Applied Optoelectronics (NASDAQ: AAOI) inks $30.9M FAB2 cleanroom design-build contract

Filing Impact
(Moderate)
Filing Sentiment
(Neutral)
Form Type
8-K

Rhea-AI Filing Summary

Applied Optoelectronics, Inc. entered into a design-build agreement with LCC3 Solution Inc. to develop its FAB2 cleanroom project in Sugar Land, Texas. The project covers approximately 92,674 square feet of ISO 6 (Class 1K) certified cleanroom space inside an existing warehouse and includes design, engineering, procurement, construction, testing, commissioning, and closeout work.

The total contract amount is approximately $30,885,000, with payments made monthly based on progress and a 10% retainage held until final completion and punch list resolution. The agreement includes liquidated damages for schedule delays, capped at $1,600,000, as well as schedule-based incentives up to $1,810,000 and performance-based incentives up to $1,724,000 for cleanroom validation and $1,600,000 for warranty performance. Substantial completion is targeted for September 30, 2026.

Positive

  • None.

Negative

  • None.
false 0001158114 0001158114 2026-02-27 2026-02-27 iso4217:USD xbrli:shares iso4217:USD xbrli:shares

 

 

 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

 

 

FORM 8-K

 

CURRENT REPORT

Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934

 

Date of Report (Date of earliest event reported): February 27, 2026

 

 

 

Applied Optoelectronics, Inc.

(Exact name of registrant as specified in its charter)

 

Delaware 001-36083 76-0533927
(State of incorporation) (Commission File Number) (I.R.S. Employer Identification No.)

 

13139 Jess Pirtle Blvd.
Sugar Land
, Texas 77478

(Address of principal executive offices and zip code)

 

(281) 295-1800

(Registrant’s telephone number, including area code)

 

 

 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions (see General Instruction A.2. below):

 

¨Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

 

¨Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

 

¨Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

 

¨Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

 

Securities registered pursuant to Section 12(b) of the Act:

 

Title of each class Trading Symbol(s) Trading Name of each exchange on which registered
Common Stock, Par value $0.001 AAOI NASDAQ Global Market

 

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).

 

Emerging growth company ¨

 

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. o

 

 

 

 

   

 

 

Item 1.01 Entry into a Material Definitive Agreement.

 

On February 27, 2026, Applied Optoelectronics, Inc. (the “Company”) executed a Standard Form of Agreement Between Owner and Design-Builder (AIA Document A141–2024), together with the related Exhibits Package (collectively, the “Design-Build Agreement”), with LCC3 Solution Inc. (the “Design-Builder”), effective as of February 13, 2026, pursuant to which the Design-Builder will design and construct the Company’s FAB2 cleanroom project (the “Project”) at 1111 Gillingham Lane, Sugar Land, Texas 77478.

 

The Project consists of an interior design-build for approximately 92,674 square feet of ISO 6 (Class 1K) certified cleanroom space within an existing warehouse and includes design, engineering, procurement, construction, testing, commissioning, and related closeout activities.

 

The total contract amount for the Project is approximately $30,885,000 (the “Contract Sum”), inclusive of design, construction, and related professional services, as set forth in the Design-Build Agreement. Payments are generally based on progress, with 10% retainage withheld from each pay application and released upon final completion, subject to final acceptance and completion of punch list items. Pay applications are submitted monthly, and payments are due within 15 days after the Company’s receipt of a properly completed pay application.

 

The Design-Build Agreement provides for liquidated damages in the event of delays in achieving specified key milestones or substantial completion, subject to contractual adjustments and conditions, with an aggregate liquidated damages cap of $1,600,000.

 

The Design-Build Agreement also provides for (i) schedule-based incentives tied to the timely achievement of specified key milestones up to $1,810,000 and (ii) performance-based incentives, including up to $1,724,000 tied to cleanroom validation testing and up to $1,600,000 tied to warranty performance, in each case subject to the conditions and determinations set forth in the Design-Build Agreement.

 

The Project has a targeted Substantial Completion date of September 30, 2026.

 

 

Item 2.03 Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement of a Registrant.

 

The information contained in Item 1.01 of this Current Report on Form 8-K with respect to the Lease Agreement is incorporated by reference into Item 2.03.

 

 

Item 9.01 Financial Statements and Exhibits.

 

(d) Exhibits

 

10.1 Standard Form of Agreement Between Owner and Design-Builder (AIA Document A141–2024), effective as of February 13, 2026, by and between Applied Optoelectronics, Inc. and LCC3 Solution Inc.
10.2 Exhibits Package to Design-Build Contract (FAB2 Exhibit Package), effective as of February 13, 2026.
104 Cover Page Interactive File (the cover page tags are embedded within the Inline XBRL document).

 

 

 

 2 

 

 

SIGNATURES

 

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

 

 

APPLIED OPTOELECTRONICS, INC.

 
       
       
  By: /s/ David C. Kuo  
    David C. Kuo  
   Senior Vice President and Chief Legal Officer  

 

Date: March 5, 2026

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 3 

 

FAQ

What did Applied Optoelectronics (AAOI) agree to build in the new FAB2 project?

Applied Optoelectronics agreed to build an interior FAB2 cleanroom project covering about 92,674 square feet of ISO 6 (Class 1K) certified space. The work includes design, engineering, procurement, construction, testing, commissioning, and related closeout activities inside an existing warehouse in Sugar Land, Texas.

How much is Applied Optoelectronics (AAOI) spending on the FAB2 cleanroom contract?

The total contract amount for the FAB2 cleanroom project is approximately $30,885,000. This Contract Sum includes design, construction, and related professional services under the design-build agreement between Applied Optoelectronics and LCC3 Solution Inc., covering the full scope of the project’s development activities.

What incentives are included in AAOI’s FAB2 design-build agreement?

The agreement includes schedule-based incentives up to $1,810,000 for meeting key milestones on time. It also provides performance-based incentives of up to $1,724,000 tied to cleanroom validation testing and up to $1,600,000 linked to warranty performance, subject to specified conditions and determinations.

What liquidated damages apply if the AAOI FAB2 project is delayed?

The agreement provides for liquidated damages if specified key milestones or substantial completion are delayed, subject to contractual adjustments and conditions. These liquidated damages are capped in the aggregate at $1,600,000, giving a defined financial consequence for schedule slippage on the project.

When is Applied Optoelectronics’ FAB2 cleanroom targeted for substantial completion?

The FAB2 cleanroom project has a targeted Substantial Completion date of September 30, 2026. This target reflects when the major work should be finished such that the facility is sufficiently complete for its intended use, pending final acceptance and punch list completion.

How are payments structured under AAOI’s FAB2 design-build contract?

Payments are based on monthly progress pay applications submitted by the design-builder. The company withholds 10% retainage from each application, releasing this amount upon final completion, subject to final acceptance and completion of punch list items, with payments due within 15 days of proper submission.

Filing Exhibits & Attachments

25 documents
Applied Optoelec

NASDAQ:AAOI

View AAOI Stock Overview

AAOI Rankings

AAOI Latest News

AAOI Latest SEC Filings

AAOI Stock Data

9.06B
71.95M
Communication Equipment
Semiconductors & Related Devices
Link
United States
SUGAR LAND