STOCK TITAN

Fervo Energy (FRVO) widens Q2 loss but raises $2.2B in IPO

(Moderate)
(Neutral)
Form Type
8-K

Rhea-AI Filing Summary

Fervo Energy Company reported second-quarter 2026 results highlighting its transition to a capitalized growth phase following its Nasdaq IPO. The company completed an upsized initial public offering in May 2026, raising approximately $2.2 billion in gross proceeds, and ended June 30, 2026 with $2.11 billion in cash and cash equivalents and total assets of $3.54 billion.

For Q2 2026, Fervo generated $113 thousand of revenue, recorded an operating loss of $28.7 million and a net loss of $55.9 million, driven largely by higher general and administrative expenses and other non-operating expense. Capital expenditures were $226.5 million in Q2 2026 versus $108.0 million a year earlier, reflecting accelerated investment at its Cape Station project and broader development pipeline; total capex of $850–900 million is expected in the second half of 2026.

Operationally, Fervo advanced Cape Station Phase I (around 100 MW across three GeoBlocks) toward first power in late 2026 and continued development of Phase II (400 MW targeted for 2028). The company increased its long-term development target to 1.1 GW by 2030 and reported a development pipeline of more than 50 GW, supported by record drilling performance and expansion of its GeoCluster portfolio.

Positive

  • $2.2 billion IPO proceeds significantly strengthen liquidity, supporting Fervo’s plan to place over a gigawatt of capacity online by decade’s end.
  • Cash and cash equivalents of $2.11 billion at June 30, 2026 provide a substantial buffer to fund large-scale capex and development activities.
  • Stockholders’ equity improved from a $(246.5) million deficit at December 31, 2025 to positive $2.79 billion at June 30, 2026, materially reinforcing the balance sheet.
  • Long-term development target increased to 1.1 GW by 2030, with a development pipeline exceeding 50 GW, indicating sizable future project optionality.
  • Cape Station Phase I neared commissioning with GeoBlocks 1 and 2 mechanically complete and Phase II (400 MW) advancing toward a targeted 2028 delivery.
  • The $421 million non-recourse project debt for Cape Station Phase I enabled repayment and termination of the prior XRC Facility, optimizing project-level financing.

Negative

  • Q2 2026 net loss widened to $55.9 million from $11.4 million a year earlier, reflecting higher expenses and other non-operating losses.
  • Q2 2026 capital expenditures of $226.5 million, up from $108.0 million in Q2 2025, and expected H2 2026 capex of $850–900 million imply heavy near-term cash outflows.
  • General and administrative expense rose to $27.4 million in Q2 2026 from $9.5 million in Q2 2025, indicating a substantially higher cost base.
  • Other non-operating expense, net, was $35.5 million in Q2 2026 and $47.4 million for the first half, materially increasing loss before taxes.
  • Despite new revenues of $113 thousand in Q2 2026, the business remains at an early revenue stage relative to its growing expense profile.

Filing Explained

Fervo terminated the XRC borrowing after repayment; its May 14 reverse split changed share count without changing value by itself.

Fervo reports that it repaid all outstanding borrowings under the XRC Facility using proceeds from the Project Granite Facility and terminated the XRC Facility, so that specific borrowing arrangement is complete rather than still outstanding.

The filing also states that a May 14, 2026 0.7194-for-1 reverse stock split was effected for the IPO. The split reduced the share count and proportionally raised the per-share price; the split itself does not change company value.

