EXHIBIT 99.1
Anfield Energy Files Its Updated Preliminary Economic Assessment
Which Reflects its Robust Hub-And-Spoke Uranium and Vanadium Production Strategy
VANCOUVER, British Columbia, June 18, 2026 (GLOBE NEWSWIRE) -- Anfield Energy Inc. (NASDAQ: AEC; TSX.V: AEC; FRANKFURT:
0AD) (“Anfield” or the “Company”), following its May 4th news release, is pleased to report that is
has filed its combined preliminary economic assessment (“PEA”) titled, “The Shootaring Canyon Mill and Tributary Mines,
Utah and Colorado, USA, Preliminary Economic Assessment” on SEDAR+. The PEA incorporates its Utah-based Velvet-Wood uranium and
vanadium project (“Velvet-Wood”), its Colorado-based Slick Rock uranium and vanadium project (“Slick Rock”) and
six of the nine mines which comprise the West Slope complex (“West Slope Mines”). These eight projects, being Velvet-Wood,
Slick Rock and the West Slope Mines, are located proximal to one another within the prolific Uravan Mineral Belt, and within close distance
of the Company’s Shootaring Canyon Mill (“Shootaring”) which will act as a centralized mineral processing facility in
the PEA. The PEA was prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI
43-101”).
Highlights include:
- The updated PEA indicates a pre-tax project internal rate of
return (“IRR”) of 106% and a net present value (“NPV”) of US$606 million (with a post-tax IRR of 97% and NPV of
$533 million), based on a discount rate of 8% and a uranium price of US$100 per pound, along with a vanadium price of US$9 per
pound, with an expected mine and mill capex payback period of 1.3 years.
- Average annual production of approximately 1.3 million pounds of uranium
(U3O8) and 6.4 million pounds of vanadium (V2O5) per year is estimated over the 15-year mine
life, including a peak production year of 1.9 million pounds of uranium and 7.8 million pounds of vanadium.
- The combined feed of the Velvet-Wood, Slick Rock and the West Slope
Mines is designed to meet the increased tonnage capacity at Shootaring of 1,000 tons per day.
- Estimated mill-related capital expenditures at Shootaring, including
20% contingency amount for each item, of: (1) US$31.1 million for general upgrades; (2) US$34.6 million to install a modern vanadium circuit;
and (3) US$14.4 million to update the tailings management facility, for a total of US$80.1 million.
- Estimated mine-related capital expenditures, including: (1) engineering
and design; (2) mine facilities; (3) mine equipment; (4) the reopening of the decline at Velvet and the sinking of a production shaft
at Wood; and (5) the sinking of two production shafts at Slick Rock, with a 10% contingency, of a combined total of US$37.5 million, partially
offset by expected cash flow of approximately $23.2 million related to initial uranium production from Anfield’s stockpiled material.
Anfield CEO, Corey Dias, stated, “Once again, we are very pleased with the outcome of this updated PEA as it
provides Anfield with strong further evidence of the true value of the combination of Velvet-Wood, Slick Rock and the West Slope mines
within Anfield’s uranium and vanadium hub-and-spoke production model.
Critically, the future potential addition of the Company’s thirteen remaining U.S. Department of Energy leases
(“DOE Leases”) to Anfield’s production model pipeline - which will require little incremental capital expenditure -
provides significant valuation upside, especially given that Shootaring’s restart costs will have already been borne by initial
production from the Velvet-Wood, Slick Rock and West Slope mines. Moreover, the prospect of our largest single uranium mine – Marquez-Juan
Tafoya – as an additional source of uranium could further extend the production timeline or provide an incentive to once again expand
throughput capacity at Shootaring.
The prospect of Shootaring becoming the second of only two operational conventional uranium and vanadium mills in the
United States is significant both economically as well as with respect to security of supply for utilities. This PEA not only represents
a significant milestone for Anfield but also outlines a technical and economic path towards commercial development of its core uranium
and vanadium assets. Finally, the Company is currently reviewing a number of other value-added techniques and technologies to facilitate
the reduction of waste in order to improve uranium and vanadium grades which can provide the Company with an opportunity to further improve
annual production output.
