Recovery (+/-%) |
|
|
|
|
|
|
|
Operating Costs (+/%) |
|
|
|
|
|
|
|
Initial Capex (+/-%) |
|
|
|
|
|
|
Table 3: Sensitivity Summary Post Tax NPV
|
Inputs |
Sensitivity Summary Post-Tax IRR (%) |
|||||
|
|
(20.0 %) |
(10.0 %) |
Base Case |
10.0 % |
20.0 % |
|
|
Head Grade (+/-%) |
85.8 % |
98.7 % |
111.1 % |
123.0 % |
134.2 % |
|
|
Recovery (+/-%) |
86.3 % |
98.9 % |
111.1 % |
119.5 % |
119.8 % |
|
|
Operating Costs (+/-%) |
117.6 % |
114.3 % |
111.1 % |
107.8 % |
104.6 % |
|
|
Initial Capex (+/-%) |
132.5 % |
120.8 % |
111.1 % |
102.7 % |
95.5 % |
|
Table 4: Sensitivity Summary Post Tax IRR (%)
Mineral Reserves
The Proven and Probable Mineral Reserve for the
The initial Mineral Reserve estimate was prepared by Jason Blais, P.Eng., Principal Mining Consultant of Mining Plus with an effective date of November 4th, 2025.
|
Classification |
Tonnes |
Grade |
Contained Metal |
||||
|
(kt) |
Ag (g/t) |
Au (g/t) |
AgEq (g/t) |
Ag (k oz) |
Au (k oz) |
AgEq (k oz) |
|
|
Proven |
1,948 |
308 |
2.35 |
502 |
19,264 |
147 |
31,424 |
|
Probable |
10,854 |
239 |
1.95 |
400 |
83,351 |
681 |
139,687 |
|
Planned Stockpile Proven |
4 |
330 |
3.70 |
635 |
41 |
0.5 |
82 |
|
Probable |
3 |
318 |
2.90 |
558 |
34 |
0.3 |
54 |
|
Total Proven + Probable |
12,809 |
249 |
2.01 |
416 |
102,689 |
829 |
171,246 |
Table 5: Mineral Reserve Estimate
|
1. |
The Mineral Reserve is estimated using the 2019 CIM Estimation of Mineral Resources & Mineral Reserves Best Practice Guidelines and 2014 CIM Definition Standards for Mineral Resources & Mineral Reserves. |
|
2. |
Mineral Reserves are based on Measured and Indicated Mineral Resource Classifications only. |
|
3. |
The Mineral Reserve was calculated using long-term metal prices of |
|
4. |
The block model NSR value was calculated on an individual block basis using interim Phase 2 process recovery formulas for each zone. |
|
5. |
The Mineral Reserve is estimated using three NSR cut-off values (COV). A Fully Costed COV was calculated at |
|
6. |
The Planned Stockpile is anticipated to be mined from the |
|
7. |
Royalty rates of |
|
8. |
AgEq (g/t) = (Ag(g/t) + 82.54*Au(g/t)) for Copala & Tajitos and AgEq = (Ag(g/t) + 82.97*Au(g/t)) for Napoleon & Luisa at |
|
9. |
Mining recovery between |
|
10. |
The Mineral Reserve includes both planned and unplanned dilution. Unplanned dilution includes dilution from overbreak, backfill and material handling. Dilution within Stope Optimizer (SO) outputs was estimated at |
|
11. |
For LHS, a minimum mining width of 1.5 meters was used excluding overbreak and unplanned dilution, and for DAF, a minimum mining width of 5.0 meters was used. |
|
12. |
The economic viability of the Mineral Reserve is demonstrated using a discounted cash flow model. |
|
13. |
The independent and qualified person responsible for the Mineral Reserve, as defined by NI 43-101, is Mr. Jason Blais, P.Eng., Principal Mining Consultant for Mining Plus Canada Consulting Ltd. |
|
14. |
The effective date of the Mineral Reserve Estimate is November 4th, 2025. |
|
15. |
Totals may not add up due to rounding.