Item 2.02 Results of Operations and Financial Condition Financial
Disclosure of earnings results, typically an earnings press release or preliminary financials.
Item 7.01 Regulation FD Disclosure Disclosure
Material non-public information disclosed under Regulation Fair Disclosure, often investor presentations or guidance.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, and exhibit attachments filed with this report.
Q2 2026 Revenue $113 thousand Revenues for the three months ended June 30, 2026
Q2 2026 Operating Loss $28.7 million Operating loss for the three months ended June 30, 2026
Q2 2026 Net Loss $55.9 million Net loss for the three months ended June 30, 2026
Q2 2026 Capital Expenditures $226.5 million Capital expenditures in Q2 2026 vs $108.0 million in Q2 2025
H2 2026 Capex Guidance $850.0–$900.0 million Expected total capital expenditures in the second half of 2026
IPO Gross Proceeds $2.2 billion Gross proceeds from the upsized initial public offering in May 2026
Cash and Cash Equivalents $2,106,371 thousand Cash and cash equivalents as of June 30, 2026
Development Target 2030 1.1 gigawatts Long-term development target by 2030 after 100 MW increase
Development Pipeline More than 50 gigawatts Total development pipeline as of quarter-end
Non-recourse Project Debt $421 million Project Granite Facility for Cape Station Phase I closed in Q1 2026
GeoBlock technical
"Cape Station Phase I is an approximately 100-megawatt installation comprising three 33-megawatt GeoBlocks."
GeoCluster technical
"two new GeoClusters into Early Development"
behind-the-meter technical
"pursuing behind-the-meter delivery pathways in addition to conventional grid-delivered power"
Equipment or systems located on a customer’s side of the electricity meter—such as rooftop solar panels, battery storage, electric vehicle chargers, or energy controls—that generate, store, or manage power for use on-site rather than being supplied through the utility’s grid. Investors care because behind-the-meter assets change how much power a customer buys, can create new revenue or savings streams, affect demand patterns, and shift regulatory or business models in the energy market, much like a homeowner installing their own water tank reduces municipal supply needs.
non-recourse project debt financial
"the $421 million non-recourse project debt financing for the first phase of Cape Station"
redeemable noncontrolling interest financial
"Cape Phase I HoldCo - Redeemable noncontrolling interest"
A redeemable noncontrolling interest is a minority ownership stake in a business that the minority owner can require to be bought back for cash or that must be redeemed under set conditions. Investors care because it is not permanent equity: it represents a foreseeable cash obligation and can reduce the parent company’s reported equity and available cash, much like a loan from a roommate you must repay on request rather than shared ownership of the house.
reverse stock split financial
"retroactively adjusted to reflect the 0.7194-for-1 reverse stock split effected on May 14, 2026"
A reverse stock split reduces a company's number of outstanding shares while raising the price per share proportionally, so the total value of each investor's holding is unchanged; a 1-for-10 split turns 100 shares worth $1 each into 10 shares worth $10 each. Companies often do this to regain compliance with an exchange's minimum price rule or to attract investors who avoid very low-priced stocks.
Revenue $113 thousand (Q2 2026); $174 thousand (H1 2026) Increased from zero in the comparable 2025 periods
Operating Loss $28.7 million (Q2 2026); $48.8 million (H1 2026) Higher than the prior-year operating losses
Net Loss $55.9 million (Q2 2026); $87.7 million (H1 2026) Wider than net losses in the 2025 periods
Capital Expenditures $226.5 million (Q2 2026) Up from $108.0 million in Q2 2025
Guidance

Total capital expenditures of approximately $850.0 to $900.0 million expected in the second half of 2026.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

FAQ

How did Fervo Energy (FRVO) perform financially in Q2 2026?

Fervo Energy reported an operating loss of $28.7 million and a net loss of $55.9 million in Q2 2026 on $113 thousand of revenue. Higher general and administrative and non-operating expenses contributed to the wider loss versus the prior year.

How much cash did Fervo Energy (FRVO) have at June 30, 2026?

At June 30, 2026, Fervo Energy held $2.11 billion in cash and cash equivalents, up from $461.8 million at year-end 2025. Total assets reached $3.54 billion, reflecting IPO proceeds and increased construction-in-process at Cape Station.

What capital expenditures did Fervo Energy (FRVO) report and guide for 2026?

Fervo recorded $226.5 million in capital expenditures in Q2 2026, compared with $108.0 million in Q2 2025. It expects $850–900 million of capex in the second half of 2026, mainly for Cape Station construction and broader pipeline development.

What are Fervo Energy’s (FRVO) growth and capacity targets?

Fervo increased its long-term development target to 1.1 GW by 2030, a 100 MW increase. Its development pipeline exceeds 50 GW, supported by additional GeoClusters totaling 10.5 GW entering Early Development and advancing GeoBlocks into Advanced Development.