Anfield is well-positioned to benefit from an improving uranium market as nuclear energy becomes critically needed
for data centres in the U.S. and as nuclear energy becomes a more integral part of the global transition towards electrification.”
Project Economics
The PEA provides for a 12-month pre-production period. This includes the following capital expenditures, forecasted
at approximately US$97 million (including a 20% contingency): (1) initial mill and mine permitting and licensing; (2) an updated mining
and reclamation plan; (3) initiation of mine development; (4) completion of the construction of mine facilities and purchasing of equipment;
(5) refurbishment of the Shootaring uranium circuit and the construction of a vanadium circuit; and (6) the updating of the tailings waste
management facility. An additional US$20 million of mine-related expenditures will occur during the initial production year. The total
costs for “Life of Mine” is estimated at US$173 million, including sustaining capital.
The PEA indicates a pre-tax IRR of 106% at a uranium price of US$100 per pound and US$9 per pound of vanadium. The
pre-tax NPV of the project at an 8% discount rate at the aforementioned prices is US$606 million. The PEA also indicates a post-tax IRR
of 97% and a pre-tax NPV of $533 million.
Sensitivity to commodity prices
Changing the commodity price for uranium and vanadium equally by 10% varies the NPV@8% approximately +/- US$136 million
pre-tax, and +/- US$117 million post-tax. In both pre-tax and post-tax scenarios the IRR varies by approximately 20% with a 10% variation
in price.
Sensitivity to Commodity Price and Discount Rate

NPV: Sensitivity to Uranium Price

NPV: Sensitivity to Vanadium Price

Source: BRS
Shootaring Mill
The Shootaring area covers approximately 265 acres of surface ownership and approximately 905 acres of mineral leases.
Shootaring was licensed and constructed by Plateau Resources Limited and operated in 1982. U.S. Energy Corp. and Uranium
One Inc. were also previous owners of Shootaring. Shootaring has not been decommissioned and has been under care and maintenance since
cessation of operations. The mill license has been maintained and Anfield is currently conducting engineering and design studies for both
the refurbishment of Shootaring and tailings facility in support of converting the license from its status of care and maintenance to
operations.
Velvet-Wood
Velvet-Wood covers approximately 2,140 acres, including unpatented mining claims and a State of Utah mineral lease
related to the Velvet-Wood mine areas comprising Velvet-Wood.
Between 1979 and 1984, Atlas Minerals mined approximately 400,000 tons of ore from the Velvet deposit at grades of
0.46% U3O8 and 0.64% V2O5, recovering approximately 4.0 million pounds of U3O8
and 5.0 million pounds of V2O5.
The current mineral resources of the combined Velvet and Wood historical mines have been estimated to comprise 0.63
million tons containing 4.3 million pounds of eU3O8, at a grade of 0.34% eU3O8 (measured
and indicated mineral resource), and 80,000 tons containing 544,000 pounds of eU3O8, at a grade of 0.34% U3O8
(inferred mineral resource) with a vanadium-to-uranium ratio of 1.4 to 1.
Surface Stockpiles
In addition to the estimated mineral resource at Velvet-Wood, Anfield controls mineralized stockpiles from past mining
at two locations: (1) one stockpile at the Patty Ann mine area near the historic Velvet mine; and (2) several stockpiles near Shootaring.
The volumes and uranium content of the stockpiles were estimated from volumetric surveys and sampling conducted by BRS Inc. (“BRS”)
in March, 2015. The PEA includes the stockpiles located near Shootaring only. In total these stockpiles are estimated to contain approximately
77,500 tons of material at an average grade of 0.16% U3O8 and contain approximately 250,000 pounds of uranium.