|
|
Metal |
Unit |
Copala & Tajitos
( |
Napoleon & Luisa |
Napoleon
( |
|
Ag Price |
USD/oz |
28.5 |
28.5 |
28.5 |
|
Au Price |
USD/oz |
2,300 |
2,300 |
2,300 |
|
Average Ag Process Recovery |
% |
92.8 |
94.4 |
94.4 |
|
Average Au Process Recovery |
% |
93.2 |
95.3 |
95.3 |
|
Ag Payable |
% |
99.9 |
99.9 |
99.9 |
|
Au Payable |
% |
99.85 |
99.85 |
99.85 |
|
Product Freight |
USD/t |
3,000 |
3,000 |
3,000 |
|
Ag Refining |
USD/oz |
0.50 |
0.50 |
0.50 |
|
Au Refining |
USD/oz |
5.00 |
5.00 |
5.00 |
|
Royalty |
% |
3.50 % |
3.50 % |
2 % |
|
Ag Multiplier |
USD/g |
0.8027 |
0.8162 |
0.8289 |
|
Au Multiplier |
USD/g |
66.2536 |
67.7202 |
68.7728 |
|
Ag Equivalence |
g Ag/g Au |
82.538 |
82.970 |
82.969 |
Table 6: Inputs Used to Calculate NSR for Gold & Silver
Mineral Resources
|
|
Resource |
Tonnes |
Grade |
Total Metal |
||||||||
|
Au |
Ag |
Pb % |
Zn % |
AgEq |
Au |
Ag |
Pb |
Zn |
AgEq |
|||
|
|
Measured |
1.88 |
3.09 |
442 |
0.08 |
0.15 |
684 |
187 |
26,744 |
3.2 |
6.3 |
41,418 |
|
Indicated |
4.29 |
2.50 |
402 |
0.09 |
0.17 |
600 |
345 |
55,374 |
8.4 |
15.8 |
82,781 |
|
|
M+I |
6.17 |
2.68 |
414 |
0.09 |
0.16 |
626 |
532 |
82,118 |
11.6 |
22.1 |
124,199 |
|
|
Inferred |
2.32 |
1.83 |
322 |
0.16 |
0.27 |
476 |
137 |
24,014 |
8.3 |
13.8 |
35,452 |
|
|
|
Indicated |
0.72 |
2.34 |
380 |
0.14 |
0.25 |
571 |
55 |
8,833 |
2.2 |
4.0 |
13,277 |
|
Inferred |
0.89 |
2.08 |
346 |
0.27 |
0.43 |
527 |
60 |
9,936 |
5.2 |
8.5 |
15,132 |
|
|
Cristiano |
Indicated |
0.36 |
3.67 |
610 |
0.25 |
0.45 |
912 |
43 |
7,102 |
2.0 |
3.6 |
10,614 |
|
Inferred |
0.34 |
2.49 |
460 |
0.16 |
0.31 |
665 |
27 |
4,959 |
1.2 |
2.3 |
7,168 |
|
|
Total |
Measured |
1.88 |
3.09 |
442 |
0.08 |
0.15 |
684 |
187 |
26,744 |
3.2 |
6.3 |
41,418 |
|
Indicated |
5.37 |
2.56 |
413 |
0.11 |
0.20 |
617 |
443 |
71,309 |
13 |
23 |
106,672 |
|
|
M+I |
7.26 |
2.70 |
420 |
0.10 |
0.19 |
635 |
630 |
98,053 |
16 |
30 |
148,090 |
|
|
Inferred |
3.55 |
1.96 |
341 |
0.19 |
0.31 |
507 |
224 |
38,909 |
15 |
25 |
57,752 |
|
|
Napoleon |
Resource |
Tonnes |
Grade |
Total Metal |
||||||||
|
Au (g/t) |
Ag (g/t) |
Pb % |
Zn % |
AgEq (g/t) |
Au (koz) |
Ag (koz) |
Pb (Mlbs) |
Zn (Mlbs) |
AgEq (koz) |
|||
|
La Luisa |
Indicated |
0.49 |
2.12 |
143 |
0.31 |
1.44 |
364 |
33 |
2,238 |
3.3 |
15.4 |
5,693 |
|
Inferred |
2.83 |
2.24 |
132 |
0.28 |
1.24 |
355 |
204 |
12,049 |
17.8 |
77.5 |
32,307 |
|
|
Cruz Negra |
Indicated |
0.03 |
2.01 |
145 |
0.38 |
2.01 |
380 |
2 |
154 |
0.3 |
1.5 |
403 |
|
Inferred |
0.35 |
3.58 |
171 |
0.30 |
1.64 |
510 |
40 |
1,907 |
2.3 |
12.5 |
5,676 |
|
|
Josephine |
Indicated |
0.06 |
2.54 |
230 |
0.38 |
1.09 |
473 |
5 |
452 |
0.5 |
1.5 |
928 |
|
Inferred |
0.21 |
1.81 |
176 |
0.34 |
1.01 |
360 |
12 |
1,180 |
1.6 |
4.6 |
2,406 |
|
|
Napoleon HW(4) |
Indicated |
0.99 |
2.09 |
217 |
0.47 |
1.64 |
448 |
66 |
6,885 |
10.2 |
35.7 |
14,206 |
|
Inferred |
0.59 |
2.12 |
202 |
0.64 |
2.15 |
458 |
40 |
3,800 |
8.2 |
27.7 |
8,619 |
|
|
Napoleon +Splays |
Measured |
0.36 |
2.34 |
161 |
0.51 |
1.41 |
404 |
27 |
1,853 |
4.0 |
11.1 |
4,638 |
|
Indicated |