What progress did Fervo Energy (FRVO) report at Cape Station?

Cape Station Phase I, an approximately 100 MW project, achieved mechanical completion on GeoBlocks 1 and 2, with first test power from GeoBlock 1 targeted for Q4 2026. Phase II, totaling 400 MW, continues toward a planned 2028 online date.

What was the impact of Fervo Energy’s (FRVO) IPO in 2026?

In May 2026, Fervo completed an upsized IPO, raising approximately $2.2 billion in gross proceeds. The transaction shifted stockholders’ equity from a $(246.5) million deficit at year-end 2025 to positive $2.79 billion by June 30, 2026.

How is Fervo Energy (FRVO) financing Cape Station Phase I?

Fervo closed a $421 million non-recourse project debt facility for Cape Station Phase I in Q1 2026 and used its proceeds to repay all borrowings under the XRC Facility, which was then terminated, aligning financing directly with the project.
0001853868false00018538682026-08-122026-08-12

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
___________
FORM 8-K

CURRENT REPORT
Pursuant to Section 13 or 15(d) of the
Securities Exchange Act of 1934

Date of report (Date of earliest event reported): August 12, 2026
___________
FERVO ENERGY COMPANY
(Exact Name of Registrant as Specified in Charter)
DE001-4328582-3168838
(State or other jurisdiction of incorporation)(Commission File Number)(I.R.S. Employer Identification No.)
811 Main Street
Suite 1700
Houston,TX77002
(Address of principal
executive offices)
(Zip Code)
(832) 554-3253
(Registrant's telephone number, including area code)

Not Applicable
(Former name or former address, if changed since last report)

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

Securities registered pursuant to Section 12(b) of the Act:
Title of each classTrading Symbol(s)Name of each exchange on which registered
Common Stock, par value $0.0001 per shareFRVOThe Nasdaq Stock Market LLC
(NASDAQ Global Select Market)

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).

Emerging growth company




If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act.   



Item 2.02. Results of Operations and Financial Condition.

On August 12, 2026, Fervo Energy Company (the “Company”) issued a press release announcing financial and operating results for the second quarter ended June 30, 2026 (the “earnings release”). A copy of the earnings release is furnished to the Securities and Exchange Commission (the “SEC”) as Exhibit 99.1 to this Current Report on Form 8-K.

The information contained in this Item 2.02 and the earnings release shall be considered “furnished” and shall not be deemed “filed” for purposes of Section 18 of the Securities Exchange Act of 1934, as amended, or otherwise subject to the liabilities of that Section or Sections 11 and 12(a)(2) of the Securities Act of 1933, as amended, nor shall it be deemed incorporated by reference into any reports or filings with the SEC, whether made before or after the date hereof, except as expressly set forth by specific reference in such a filing.

Item 7.01. Regulation FD Disclosure.

The Company uses any of the following to comply with its disclosure obligations under Regulation FD: press releases, SEC filings, public conference calls, or the Company’s website. The Company routinely posts important information on its website (https://fervoenergy.com), including information that may be deemed to be material. The Company encourages investors and others interested in the Company to monitor these distribution channels for material disclosures. The information posted on the Company’s website is not incorporated by reference into this Current Report on Form 8-K or in any other report or document the Company files with the SEC.

Item 9.01. Financial Statements and Exhibits.

(d) Exhibits
  
Exhibit NumberDescription
99.1
Press Release of the Company, dated August 12, 2026.
104Cover Page Interactive Data File (formatted as inline XBRL and contained in Exhibit 101).



SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
FERVO ENERGY COMPANY
Date:August 12, 2026
By:/s/ David Ulrey
Name:David Ulrey
Title:Chief Financial Officer