Slick Rock
Slick Rock Complex is located in the Uravan Mineral Belt region of Colorado and covers approximately 6,130 acres, including
293 unpatented mining lodes claims, and two DOE Leases. The PEA estimates 0.8 million pounds of eU3O8, at a grade
of 0.16% eU3O8 (indicated mineral resource) and 2.25 million tons containing 9.1 million pounds at a grade
of 0.20% U3O8 (inferred mineral resource) with a vanadium-to-uranium-ratio of 6 to 1.
JD-6, JD-7, JD-8 and JD-9
The JD Mines, located in Colorado, represent four of the nine West Slope mines acquired from Cotter Corporation in
late 2018. The PEA estimates 4.6 million pounds of eU3O8, at a grade of 0.22% eU3O8 (indicated
mineral resource) with a vanadium-to-uranium-ratio of 5 to 1.
SR-11 and SM-18
The SR-11 and SM-18 mines, located in Colorado, represent two of the nine West Slope mines acquired from Cotter Corporation
in late 2018. The PEA estimates 0.16 million tons containing 0.7 million pounds at a grade of 0.24% U3O8 (inferred
mineral resource) with a vanadium-to-uranium-ratio of 6 to 1 for SR-11 and 0.18 million tons containing .7 million pounds at a grade of
0.21% U3O8 (inferred mineral resource) with a vanadium-to-uranium-ratio of 5 to 1 for SM-18. Please see resource
disclosure for both SR-11 and SM-18 in section titled Mineral Resource Estimate below.
Mineral Resource Estimate
The PEA is based on the mineral resource estimates set forth in the Company’s previous technical reports titled
“US DOE Uranium/Vanadium Leases JD-6, JD-7, JD-8 and JD-9, Montrose County, Colorado, USA, Mineral Resource Technical Report, National
Instrument 43-101” dated effective April 10, 2022 and “The Shootaring Canyon Mill and Velvet-Wood and Slick Rock Uranium Projects,
Preliminary Economic Assessment National Instrument 43-101” dated effective May 6, 2023. There has been no material change in such
mineral resource estimates for the Velvet-Wood, Slick Rock, Shootaring and the JD Mines. For the purpose of this PEA, the mineral resource
estimates were reviewed by the qualified persons under the PEA and deemed to remain valid and effective.
SR-11 Project Resource Estimate
The SR-11 Project is located approximately 8 miles southwest of the Slick Rock Complex and includes the SR-11 DOE Lease.
This lease was previously held and operated by Cotter Corporation into the Mid 2000s. This is the initial resource estimate for the property
performed by Anfield. The data set acquired from Cotter Corporation was validated using existing and available geophysical
logs. Drilling density would otherwise justify a higher resource classification. However, more field validation of historic drill hole
locations or new confirmatory drilling is needed to raise the classification above Inferred.
The existing data for SR-11 consists of 741 drill collars, of which 605 drill holes had associated grade and thickness
data. The 136 drill holes without data were limited to the margins of the SR-11 resource area and thus are considered by the authors to
have low impact on the data set overall. GT Contour modeling was performed using under the key assumptions described in the table below,
and was performed at 0.1ft%, 0.3ft% and 0.5 ft% eU3O8 GT cutoffs for sensitivity analysis. Nominal minimum thickness at the 0.4 ft% GT
cutoff is 4 feet. However, lower GT cutoffs would reduce the nominal mining thickness to closer 3ft. Meaning that Jack Leg, room and pillar
mining would likely dominate the method of extraction of the SR-11 resource.
The minimum sum GT contour resource model cutoff is the primary cutoff criteria applied to the contour model volume
as the initial screening of those portions of the model quantities not meeting the criteria for reasonable economic extraction. In addition,
individual model areas outside the conceptual mine limits not meeting a minimum of 10,000 lbs of eU3O8 resource were excluded from the
resource totals as not meeting a minimum expectation of reasonable economic extraction. It is the opinion of the authors of the PEA that
the resource models are reasonably valid within the mineral resource classifications assigned to each area of the complex.