3.78 |
2.25 |
150 |
0.52 |
1.78 |
399 |
273 |
18,184 |
42.9 |
148.2 |
48,404 |
|
|
M+I |
4.13 |
2.26 |
151 |
0.51 |
1.75 |
399 |
300 |
20,037 |
47 |
159 |
53,042 |
|
|
Inferred |
2.28 |
1.46 |
159 |
0.44 |
1.63 |
340 |
107 |
11,637 |
21.9 |
81.8 |
24,941 |
|
|
Total |
Measured |
0.36 |
2.34 |
161 |
0.51 |
1.41 |
404 |
27 |
1,853 |
4.0 |
11.1 |
4,638 |
|
Indicated |
5.34 |
2.21 |
163 |
0.49 |
1.72 |
405 |
379 |
27,913 |
57 |
202 |
69,634 |
|
|
M +I |
5.70 |
2.22 |
162 |
0.49 |
1.70 |
405 |
406 |
29,766 |
61 |
213 |
74,272 |
|
|
Inferred |
6.25 |
2.00 |
152 |
0.38 |
1.48 |
368 |
403 |
30,573 |
52 |
204 |
73,949 |
|
Table 7: Mineral Resources for
|
1. |
The classification of the current Mineral Resource Estimate into Indicated and Inferred is consistent with current 2014 CIM Definition Standards - For Mineral Resources and Mineral Reserves. |
|
2. |
Tables presented include only the |
|
3. |
All figures are rounded to reflect the relative accuracy of the estimate and numbers may not add due to rounding. |
|
4. |
All mineral resources are presented undiluted and in situ, constrained by continuous 3D wireframe models (considered mineable shapes), and are considered to have reasonable prospects for eventual economic extraction. |
|
5. |
Mineral resources which are not mineral reserves do not have demonstrated economic viability. An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration. |
|
6. |
It is envisioned that the Panuco Project deposits may be mined using underground mining methods including longhole stoping (LHS) and/or drift-and-fill (DAF). Mineral resources are reported at a base case cut-off grade of 150 g/t AgEq. The mineral resource grade blocks were quantified above the base case cut-off grade, below surface and within the constraining mineralized wireframes. |
|
7. |
Based on the size, shape, general thickness and orientation of the majority of the mineralized zones within the project area, it is envisioned that the deposits may be mined using a combination of underground mining methods including longhole stoping (LHS) and/or drift-and-fill (DAF). |
|
8. |
The base-case AgEq Cut-off grade considers metal prices of |
|
9. |
The base case cut-off grade of 150 g/t AgEq considers a mining cost of |
|
10. |
The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. |
|
11. |
Mineral Resources are inclusive of Mineral Reserves. |
|
12. |
The independent and qualified person responsible for the Mineral Resource, as defined by NI 43-101, is Allan Armitage, Ph.D, P.Geo., of SGS . |
|
13. |
The effective date of the Mineral Resource Estimate is September 9, 2024. |
Capital and Operating Costs
The pre-production initial CAPEX is estimated to be
Sustaining Capital is expected to average approximately
The Feasibility Study is based on contractor underground mining, which has an estimated LOM cost of
The capital and operating cost estimate was developed in Q4 2025 United States Dollars (US$). The capital cost summary is presented in Table 8, and the operating cost summary is presented in Table 9.