fervologoa.jpg
Fervo Energy Company
811 Main St, 1700
Houston, TX 77002
Fervo Energy Reports Second Quarter 2026 Results
Houston, TX - August 12, 2026 - Fervo Energy Company (“Fervo” or the “Company”) (NASDAQ: FRVO), the
global pioneer of next-generation geothermal energy, today reported financial and operational results for the
second quarter ended June 30, 2026.
"Fervo continues to demonstrate the power of enhanced geothermal at scale," said Tim Latimer, CEO and Co-
founder of Fervo. "We believe that demand for firm, carbon-free power has never been stronger, and our
commercial pipeline reflects that - we're converting our extensive resource portfolio into shovel-ready capacity
quarter after quarter. Alongside that growth, commissioning at Cape Station Phase I, record-setting drilling at
Phase II, and continued derisking of our pipeline all bring Fervo closer to the goal of making geothermal the
world's cheapest, most reliable form of power."
BUSINESS AND OPERATIONAL HIGHLIGHTS
Continued to see strong growth in power demand across all categories of buyers, with behind-the-meter
capabilities playing a growing role in meeting that demand outside conventional grid interconnection
timelines.
Raised its long-term development target to 1.1 gigawatts by 2030 - a 100-megawatt increase - as commercial
and technical confidence in the Company's pipeline continues to build.
Advanced Cape Station Phase I toward commercial operation, achieving mechanical completion on
GeoBlocks 1 and 2 and progressing commissioning, with GeoBlock 3 mechanical completion expected in the
coming months. GeoBlock 1 first power is targeted for the fourth quarter of 2026, with full production
anticipated by year-end; GeoBlocks 2 and 3 are expected to reach initial power in early 2027.
Set a new company drilling record with Sawtooth 7 - the ninth Fervo 3.0 well and most complex well design
to date - reaching a measured depth of nearly 19,500 feet in a 460°F resource with a spud-to-total-depth of
just 21 days.
Progressed Cape Station's second phase of development, with eight GeoBlocks slated to come online in 2028,
and added a third Helmerich & Payne rig in line with the Phase II development plan.
Accelerated pipeline maturation, moving eight GeoBlocks (400 megawatts) into Advanced Development
while advancing 10.5 gigawatts of capacity potential across two new GeoClusters into Early Development.
FINANCIAL HIGHLIGHTS
Marked its debut as a public company in the second quarter of 2026, completing its IPO and raising
approximately $2.2 billion in gross proceeds.
Reported Q2 2026 operating loss of $28.7 million and net loss of $55.9 million.
Reported Q2 2026 capital expenditures of $226.5 million, compared to $108.0 million in Q2 2025, reflecting
continued investment in Cape Station development and construction activities.
Expect total capital expenditures of approximately $850.0 to $900.0 million in the second half of 2026, in line
with previously disclosed expectations, reflecting continued construction activity at Cape Station as well as
broader pipeline development activities, including long-lead procurement and appraisal work across the
Company's GeoCluster portfolio.
BUSINESS UPDATES
Commercial
Fervo continues to see robust commercial demand for firm, carbon-free power, driven by the scale of AI and data
center build-out, the re-shoring of domestic manufacturing, and broader electrification straining existing grid
capacity. Buyers across categories – utilities, industrial offtakers, and hyperscale data center developers –
continue to seek out Fervo's 24/7 geothermal power as a differentiated solution to that demand, and the
Company's commercial pipeline reflects that momentum.
As part of its GeoCluster approach to AI data center development, Fervo is pursuing behind-the-meter delivery
pathways in addition to conventional grid-delivered power purchase agreements - structures under which the
Company delivers baseload power directly to a customer's on-site load, alongside ancillary energy systems
developed by others, rather than through the grid. Fervo believes that behind-the-meter developments will serve
as a critical bridge for customers that urgently need power sooner than the grid can provide, and that these
developments will be connected to the grid over time.
Construction
Cape Station Phase I is an approximately 100-megawatt installation comprising three 33-megawatt GeoBlocks.
Fervo has achieved mechanical completion on GeoBlocks 1 and 2, with mechanical completion of GeoBlock 3
expected over the coming months. Commissioning on GeoBlock 1 continued throughout the quarter with the first
set of wells having been connected to the power plant, moving geothermal brine through the heat exchangers and
spinning the turbines. Fervo expects to begin generating test power at GeoBlock 1 in the fourth quarter of 2026,
with full production anticipated by year-end. GeoBlocks 2 and 3 are expected to follow a similar sequence, with
initial power in early 2027 ramping to full power over the ensuing months.
Fervo's second phase of development at Cape Station, 400 megawatts across eight 50-megawatt GeoBlocks,
continues to advance toward its 2028 delivery date, building on the lessons of Phase I. This expansion
