Brazil Potash (NYSE: GRO) completes full FEED coverage for Autazes project

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Brazil Potash Corp. has awarded a second Front-End Engineering Design (FEED) contract for the Autazes potash project’s mine shafts and underground development to WSP UK Ltd., with Redpath Deilmann Mining Inc. as subconsultants. This, together with earlier FEED awards to Wood and Promon Engenharia for surface facilities and infrastructure, means the entire Autazes Project now has dedicated FEED coverage. The FEED work is described as a critical step toward securing construction debt financing by giving lenders detailed engineering documentation for due diligence.

The FEED contract has an estimated total value of USD 26 million, with the first 12‑month Early Works phase awarded at USD 4.3 million. Brazil Potash plans initial annual potash production of up to 2.4 million tons, which management believes could supply approximately 20% of Brazil’s current potash demand and help reduce reliance on imports while targeting an estimated 1.4 million tons per year of greenhouse gas emissions reductions.

Positive

  • None.

Negative

  • None.
Total FEED contract value USD 26 million Estimated total value of mine shafts and underground FEED contract
Early Works phase value USD 4.3 million First 12-month Early Works phase of FEED contract
Early Works duration 12 months Initial FEED Early Works phase timeline
Planned annual potash production 2.4 million tons per year Initial planned output at Autazes Project
Brazil potash import dependence over 95% Share of potash fertilizer imported by Brazil in 2021
Target share of Brazil demand approximately 20% Management’s estimate of Autazes’ potential share of current domestic demand
Target GHG emissions reduction 1.4 million tons per year Estimated greenhouse gas reductions from domestic potash production and logistics
Shafts referenced as critical path two shafts Number of mine shafts defining the Autazes construction schedule
Front-End Engineering Design technical
"Brazil Potash Awards Front End Engineering Design (FEED) Contract For Mine Shafts"
Front-end engineering design is the early, detailed planning phase of a capital project when engineers create the core blueprints, scope, and cost and schedule estimates that guide construction and procurement. For investors, it matters because a thorough front-end design reduces uncertainty about total costs, timing, and technical risks—similar to having a detailed house plan and budget before breaking ground—so it helps assess whether a project is likely to stay on time and on budget.
Development Finance Institutions financial
"construction debt financing, which is currently being advanced through ongoing dialogue with Development Finance Institutions"
Development finance institutions are government-backed or state-supported lenders and investors that provide long-term funding, guarantees, and technical support for projects aimed at economic growth, job creation, and basic services in lower-income or underserved regions. They matter to investors because their involvement can lower project risk, attract private capital, and signal that an investment meets social or environmental standards—like a public-sector co-investor or scaffolding that helps a risky project get built and financed.
Export Credit Agencies financial
"ongoing dialogue with Development Finance Institutions and Export Credit Agencies"
Export credit agencies are government-backed institutions that provide loans, guarantees or insurance to help domestic companies sell goods and services abroad. Think of them as a government co-signer or insurer that reduces the risk of nonpayment or political trouble in foreign markets; for investors, their support can make large cross-border deals more likely, lower financing costs, and change a company’s export revenue and credit risk profile.
bankability financial
"intended to support lender due diligence, establishing the foundations required for bankability"
The likelihood that a company, project, or asset can attract loans or investment because it is seen as low risk and able to deliver promised returns. Think of it like a borrower’s reputation with lenders: the more “bankable” something is, the easier and cheaper it is to get financing, which affects a firm’s ability to grow, complete projects, refinance debt, and its market value to investors.
ground freezing technical
"employing ground freezing and grouting techniques together with both mechanized and conventional shaft sinking methods"
A construction technique that freezes water in soil to create a temporary, solid barrier used to support excavations, tunnels or shafts and control groundwater during work. For investors, it matters because it is a specialized, often costly method that can reduce project risk and delays by stabilizing ground conditions—like turning soft mud into solid ice—so its use affects budgets, schedules, regulatory approvals and environmental considerations.
geomechanical analysis technical
"WSP UK Ltd. contributes the engineering backbone of the FEED — covering geomechanical analysis, freeze modelling"
See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates

FAQ

What contract did Brazil Potash (GRO) announce for the Autazes Project?

Brazil Potash awarded a Front-End Engineering Design contract for mine shafts and underground development to WSP UK Ltd., with Redpath Deilmann Mining Inc. as subconsultants, completing full FEED coverage across the Autazes Project scope.

How large is the new FEED contract Brazil Potash (GRO) announced?

The estimated total value of the FEED contract is USD 26 million. The first Early Works phase has been awarded for USD 4.3 million and will run 12 months, focusing on geotechnical work and design foundations.

Why is completing FEED important for Brazil Potash’s Autazes Project (GRO)?