|
WBS Description |
Initial Capital |
Sustaining Capital Cost |
Expansion Capital |
Total Capital Cost |
|
Mining |
60.2 |
259.1 |
0.6 |
319.6 |
|
Process Plant |
63.9 |
0 |
8.8 |
98.0 |
|
Additional Process Facilities |
18.7 |
25.0 |
1.1 |
19.9 |
|
On Site Infrastructure |
32.8 |
0.2 |
1.7 |
34.7 |
|
Off Site Infrastructure |
1.1 |
- |
- |
1.1 |
|
Total Directs |
176.7 |
284.4 |
12.2 |
473.4 |
|
Project Preliminaries |
8.1 |
- |
- |
8.1 |
|
Project Delivery |
19.7 |
- |
1.6 |
21.3 |
|
Owner's Costs |
10.1 |
- |
- |
10.1 |
|
Provisions (Contingency) |
24.0 |
2.9 |
1.5 |
28.5 |
|
Total Indirects |
61.9 |
2.9 |
3.1 |
68.0 |
|
Project Totals |
238.7 |
287.3 |
15.4 |
541.3 |
Table 8: Project Capital Cost Estimates (US$M) (totals may differ due to rounding)
|
1. |
Totals may differ due to rounding |
|
Cost Area |
Average Annual Costs (US$M) |
US$/t Processed |
|
Mining |
71.9 |
53.31 |
|
Process (incl. TSF) |
33.5 |
24.84 |
|
General and Administration |
9.4 |
6.96 |
|
Total |
114.9 |
85.11 |
Table 9: Project Operating Cost Estimates (US$M)
|
2. |
Totals may differ due to rounding |
Mining
The Panuco Project is a collection of silver-gold deposits located in the
Based on the characteristics of the deposit, long-hole stoping ("LHS") was selected as the primary mining method for all deposits, with drift-and-fill ("DAF") selected for the northern portion of the Copala North Zone, which is located directly under the
The mining methods considered for the Panuco Project are proposed to use a combination of cemented rock backfill (CRF), uncemented rock backfill, and paste backfill for stope support.
