Hallador Energy Company reported weaker results for the six months ended June 30, 2026, moving from net income of $18.2 million in 2025 to a net loss of $24.6 million, or $(0.52) per basic share. Total sales and operating revenues declined to $206.0 million from $220.5 million, driven mainly by lower Electric Operations revenue and outages at the Merom power plant, partially offset by higher coal pricing and volume.
Electric Operations sales fell to $127.3 million from $145.9 million as delivered energy revenue dropped and cost of purchased power and maintenance expenses rose sharply due to equipment issues and a major outage, producing Segment EBITDA of only $2.2 million versus $41.8 million a year earlier. Coal Operations sales were $97.3 million versus $100.3 million, with higher realized coal prices offset by cost pressure and lower segment EBITDA.
Operating cash flow reversed from an inflow of $49.8 million to an outflow of $3.4 million, while capital expenditures increased to $33.9 million. Liquidity totaled $84.2 million, including $28.98 million of cash and $55.3 million of revolver availability under a new $120 million credit facility. Hallador also entered into a $350.0 million agreement to acquire approximately 460 MW of Siemens turbine equipment, expecting about $100.0 million of additional related costs, and extended Merom’s useful life to 2040, reducing current depreciation expense.
Hallador Energy Company reported a Q1 2026 net loss as it reshaped its balance sheet and contract portfolio. Total sales and operating revenues were $101.8 million, down from $117.7 million a year earlier, as electric sales declined while coal sales to third parties increased.
The company posted a net loss of $9.3 million, versus net income of $10.0 million in Q1 2025, with diluted earnings per share moving from $0.23 to a loss of $0.20. Electric Operations swung from strong profitability to a loss before income taxes of $5.0 million, driven by lower generation volumes, higher purchased power and maintenance tied to equipment issues at the Merom plant. Coal Operations narrowed their loss before taxes to $3.0 million, helped by higher realized coal prices and much lower depreciation after prior impairments.
Liquidity improved meaningfully: cash, cash equivalents and restricted cash rose to $43.4 million, and bank debt was reduced from $30.0 million to zero. Hallador closed a new $75.0 million revolving credit facility with an additional $45.0 million delayed draw term loan and completed an equity offering with net proceeds of about $53.8 million. As of March 31, 2026, total liquidity was $97.5 million and forward contracted consolidated revenue across power and third‑party coal totaled $859.6 million through 2029.
Hallador Energy (HNRG) reported stronger results for the quarter ended September 30, 2025. Revenue rose to $146.8 million from $105.2 million a year ago, and net income increased to $23.9 million from $1.6 million. For the nine months, revenue was $367.5 million versus $310.8 million, with net income of $42.1 million compared to a $10.3 million loss in the prior-year period.
Electric sales were $93.2 million and coal sales were $51.3 million in Q3. Operating cash flow for the nine months was $73.0 million; capital expenditures were $44.3 million. Liquidity totaled $46.4 million, including $33.8 million of revolver availability and cash. Bank debt was $44.0 million at quarter-end at an all-in rate of 9.27%. A third amendment to the credit agreement deferred certain covenants to Q3 2025 and moved the $6.0 million October 2025 and $6.5 million January 2026 payments to January 2026, with full repayment of the term loan by March 2026 funded from restricted cash.
The company executed prepaid, physically delivered power contracts of $35.0 million and $20.0 million, and ended with contract liabilities of $147.6 million. Management is in discussions to refinance the facility and remained in covenant compliance as of September 30, 2025.
Hallador Energy Company (HNRG) reported revenue of $102.9 million in Q2 2025, up from $93.8 million a year earlier, driven by stable electric sales and higher coal sales. The company generated $17.6 million of EBITDA margin for the quarter (an improvement of $9.1 million year-over-year) and reported net income of $8.248 million for the three months and $18.227 million for the six months ended June 30, 2025, resulting in basic EPS of $0.19 and $0.43, respectively.
Balance sheet highlights: total assets of $409.5 million, total liabilities of $287.4 million, and stockholders' equity of $122.2 million. Cash and restricted cash totaled $32.4 million at June 30, 2025, including $23.1 million restricted primarily for workers' compensation and a $19.0 million compensating balance related to a $35.0 million prepaid forward power contract that generated restricted proceeds. Bank debt totaled $45.0 million with current term loan amounts moved into January 2026 under a Third Amendment; management is pursuing refinancing but no assurance of success was provided.