incorporates the Company's 3.0 well design, with longer laterals and larger-diameter casing than Phase I,
engineered to increase power output per well while reducing installed cost per kilowatt. During the quarter, Fervo
drilled Sawtooth 7, its ninth Fervo 3.0 well, reaching a measured depth of nearly 19,500 feet in a 460°F resource
in just 21 days spud-to-total-depth, a new Company record for drilling pace on its most complex well design to
date.
The drilling performance of the Sawtooth 7 well, combined with its design and resource temperature, underpins
Fervo's confidence in its cost trajectory. Based on progress to date, Fervo continues to expect Phase II to achieve
an all-in cost of $5,500 per kilowatt, a key step toward its long-term target of $3,000 per kilowatt.
Portfolio
Fervo's development pipeline, which totaled more than 50 gigawatts as of quarter-end, continued to advance
during the second quarter. Approximately 400 megawatts moved from Early Development into Advanced
Development, driven by progress at one of the Company's leading prospects, where Fervo completed geological
surveys, secured appraisal permits, initiated origination activities, and submitted an interconnection queue
application. Separately, two additional GeoClusters totaling 10.5 gigawatts of capacity potential entered Early
Development, following newly completed heat-initially-in-place studies by independent engineering firm
DeGolyer and MacNaughton. Fervo also anticipates beginning an appraisal drilling program in Q4 2026.
Fervo's current land portfolio spans over 650,000 acres.
Financing
In May 2026, Fervo completed its initial public offering (IPO) and listed on Nasdaq. The IPO was significantly
upsized and priced well above the initial range, resulting in gross proceeds of approximately $2.2 billion,
including the full exercise of the underwriters' over-allotment option. The IPO allows Fervo to accelerate its
strategic priorities, as the Company prepares to place over a gigawatt of capacity online by the end of the decade.
Earlier in the quarter, Fervo repaid all outstanding borrowings under the loan agreements with XRL ALC, LLC
(the “XRC Facility”) using proceeds from the Project Granite Facility, the $421 million non-recourse project debt
financing for the first phase of Cape Station that Fervo closed in Q1 2026, and the XRC Facility was terminated.
CONFERENCE CALL
Fervo will host a conference call to discuss its second quarter 2026 business, operational and financial highlights
at 10:00 a.m. ET (9:00 a.m. CT) today, August 12, 2026. A live webcast of the conference call will be available in
the “Events” section of the Company’s investor relations website at ir.fervoenergy.com. A replay of the call will
be available shortly after the live webcast’s conclusion.
ABOUT FERVO
Fervo Energy (NASDAQ: FRVO) is a modern power company built around one of the market’s most important
needs: affordable, dependable new power supply. Through the large-scale deployment of enhanced geothermal
systems, Fervo has established a repeatable, industrial approach to building utility-scale power. The Company is
transforming geothermal into a clean, reliable, cost-competitive solution designed to meet rising demand from AI
hyperscalers, utilities, and a more electricity-intensive economy. For more information, visit
www.fervoenergy.com
FORWARD-LOOKING STATEMENTS
This press release contains “forward-looking statements” within the meaning of Section 27A of the Securities Act
and Section 21E of the Exchange Act, which involve risks, uncertainties, and assumptions. All statements, other
than statements of historical fact, are forward-looking statements. When used in this press release, the words
“aim,” “anticipate,” “believe,” “continue,” “could,” “estimate,” “expect,” “forecast,” “future,” “guidance,”
“intend,” “may,” “model,” “outlook,” “plan,” “positioned,” “potential,” “predict,” “project,” “seek,” “should,”
“target,” “will,” “would,” and similar expressions (including the negative of such terms) are intended to identify
forward-looking statements, although not all forward-looking statements contain such identifying words.
Although Fervo believes that the expectations and assumptions reflected in its forward-looking statements are
reasonable as and when made, they involve risks and uncertainties that are difficult to predict and, in many cases,
beyond Fervo’s control. Accordingly, forward-looking statements are not guarantees of future performance, and
Fervo’s actual outcomes could differ materially from what Fervo has expressed in its forward-looking statements.
Factors that could cause the outcomes to differ materially include (but are not limited to) the following: risks
related to expanding our geothermal operations and accessing new markets; challenges in maintaining compliance
with extensive environmental regulations and permitting requirements; uncertainties in forecasting future
operational results and growth due to economic conditions and market demand; compliance with environmental
regulations and climate change initiatives impacting operational costs; inherent risks in the geothermal industry,
including potential operational disruptions and associated liabilities; the influence of consumer preferences,