For the feasibility design of the Panuco Project, planned dilution and unplanned rock dilution (ELOS) was accounted for using the Deswik Stope Optimizer® ("SO"). Dilution within SO outputs was estimated at
A Net Smelter Return (NSR) model was used to estimate the revenue of the mineralized material. Interim process recoveries, doré grades, smelting and refining terms, royalties and transportation costs were assumed to determine the NSR value. A Cut-Off Value ("COV") was used to flag material by whether the revenue in a block exceeds the costs of extraction and processing of that block. Following the financial model completion, there were three COVs used to assess mining at
The Fully Costed COV represents the break-even value of Mineral Reserve required to cover all the associated operating and sustaining capital costs of extraction and processing. Fully costed COVs were initially assumed for
The Incremental COV of US
The Marginal COV of
Due to the distance between the various geological deposits, the project is separated into two underground mines. The Copala Mine, the larger of the two, accesses the
Contractor mining is currently proposed for the Panuco Project to minimize upfront capital, leverage skilled labour and achieve higher productivity. The annual
|
Period |
Waste |
Development |
Stoping1 |
Total Mineralized |
Total Mined
|
|
kt |
kt |
kt |
kt |
kt |
|
|
YEAR \ |
6,284 |
2,508 |
10,294 |
12,802 |
19,085 |
|
|
343 |
74 |
- |
74 |
417 |
|
|
446 |
137 |
336 |
473 |
919 |
|
|
449 |
199 |
661 |
859 |
1,308 |
|
|
797 |
235 |
991 |
1,226 |
2,023 |
|
|
626 |
361 |
948 |
1,310 |
1,936 |
|
|
650 |
304 |
1,295 |
1,599 |
2,250 |
|
|
659 |
220 |
1,315 |
1,535 |
2,194 |
|
|
776 |
313 |
1,220 |
1,533 |
2,310 |
|
|
634 |
358 |
1,139 |
1,497 |
2,131 |
|
|
622 |
238 |
1,144 |
1,382 |
2,004 |
|
|
282 |
68 |
1,092 |
1,160 |
1,441 |
|
|
- |
- |
153 |
153 |
153 |
Table 10: Total and Annual Material Movement Schedule for the Panuco Project
|
1. |
Stoping includes Drift and Fill production. |
Processing and Metallurgy
Vizsla Silver has completed four rounds of metallurgical test work on the Panuco Project deposits since 2021. The latest round of test work (2025) focussed on variability within the deposit, defining consumable usage within the deposits and ensuring process efficiency was optimized.
Test work in 2025 included comminution test work, variability work on both whole ore leach and flotation flowsheets, oxygen uptake, thickening, rheology, paste characterisation and cyanide detoxification.
Based on the test work and mine plan feed grades, life-of-mine average recoveries are estimated at
The Feasibility Study outlines a two-phase process plant design, beginning with a 3,300-tonne-per-day whole-ore leach circuit utilizing a primary grind of 50 µm. Ore will be processed through a three-stage crushing circuit, followed by grinding to 50 µm in a ball mill. The ground slurry will then enter the leach circuit for a total retention time of approximately 96 hours. Leach discharge will flow by gravity to a counter-current decantation (CCD) circuit, where solids are separated from the pregnant liquor. Pregnant liquor then reports to the Merrill Crowe and refinery circuits to produce silver-gold doré.
Phase 2, scheduled for Year 4, will expand throughput to 4,000 tonnes per day and increase the primary grind size to 70 µm, incorporating a flotation and regrind circuit between the ball-mill discharge and leach feed. The additional circuit enables a coarser primary grind, improves overall metal recovery, and optimizes power and reagent efficiency. Flotation concentrate, which contains a high proportion of gold, will be treated in a high intensity grinding mill and reduced to 20 µm. Ground concentrate is then leached separately from the flotation tailings and then fed into the tailings leach circuit with the tailings to maximize metal recovery.
Infrastructure
Access to the Panuco Project is planned via Highway 40 through the expansion of an existing entryway, incorporating traffic control measures to ensure safe entry and exit from the site. Existing site roads will be upgraded, and community access routes will remain open and safely distanced from active mining areas.
Electrical power for the project will be sourced from a 230 kV transmission line that traverses the property. Vizsla plans to construct an on-site switching substation adjacent to the process plant (the project's largest power consumer) and distribute electricity at 13 kV throughout the site as needed.
Underground dewatering will serve as the primary water source for the project. Vizsla intends to reuse and recycle as much water as possible and has developed a water management plan where the wet season excess water can be stored for process use during drier months.
Tailings from the process plant will be piped to the tailings storage facility (TSF) which follows the access road. The TSF is designed as a centreline raise embankment with 4 stages throughout the project life.