Completing FEED is described as a critical milestone for securing construction debt financing. Detailed engineering documentation from FEED supports lender due diligence and forms the technical basis for bankability and long-lead procurement decisions at Autazes.

What production levels does Brazil Potash (GRO) plan for the Autazes Project?

Brazil Potash’s management cites an initial planned annual potash production of up to 2.4 million tons per year. They believe this could potentially supply about 20% of Brazil’s current potash demand, focused entirely on the domestic market.

How could Brazil Potash’s Autazes Project (GRO) affect Brazil’s fertilizer imports?

Brazil imported over 95% of its potash fertilizer in 2021. Management believes producing up to 2.4 million tons annually at Autazes could potentially supply about 20% of current domestic demand, reducing reliance on imported potash.

What environmental impact target does Brazil Potash (GRO) mention for Autazes?

Management indicates the project targets an estimated reduction of 1.4 million tons per year of greenhouse gas emissions. This is tied to domestic potash production and low-cost river barge logistics rather than long-distance imported fertilizer supply chains.
 
 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

WASHINGTON, D.C. 20549

 

 

FORM 6-K

 

 

REPORT OF FOREIGN PRIVATE ISSUER

PURSUANT TO RULE 13a-16 OR 15d-16

UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of June 2026

Commission File Number: 001-42423

 

 

BRAZIL POTASH CORP.

(Translation of registrant’s name into English)

 

 

198 Davenport Road

Toronto, Ontario, Canada, M5R 1J2

Tel: +1 (416) 309-2963

(Address of principal executive offices)

 

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

☒ Form 20-F   ☐ Form  40-F

 

 
 


On June 17, 2026, Brazil Potash Corp., a corporation incorporated and existing under the laws of the Province of Ontario, Canada (the “Company”), issued a press release titled “Brazil Potash Awards Front End Engineering Design (FEED) Contract For Mine Shafts and Underground Development to WSP UK Ltd., with Redpath Deilmann Mining Inc. as Subconsultants, Completing Full-Project FEED Coverage at Autazes.”

A copy of the press releases is attached hereto as Exhibit 99.1 and is incorporated by reference herein.

The information in this Report on Form 6-K is hereby incorporated by reference into the Company’s Registration Statements on Form F-3 (File No. 333-294964), Form S-8 (File No. 333-288029), and Form S-8 (File No. 333-286827) and into the prospectuses forming a part thereof.

EXHIBIT INDEX

 

Exhibit
No.

  

Description

99.1    Press Release, dated June 17, 2026.

 

2


SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

    BRAZIL POTASH CORP.
Date: June 22, 2026     By:  

/s/ Matthew Simpson

      Name: Matthew Simpson
      Title: Chief Executive Officer

 

3

Exhibit 99.1

 

LOGO

Brazil Potash Awards Front End Engineering Design (FEED) Contract For Mine Shafts and Underground Development to WSP UK Ltd., with Redpath Deilmann Mining Inc. as Subconsultants, Completing Full-Project FEED Coverage at Autazes

 

   

With both FEED programs now awarded, Brazil Potash has secured comprehensive engineering design coverage across the entire Autazes Project, a key requirement for construction debt financing discussions currently underway with Development Finance Institutions (DFIs) and Export Credit Agencies (ECAs)

 

   

Redpath Mining Inc., with 500+ shafts completed globally including among the most complex potash shafts of the last decade, engaged as subconsultants under the FEED for mine shafts and underground development, the critical path that defines the entire Autazes Project construction schedule


   

Following the award of the Surface Facilities and Infrastructure FEED to Wood and Promon Engenharia, this award completes full engineering design coverage across the entire Autazes Project

MANAUS, Brazil, June 17, 2026 (GLOBE NEWSWIRE) — Brazil Potash Corp. (“Brazil Potash” or the “Company”) (NYSE-American: GRO), a mineral exploration and development company advancing the Autazes potash project in Amazonas State, Brazil (the “Autazes Project” or “Project”), is pleased to announce the award of a second Front-End Engineering Design (“FEED”) contract for mine shafts and underground development to WSP UK Ltd., with Redpath Deilmann (“Redpath”) as subconsultants for the mine shafts scope.

“Awarding this second FEED to WSP and Redpath means every component of the Autazes Project, both underground and surface, now has world-class engineering teams behind it. Redpath is among the most experienced teams globally in potash shaft sinking, and bringing them to Autazes gives our lenders and partners the engineering rigor they need to move forward. We are one step closer to the day Brazil stops importing 95% of its own fertilizer,” said Raphael Bloise, Project Director of Brazil Potash.

WSP UK Ltd. and Redpath were selected for their extensive global experience in potash shaft sinking, proven capability under complex geotechnical conditions, and Brazilian regulatory alignment through a standalone agreement with WSP Brasil.