A sensitivity analysis was performed on the mineral resource models for each zone as shown in the table below. The
authors recommend the 0.40 GT cutoff for the SR-11 Project. With further definition of the mineral resource via drilling and additional
mine design and cost evaluation, it is the authors’ opinion that the minimum GT cutoff may be lowered with appropriate adjustments
to mining methods made.
Inferred Mineral Resources Uranium, SR-11 Lease
| Zone
/ Classification |
GT
Cutoff (ft%) |
AVG.
Thickness (ft) |
AVG.
Grade (%eU3O8) |
Tons |
Pounds
(eU3O8) |
| SR-11
/ Total Inferred |
0.1 |
3.2 |
0.15 |
361,217 |
1,064,700 |
| 0.25 |
3.6 |
0.20 |
229,039 |
909,504 |
| 0.4 |
3.9 |
0.24 |
163,480 |
774,360 |
Mineral resources are not mineral reserves and do not have demonstrated economic viability in accordance with the Canadian
Institute of Mining, Metallurgy and Petroleum standards. At a minimum, a preliminary feasibility study is required to
demonstrate the economic viability of the measured and indicated mineral resources and qualify an initial estimate of mineral reserves.
The PEA is preliminary in nature such that it includes a portion of the inferred mineral resources. Inferred mineral resources
are too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral
reserves, and there is no certainty that the outcomes estimated in the PEA will be realized.
SM-18 Project Resource Estimate
The SM-18 Project within the SM-18 DOE Lease, located approximately 11 miles north of the Paradox Complex. This lease
was previously held and operated by Cotter Corporation into the Mid 2000s. This is the initial resource estimate for the property performed
by Anfield. The data set acquired from Cotter Corporation was validated using existing and available geophysical logs. Drilling
density would otherwise justify a higher resource classification. However, more field validation of historic drill hole locations or new
confirmatory drilling is needed to raise the classification above Inferred.
The existing data for SM-18 consists of 681 drill collars, of which 677 drill holes had associated grade and thickness
data. The 4 drill holes without data were limited to the margins of the SM-18 resource area and thus are considered by the authors of
the PEA to have low impact on the data set overall. GT Contour modeling was performed using the key assumptions described in the table
below, and was performed at 0.1ft%, 0.3ft% and 0.5 ft% eU3O8 GT cutoffs for sensitivity analysis. Nominal minimum thickness at the 0.4
ft% GT cutoff is 4 feet.
The minimum sum GT contour resource model cutoff is the primary cutoff criteria applied to the contour model
volume as the initial screening of those portions of the model quantities not meeting the criteria for reasonable economic extraction.
In addition, individual model areas outside the conceptual mine limits not meeting a minimum of 10,000 lbs of eU3O8 resource were excluded
from the resource totals as not meeting a minimum expectation of reasonable economic extraction. It is the opinion of the authors that
the resource models are reasonably valid within the mineral resource classifications assigned to each area of the complex.
A sensitivity analysis was performed on the mineral resource models for each zone as shown in the table below. The
authors recommend the 0.40 GT cutoff for the SR-11 Project. With further definition of the mineral resource via drilling and additional
mine design and cost evaluation, it is the authors’ opinion that the minimum GT cutoff may be lowered with appropriate adjustments
to mining methods made.
SM-18 Project Inferred Mineral Resource Estimates by GT Cutoff
| Zone |
GT
Cutoff (ft%) |
AVG.
Thickness (ft) |
AVG.
Grade (%eU3O8) |
Tons |
Pounds (eU3O8) |
| A |
0.1 |
3.2 |
0.112 |
574,325 |
1,286,280 |
| 0.25 |
4.1 |
0.152 |
325,058 |
985,779 |
| 0.4 |
4.2 |
0.211 |
178,965 |
755,367 |
| Total |
0.1 |
3.2 |
0.112 |
574,325 |
1,286,280 |
| 0.25 |
4.1 |
0.152 |
325,058 |
985,779 |
| 0.4 |
4.2 |
0.211 |
178,965 |
755,367 |
While no formal economic evaluation, preliminary economic assessment, preliminary feasibility study, or feasibility
study has been completed and while mineral resources are not mineral reserves and do not have demonstrated economic viability, reasonable
prospects for future economic extraction were applied to the mineral resource estimate herein through consideration of grade and GT cutoffs
and by screening out areas of isolated mineralization which would not support the cost of conventional mining under current and reasonably
foreseeable conditions.