The Feasibility Study envisages a stockpile of ore created ahead of commissioning the process plant. This approach reduces project start-up risk and supports consistent grade control during commissioning and early operations. The pre-production stockpile is estimated to total approximately 523,000 tonnes, providing a buffer equivalent to five months of process plant feed.
Permitting & Environmental
The project currently operates under mine exploration permits granted in 2020 and 2021 by SEMARNAT (the Secretariat of Environment and Natural Resources). An active Informe Preventivo (IP) covers the Panuco Project area, authorizing ongoing drilling and exploration activities. All activities related to the Test Mine are authorized under existing permits.
The construction and operation phases of the project require several additional environmental permits. Applications for the Environmental Impact Assessment (EIA) and the corresponding Risk Assessment were submitted in the first quarter of 2025 and are currently under review by SEMARNAT. In parallel, the preparation of technical documentation for the Land Use Change is in progress. Additional permits required for project development include a construction permit from the local municipality, and explosives permit from the Ministry of Defense.
The baseline environmental information collected to date has been largely presented in reports commissioned to support the submission of an Environmental Impact Assessment (MIA in
Regarding communities, Vizsla Silver has negotiated operating agreements with all five Ejidos in the greater
Project Enhancement Opportunities
The Feasibility Study does not incorporate any inferred resources; however, opportunities exist across all deposit areas to upgrade inferred material to indicated or measured categories, particularly once underground drilling can be conducted from optimized collar locations, reducing drill costs and improving data quality. Extending the mine life at
Metal prices applied in the Feasibility Study's Mineral Reserve Estimate are more conservative than those used in the financial model. This creates potential to increase the contained ounces in the mine plan by converting additional Measured and Indicated Mineral Resources to Mineral Reserves by using the financial model metal prices to evaluate the inclusion of additional inventory.
Vizsla is evaluating partnerships with regional power providers that could reduce substation capital costs and support the delivery of lower-carbon electricity to the project within
Qualified Persons
A team of independent Qualified Persons (as such term is defined under NI 43-101) at Ausenco, Mining Plus and SGS have led and prepared the Feasibility Study and have reviewed and verified the technical disclosure in this press release, including:
- Kevin Murray P.Eng., of Ausenco, is an independent Qualified Person responsible for the metallurgical testing, recovery methods, process plant and infrastructure cost estimation and economic analysis in the Feasibility Study.
- Mr. Jason Blais, P.Eng., of Mining Plus is an independent Qualified Person responsible for the mineral reserve estimate, mining methods and mining cost estimation in the Feasibility Study.
- Mr. Cale DuBois, P.Eng., of Mining Plus is an independent Qualified Person responsible for the underground mining geotech in the Feasibility Study.
- James Millard Geo., of Ausenco, is an independent Qualified Person responsible for the environmental, permitting and social considerations in the Feasibility Study.
- Allan Armitage, Ph.D, P.Geo., of SGS, is an independent Qualified Person responsible for the Property description and location, mineral resource estimate and discussion of adjacent properties in the Feasibility Study.
In accordance with NI 43-101, Jesus Velador, Ph.D. MMSA QP., Vice President of Exploration, is the Qualified Person for the Company and has reviewed and approved the technical and scientific content of this news release.
About Vizsla Silver and the Panuco Project
Vizsla Silver is a Canadian mineral exploration and development company headquartered in
About Ausenco
Ausenco is a global engineering, consulting and project delivery company providing solutions to the minerals and metal industry. Ausenco's experience in precious metals projects ranges from conceptual, pre-feasibility and feasibility studies for new project developments to project execution with EPCM delivery. Ausenco is currently engaged on several global projects with similar characteristics and opportunities to the
Information Concerning Estimates of Mineral Resources
The scientific and technical information in this news release was prepared in accordance with NI 43-101 which differs significantly from the requirements of the
You are cautioned not to assume that any part or all of mineral resources will ever be converted into reserves. Pursuant to CIM Definition Standards, "inferred mineral resources" are that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Such geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An inferred mineral resource has a lower level of confidence than that applying to an indicated mineral resource and must not be converted to a mineral reserve. However, it is reasonably expected that the majority of inferred mineral resources could be upgraded to indicated mineral resources with continued exploration. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies, except in rare cases. Investors are cautioned not to assume that all or any part of an inferred mineral resource is economically or legally mineable. Disclosure of "contained ounces" in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute "reserves" by SEC standards as in place tonnage and grade without reference to unit measures.