Completing the FEED Program: Mine Shafts and the Path to Financing

With the Surface Facilities and Infrastructure FEED already awarded to Wood and Promon Engenharia, this award closes the loop on engineering design across the full Autazes scope. Mine shafts and underground development will now be developed to the same level of engineering fidelity as the surface works, creating a unified, lender-ready engineering basis for the entire Project. The completion of FEED studies is a critical milestone for securing construction debt financing, which is currently being advanced through ongoing dialogue with Development Finance Institutions and Export Credit Agencies. The FEED phase converts conceptual and pre-feasibility premises into detailed engineering documentation intended to support lender due diligence, establishing the foundations required for bankability, investment readiness, and long-lead procurement.

Global Expertise in Deep Potash Shafts and Critical-Path Risk

Redpath has participated in and delivered shaft sinking works on more than 500 shafts worldwide, including numerous historic shafts in the Saskatchewan potash basin in Canada, as well as major recent potash projects such as Jansen, Woodsmith, Rocanville, K3, and Nezhinsky, employing ground freezing and grouting techniques together with both mechanized and conventional shaft sinking methods, some of which have been completed and others are currently under execution.

Shaft sinking constitutes the critical path for the Autazes Project, the two shafts define the entire construction schedule. All subsequent infrastructure, including the processing plant, tailings, logistics, and underground development, depends on the timely and safe completion of the shafts.


WSP UK Ltd. and WSP Brasil: Engineering Backbone and Regulatory Integration

While Redpath leads shaft sinking and constructability, WSP UK Ltd. contributes the engineering backbone of the FEED — covering geomechanical analysis, freeze modelling, shaft liner design, and structural assessments. WSP Brasil supports compliance with Brazilian regulatory frameworks, integrating local execution with global engineering standards. Together, this integrated team is designed to provide lenders with confidence that the FEED meets both international best practice and Brazilian regulatory requirements.

Contractual Framework

The estimated total value of the FEED contract, subject to authorization of subsequent phases, is USD 26 million. At this time only the first phase, Early Works, has been awarded and spans 12 months with a value of USD 4.3 million and encompasses geotechnical investigation, freeze modelling, basis of design development, and the regulatory and engineering foundations required to advance to full FEED execution.

About Brazil Potash

Brazil Potash (NYSE-American: GRO) (www.brazilpotash.com) is developing the Autazes Project to supply sustainable fertilizers to one of the world’s largest agricultural exporters. Brazil is critical for global food security as the country has amongst the highest amounts of fresh water, arable land, and an ideal climate for year-round crop growth, but it is vulnerable as it imported over 95% of its potash fertilizer in 2021, despite having what is anticipated to be one of the world’s largest undeveloped potash basins in its own backyard. The potash produced will be transported primarily using low-cost river barges on an inland river system in partnership with Amaggi (www.amaggi.com.br), one of Brazil’s largest farmers and


logistical operators of agricultural products. With an initial planned annual potash production of up to 2.4 million tons per year, Brazil Potash’s management believes it could potentially supply approximately 20% of the current potash demand in Brazil. Management anticipates 100% of Brazil Potash’s production will be sold domestically to reduce Brazil’s reliance on potash imports while concurrently targeting a reduction of an estimated 1.4 million tons per year of GHG emissions.

Forward-Looking Statements Disclaimer

This press release includes forward-looking statements, which are statements that are not historical facts. Words such as “expects”, “anticipates”, “believes”, “intends”, “will”, “estimates”, “plans”, “may” and similar expressions are intended to identify forward-looking statements. Such forward-looking statements, including statements relating to the anticipated benefits of the Autazes Project to Brazil’s agricultural sector, expected production volumes, the Company’s potential engagement with development finance institutions and export credit agencies, the expected benefits and timeline of the FEED study, the anticipated capabilities of the Redpath and WSP consortium, estimated greenhouse gas emissions reductions, and the status of the Company’s project, government regulation and environmental regulation, are subject to risks and uncertainties, many of which are beyond the control of the Company, including those described in the “Risk Factors” section of the Company’s registration statement on Form F-1, as amended, for the IPO filed with the SEC, the Company’s most recent annual report on Form 20-F filed with the SEC and the supplemented PREP prospectus filed in each of the provinces and territories of Canada, other than Québec. Readers are cautioned not to place undue reliance on any of these forward-looking statements. These forward-looking statements speak only as of the date hereof. The Company expressly disclaims any obligations or undertaking to release publicly any updates or


revisions to any forward-looking statements contained herein to reflect any change in the Company’s expectations with respect thereto or any change in events, conditions or circumstances on which any statement is based, unless required by law. This press release does not constitute an offer to sell or a solicitation of an offer to buy any securities of the Company.

Contact:

Brazil Potash Investor Relations

info@brazilpotash.com

Filing Exhibits & Attachments

1 document