NI 43-101 Disclosure
The combined PEA completed for Velvet-Wood, Slick Rock and the West Slope Mines, using centralized processing at Shootaring,
has been authored by Terence (Terry) McNulty, P.E., D. Sc., of T.P. McNulty and Associates Inc. and co-author Douglas L. Beahm, P.E. PG.
Dr. McNulty is independent of the issuer in accordance with the application of Section 1.5 of NI 43-101. Mr. Beahm is not independent
of the Company, as he is the Company’s Chief Operating Officer. The authors have reviewed and verified that the scientific
and technical content of this news release in respect of the PEA is accurate and approve the written disclosure of such information.
Additional scientific and technical information in this news release not specific to the PEA has been prepared under
the supervision of and approved by Douglas L. Beahm, P.E., P.G., a qualified person as defined by NI 43-101, and Mr. Beahm
has reviewed, verified and approved such scientific and technical information contained in this news release. No limitations
or failures to verify were identified. Mr. Beahm is not independent of the Company, as he is the Company’s Chief Operating
Officer.
Results of the PEA represent forward-looking information. The PEA is preliminary in nature and it includes inferred
mineral resources that are considered too speculative, geologically, to have the economic considerations applied to them that would enable
them to be categorized as mineral reserves. There is no certainty that the PEA will be realized. There is no guarantee that inferred mineral
resource estimates will be converted to indicated or measured mineral resources, or that indicated or measured mineral resources can be
converted to mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability, and as such
there is no guarantee the project economics described herein will be achieved. Mineral resource estimates may be materially affected by
environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant risks, uncertainties and other factors,
as more particularly described herein and to be described in the technical report in respect of the PEA.
Further information about the PEA referenced in this news release, including information in respect of data verification,
key assumptions, parameters, risks and other factors, is contained in the technical report. Readers are encouraged to read the technical
report in its entirety, including all qualifications, assumptions and exclusions that relate to the PEA. The technical report is intended
to be read as a whole, and sections should not be read or relied upon out of context.
Non-IFRS Financial Measures
The Company has included certain non-IFRS financial measures in this news release, such as sustaining capital, which
is not a measure recognized under IFRS and does not have a standardized meaning prescribed by IFRS. As a result, this measure may not
be comparable to similar measures reported by other companies. This measure used is intended to provide additional information to the
reader and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS. The non-IFRS financial
measure used in this news release is defined below.
Sustaining Capital is a supplementary financial measure and defined as cash-basis expenditures which maintain operations
and sustain production levels.
The projects that are subject of this news release do not currently have operations and therefore do not have historical
equivalent measures to compare to. As such, the Company cannot perform a reconciliation of this non-IFRS measure.
About Anfield
Anfield is a uranium and vanadium development company that is committed to becoming a top-tier energy-related
fuels supplier by creating value through sustainable, efficient growth in its assets. Anfield is a publicly traded corporation
listed on the NASDAQ (AEC-Q), the TSXV (AEC-V) and the Frankfurt Stock Exchange (0AD).
On behalf of the Board of Directors
ANFIELD ENERGY INC.
Corey Dias, Chief Executive Officer
Neither the TSXV nor its Regulation Services Provider (as that term is defined in policies of the TSXV) accepts responsibility
for the adequacy or accuracy of this release.
Contact:
Anfield Energy, Inc.
