i-80 Gold (NYSE American: IAUX) outlines Lone Tree plant cost and timeline
Rhea-AI Filing Summary
i-80 Gold Corp. provided an update on refurbishing its Lone Tree processing plant in Nevada, based on a Class 3 engineering study. The project is designed to modernize the facility, add a pressure oxidation (POX) circuit and tailings filtration, and improve environmental compliance.
The Lone Tree autoclave is expected to process up to 2,268 tonnes per day, or 827,806 tonnes per year at 85% availability, treating refractory ore from the Granite Creek, Archimedes, and Cove underground mines. Total project cost is estimated at $430 million, modestly higher than an earlier expectation of about $400 million, with $343 million in direct and indirect costs plus contingency, owner’s costs, and capital spares.
Permitting work is ongoing, with applications for the new design expected to be submitted in early 2026. Demolition is targeted to start in the second quarter of 2026 and construction in the second half of 2026, with commissioning of the refurbished plant expected to begin in the fourth quarter of 2027, subject to permits, financing, and a construction decision tied to the company’s recapitalization plan.
Positive
- None.
Negative
- None.
Insights
$430M Lone Tree plan advances, but depends on permits and financing.
i-80 Gold outlines a Class 3 engineering plan to refurbish the Lone Tree plant for refractory processing with an estimated total project cost of $430 million. The design centers on converting the existing autoclave to a modern POX circuit, adding tailings filtration, and upgrading circuits for mercury abatement, grinding, and oxygen supply, with nameplate throughput of 2,268 tonnes per day.
The filing notes that the cost estimate is modestly higher than a prior anticipated amount of approximately $400 million, mainly from inflation, design detail, and added tailings capacity. This level of spend is significant relative to most single-asset builds and is intended to support ore from Granite Creek, Archimedes, and Cove, but actual economic returns will depend on future margins, recoveries, and mine performance, which are described only in qualitative terms.
Execution is conditioned on several factors: updated permits for air, water, mercury, and reclamation, completion of engineering in Q4 2025, permit submission in Q1 2026, and a construction decision tied to a recapitalization. Demolition is targeted for Q2 2026, with construction in the second half of 2026 and commissioning in Q4 2027, so cash outflows and any future production impact are spread over multiple years and remain subject to permitting, financing, and technical risks highlighted in the forward-looking statements and risk factor cross-references.