government policies, and competition on the demand for geothermal energy; risks associated with fluctuations in
energy prices and material costs; dependence on a complex supply chain and successful maintenance of our
geothermal infrastructure; financial performance influenced by fluctuations in interest rates, capital availability,
and other market conditions; capacity actually constructed or for which we enter power purchase agreements
under non-binding agreements, like the Geothermal Framework Agreement; exposure to legal proceedings and
claims arising from our business operations; protecting our brand reputation and facing potential negative public
perception; negative public perception and political opposition impacting our ability to secure regulatory
approvals and market acceptance; the successful and timely execution of our growth strategy, with risks of delays
or failures; reliance on key personnel and the potential impact of labor costs and workforce challenges; heavy
reliance on technology systems and potential cybersecurity threats; global economic and political conditions
affecting our operations, supply chain, and customer demand; the risk that our estimates of capacity potential and
heat initially in place are inaccurate or that we are unable to produce quantities of electrical energy commensurate
with such estimates; and other risks and uncertainties, including those set forth under “Risk Factors” in Fervo’s
Registration Statement on Form S-1/A, filed with the Securities and Exchange Commission (the “SEC”) on May
11, 2026, and Fervo’s other filings with the SEC.
In light of these factors, the events anticipated by Fervo’s forward-looking statements may not occur at the time
anticipated or at all. Moreover, Fervo operates in a very competitive and rapidly changing environment, and new
risks emerge from time to time. Fervo cannot predict all risks, nor can it assess the impact of all factors on its
business or the extent to which any factor, or combination of factors, may cause actual results to differ materially
from those anticipated by any forward-looking statements it may make. Accordingly, you should not place undue
reliance on any forward-looking statements. All forward-looking statements speak only as of the date of this press
release or, if earlier, as of the date they were made. Fervo does not intend to, and disclaims any obligation to,
update or revise any forward-looking statements unless required by applicable law.
CONDENSED CONSOLIDATED STATEMENTS OF OPERATIONS (UNAUDITED)
(Dollars and shares in thousands except per share amounts)
Three Months Ended June 30,
Six Months Ended June 30,
2026
2025
2026
2025
Revenues ..........................................................................
$113
$
$174
$
Costs and expenses:
Operation and maintenance .........................................
306
158
788
410
Research and development (income) expense, net .......
(712)
395
(784)
359
General and administrative expense .............................
27,427
9,484
44,417
17,163
Operating lease expense ...............................................
1,490
205
4,110
2,194
Depreciation and amortization ......................................
344
56
437
103
Operating loss ..............................................................
(28,742)
(10,298)
(48,794)
(20,229)
Other income (expense):
Interest income ...............................................................
10,521
601
13,336
2,629
Interest expense ..............................................................
(2,215)
(1,739)
(4,932)
(2,966)
Other non-operating expense, net ...................................
(35,478)
(47,354)
(16)
Loss before income taxes ..................................................
(55,914)
(11,436)
(87,744)
(20,582)
Income tax expense ...........................................................
(1)
(2)
(1)
(2)
Net loss ...........................................................................
$(55,915)
$(11,438)
$(87,745)
$(20,584)
Net loss per share information: .......................................
Net loss ........................................................................
$(55,915)
$(11,438)
$(87,745)
$(20,584)
Less: Remeasurement of redeemable noncontrolling
interest ..........................................................................
(3,612)
(189)
(7,046)
(189)
Net loss attributable to common stock, basic and
diluted ..........................................................................
(59,527)
(11,627)
(94,791)
(20,773)
Weighted average common stock, basic and
diluted (1) ...................................................................
157,003
8,844
83,643
8,902
Net loss per share attributable to common
stockholders, basic and diluted (1) .............................
$(0.38)
$(1.31)
$(1.13)
$(2.33)
(1) Shares for periods presented have been retroactively adjusted to reflect the 0.7194-for-1 reverse stock split effected on May 14, 2026 in connection with
the Company’s IPO. See Note 1 – Nature of Business and Note 2 – Significant Accounting Policies in the notes to condensed consolidated financial
statements for details.
CONDENSED CONSOLIDATED BALANCE SHEETS (UNAUDITED)
(Dollars and shares in thousands)
As of June 30,
As of December 31,
2026
2025
ASSETS
Current assets:
Cash and cash equivalents ....................................................................................................
$2,106,371
$461,836
Grant receivables ..................................................................................................................
17,177
10,580
Prepaid expenses and other ..................................................................................................
30,634
9,714
Total current assets ..........................................................................................................
2,154,182
482,130
Deposits ................................................................................................................................
12,602
15,234
Construction-in-process .......................................................................................................
1,235,160
789,571
Operating leases right-of-use assets .....................................................................................
88,667
58,713
Restricted cash ......................................................................................................................
11,000
6,000
Other long-term assets ...........................................................................................................
33,478
13,520
Total assets ......................................................................................................................
$3,535,089
$1,365,168
LIABILITIES AND EQUITY
Current liabilities:
Accounts payable .....................................................................................................................
$29,667
$10,789
Accrued capital expenditures ...................................................................................................
173,961
119,303
Current portion of long-term debt ............................................................................................
11,042
Operating lease liabilities .......................................................................................................
24,744
4,822
Other current liabilities ...........................................................................................................
10,614
16,997
Total current liabilities .......................................................................................................
250,028
151,911
Long-term debt, net of issuance costs and current portion ......................................................
217,376
172,837
Operating lease liabilities .......................................................................................................
85,123
72,639
Other long-term liabilities .......................................................................................................
1,749
11,407
Total liabilities ................................................................................................................
554,276
408,794
Commitments and Contingencies (Note 19) ............................................................................
Mezzanine equity
Redeemable convertible preferred stock, par value $0.0001 per share; 0 and 283,546
authorized; 0 and 279,995 issued and outstanding as of June 30, 2026 and December 31, 2025 ...
1,022,942
Redeemable noncontrolling interest
Cape Phase I HoldCo - Redeemable noncontrolling interest ................................................
105,118
102,586
Cape Phase I Intermediate HoldCo - Redeemable noncontrolling interest ...........................
81,858
77,344
Stockholders’ equity (deficit):
Common stock, par value $0.0001 per share; 0 and 358,279 authorized; 0 and 9,457 issued
as of June 30, 2026 and December 31, 2025, respectively(1) ...............................................
1
Class A common stock, par value $0.0001 per share; 1,000,000 and 0 authorized; 286,869
and 0 issued as of June 30, 2026 and December 31, 2025, respectively .............................
29
Class B common stock, par value $0.0001 per share; 40,000 and 0 authorized; 7,785 and 0
issued as of June 30, 2026 and December 31, 2025, respectively .......................................
1
Additional paid-in capital
3,126,084
Treasury stock, at cost; 0 shares and 270 shares as of June 30, 2026 and December 31,
2025, respectively(1) .................................................................................................................
(1,960)
Accumulated deficit ................................................................................................................
(332,277)
(244,539)
Total stockholders’ equity (deficit) .......................................................................................
2,793,837
(246,498)
Total liabilities, mezzanine equity, and stockholders’ equity (deficit) ............................
$3,535,089
$1,365,168
(1) Shares for periods presented have been retroactively adjusted to reflect the 0.7194-for-1 reverse stock split effected on May 14, 2026 in connection with
the Company’s initial public offering (“IPO”). See Note 1 – Nature of Business and Note 2 – Significant Accounting Policies for details.
CONTACTS
Investor Relations
investor.relations@fervoenergy.com
ICR, Inc.
Fervo@icrinc.com
V2 Communications for Fervo Energy
fervo@v2comms.com

Filing Exhibits & Attachments

4 documents