Corporate Communications
604-669-5762
contact@anfieldenergy.com
www.anfieldenergy.com
This news release contains forward-looking statements and forward-looking information (together, “forward-looking
statements”) within the meaning of applicable Canadian securities laws. All statements, other than statements of historical facts,
are forward-looking statements. Generally, forward-looking statements can be identified by the use of terminology such as “plans”,
“expects”, “estimates”, “intends”, “anticipates”, “believes” or variations
of such words, or statements that certain actions, events or results “may”, “could”, “would”, “might”,
“occur” or “be achieved”. Forward-looking statements in this release include, but are not limited to, statements
regarding the development, operational and economic results of the PEA, including capital expenditures, NPV projections, IRR projections,
development costs and sustaining capital; the plans for Shootaring to serve as a centralized mineral processing facility; estimation of
future production; the potential of Velvet-Wood, Slick Rock, JD-7 and JD-8 within the Company’s uranium and vanadium hub-and-spoke
production model; the potential addition of the Company’s 13 remaining DOE Leases to the Company’s production model pipeline
and the expected capital expenditures needed; the Company’s plan to secure increased throughput capacity and production output at
Shootaring; the potential of the Marquez-Juan Tafoya mine as an additional source of uranium to further extend the production timeline;
the prospect of Shootaring becoming the next operational conventional uranium and vanadium mill in the United States and the benefits
therefrom; the commercial development of the Company’s core uranium and vanadium assets; the Company’s usage of value-added
techniques and technology to reduce waste in order to improve uranium and vanadium grades and further improve annual production output;
the uranium market and the trend of nuclear energy becoming integral to the global transition towards electrification and the expected
benefits therefrom; the conversion of the Shootaring license from its status of care and maintenance to operations and the economics and
viability of development of Velvet-Wood, Slick Rock and the West Slope Mines.
Forward-looking statements involve risks, uncertainties and other factors that could cause actual results, performance
and opportunities to differ materially from those implied by such forward-looking statements. Factors that could cause actual results
to differ materially from these forward-looking statements include, among other things: risks that the technical report may not be completed
as contemplated, or at all; risks that the development, operational and economic results of the PEA may differ from projections; risks
that the potential of Velvet-Wood, Slick Rock, JD-7 and JD-8 within the Company’s uranium and vanadium hub-and-spoke production
model may not be realized as contemplated, or at all; risks that the Company may not add its 13 remaining DOE Leases to the Company’s
production model pipeline as contemplated, or at all; risks that the expected capital expenditures needed to add the 13 DOE Leases to
the production model pipeline may vary from current expectations; risks that the Company may not be able to secure increased throughput
capacity and production output at Shootaring as contemplated, or at all; risks that the potential of the Marquez-Juan Tafoya mine as an
additional source of uranium to further extend the production timeline may not be realized as contemplated, or at all; risks that the
Shootaring may not become an operational conventional uranium and vanadium mill in the United States as contemplated, or at all; risks
that the commercial development of the Company’s core uranium and vanadium assets may not be completed as contemplated, or at all;
risks that the anticipated benefits of the Company’s usage of value-added techniques and technology to reduce waste in order to
improve uranium and vanadium grades may not be realized as contemplated, or at all; risks related to the global uranium market; risks
that nuclear energy may not become integral to the global transition towards electrification as contemplated; risks that the Company may
not successfully convert the status of the mill license for Shootaring from care and maintenance to operations as contemplated, or at
all; risks related to the economics and viability of development of Velvet-Wood, Slick Rock and West Slope Mines; the risks and uncertainties
relating to exploration and development; the ability of the Company to obtain additional financing; the need to comply with environmental
and governmental regulations in Canada and the United States; fluctuations in the prices of commodities; operating hazards and risks;
competition and other risks and uncertainties and other such factors as are set forth in the annual information form for the Company’s
most recently completed year end, as well as the management discussion and analysis and other disclosures of risk factors for the Company,
filed on SEDAR+ at www.sedarplus.ca.
Although the Company believes that the information and assumptions used in preparing the forward-looking statements
are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this news release, and no
assurance can be given that such events will occur in the disclosed time frames or at all. Except where required by applicable law, the
Company disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information,
future events or otherwise.
A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/3d376b10-e62e-45b7-9129-32f049d405b6