Canadian standards, including the CIM Definition Standards and NI 43-101, differ significantly from standards in the SEC Industry Guide 7. Effective February 25, 2019, the SEC adopted new mining disclosure rules under subpart 1300 of Regulation S-K of the United States Securities Act of 1933, as amended (the "SEC Modernization Rules"), with compliance required for the first fiscal year beginning on or after January 1, 2021. The SEC Modernization Rules replace the historical property disclosure requirements included in SEC Industry Guide 7. As a result of the adoption of the SEC Modernization Rules, the SEC now recognizes estimates of "measured mineral resources", "indicated mineral resources" and "inferred mineral resources". Information regarding mineral resources contained or referenced herein may not be comparable to similar information made public by companies that report according to
Website: www.vizslasilvercorp.ca
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
SPECIAL NOTE REGARDING FORWARD LOOKING STATEMENTS
This news release contains "forward-looking statements" and "forward-looking information" (together, "forward-looking statements") within the meaning of applicable Canadian securities laws and the United States Private Securities Litigation Reform Act of 1995. Forward-looking statements relate to future events or performance and reflect management's expectations or beliefs regarding future events, plans, and objectives.
Forward-looking statements in this release include, but are not limited to, statements regarding: the potential development of the Panuco Project; the results, interpretation and economic projections of the Feasibility Study, including estimated capital and operating costs, mine life, throughput rates, recoveries, production rates, payback period, AISC, NPV and IRR; the timing, scope and cost of planned exploration, development, permitting and construction activities; the expected timing for submission and approval of environmental permits; expectations regarding project financing and future funding requirements; the anticipated timing of any construction decision, start of production, or achievement of commercial production; the Company's plans to pursue additional exploration, infill drilling, resource expansion, or optimization studies; the potential to upgrade Inferred Resources to Indicated or Measured categories; potential mine life extensions; future metal prices and exchange rates; and other statements regarding management's plans, strategies, and future operations.
Forward-looking statements are based on a number of assumptions believed to be reasonable by the Company as of the date of this release, including, without limitation: the accuracy of the Feasibility Study parameters; the availability of financing on acceptable terms; that required permits and approvals will be obtained in the expected timeframe; continued community and government support; stability in market, political and economic conditions; reasonable accuracy of operating and capital cost estimates; and continued favourable metal prices and exchange rates.
Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause actual results to differ materially. Such risks include, but are not limited to: exploration, development and operating risks; permitting, environmental and regulatory risks; community relations and social licence risks; commodity price and currency fluctuations; inflation and cost escalation; financing and liquidity risks; reliance on contractors and suppliers; title and surface rights risks; changes in project parameters; inaccuracies in technical or economic modelling; the risk that the Feasibility Study assumptions prove inaccurate; and other risks described in the Company's continuous disclosure filings available under its profile on SEDAR+ at www.sedarplus.ca.
There can be no assurance that the Panuco Project will be placed into production or that the results of the Feasibility Study will be realized. The purpose of the forward-looking statements is to provide information about management's current expectations and plans and may not be appropriate for other purposes. Readers are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date of this release. Except as required by applicable law, the Company undertakes no obligation to update or revise any forward-looking statements contained herein.
No Production Decision: The Company has not made a production decision for the Panuco Project. A decision to proceed with construction will only be made following the completion and review of detailed engineering, financing arrangements, and receipt of all required permits and approvals.
View original content to download multimedia:https://www.prnewswire.com/news-releases/vizsla-silver-delivers-positive-feasibility-study-for-the-panuco-project-302612539.html
SOURCE Vizsla Silver Corp.