Mako Mining posts about $50M in Q3 2026 revenue

A procured Moss crushing-circuit upgrade is expected to raise throughput above 12,000 short tons per day by Q3 2027.

(Moderate)

Sentiment and the balance of points

Rhea-AI Sentiment reads the wording of the document, how positive or negative its language is on a 1 to 5 scale. The balance of points shown with the takes weighs what the document actually discloses, so the two can disagree, for example when a trial that missed its main goal is described in upbeat language.

Form Type
6-K

Rhea-AI Filing Summary

Mako Mining Corp. reported Q3 2026 production of 12,743 ounces of gold recovered and 11,581 ounces sold, with total revenue of ~$50 million. Cash, securities and trade receivables were $119.3 million as of September 30, 2026. San Albino recovered 9,145 ounces and sold 8,768 ounces; its mill processed 53,046 tonnes at 6.66 g/t gold with 80.5% recovery. Moss Mine recovered 3,599 ounces and sold 2,812 ounces.

Moss crushing throughput averaged 5,113 short tons per day in Q3, below the Technical Report's 8,500 short tons per day initial throughput for 2026–2027. A procured crushing-circuit upgrade is expected to raise throughput to more than 12,000 short tons per day by Q3 2027; a new leach pad is expected to operate in Q4 2026. Mako expects deferred ounces to contribute to Q4 gold sales.

USFS permits for Mt. Hamilton condemnation drilling were received, with drilling contingent on posting and acceptance of a $265,205 reclamation bond; first gold pour is anticipated in December 2027. Eagle Mountain's mineral agreement with Guyana establishes a 10-year stability framework, and the final ESIA is expected to be submitted in Q4 2026.

1 point · 0 major

How this balance works

Rhea-AI gives every point it takes from this document a weight. Minor counts 1, Moderate 3 and Major 9, so one Major point outweighs several Minor ones. The bar adds up the weights on each side, and when neither side holds more than 65% of the total the balance reads Mixed.

It reads the document as published, with the same rules for every company, and it does not look at what the market expected or at how the stock traded, so a point can be objectively good on a day the stock falls.

Rhea-AI Sentiment measures something else, the tone of the wording.

0 major · 1 point

Hollow bars mark forward-looking points. How the balance works

Positive

  • Moderate point. Forward-looking: it has not happened yet and may not happen.Moss expects throughput above 12,000 short tons per day by Q3 2027.

Negative

  • Moderate pointMoss throughput averaged 5,113 short tons per day in Q3, versus the Technical Report's initial 8,500 short tons per day for 2026–2027.
Gold recovered 12,743 ounces Mako total, Q3 2026
Gold sold 11,581 ounces Mako total, Q3 2026
Total revenue ~$50 million Q3 2026
Cash, securities and trade receivables $119.3 million As of September 30, 2026
San Albino gold recovery 80.5% Q3 2026
Moss crushing plant throughput 5,113 short tons per day Average during Q3 2026
Expected Moss throughput More than 12,000 short tons per day Expected by Q3 2027
Average realized gold price per ounce sold financial
"Average realized gold price per ounce sold is calculated"
Total cash received from selling gold during a reporting period divided by the number of ounces actually sold in that period, after any adjustments such as premiums, discounts, concentrates, and contractual deductions. It shows the average price the company realized for each ounce it sold, rather than the market spot price. Investors use it to understand how much revenue each unit of production generated—like the average sale price per item in a store—and to compare sales performance across periods or producers.
reclamation bond regulatory
"a $265,205 reclamation bond has been posted and accepted"
A reclamation bond is a cash deposit or financial guarantee a company must post with regulators to pay for restoring land and cleaning up environmental damage after activities like mining or large construction projects. Think of it as a security deposit for the site: if the company can't or won't do the cleanup, regulators use the bond to pay contractors. For investors this matters because bonds tie up cash or credit, increase project costs, and reduce the risk that future environmental liabilities suddenly hit shareholders.
heap-leach pads technical
"additional water to the heap-leach pads"
Environmental and Social Impact Assessment regulatory
"Draft Environmental and Social Impact Assessment (ESIA)"
An environmental and social impact assessment evaluates how a project, operation, or company affects the natural environment and nearby people—covering pollution, resource use, community health, labor conditions and local livelihoods. For investors it’s like a home inspection: it reveals hidden risks and potential costs (fines, cleanup, protests, supply disruptions) and opportunities (efficiency gains, stronger community relationships, access to certain markets) that can change a company’s long‑term value and risk profile.
mineral agreement regulatory
"execution of a mineral agreement with the Government of Guyana"

FAQ

AI-generated questions and answers. How Rhea-AI works. Not financial advice.

How much gold did MAKO recover and sell in Q3 2026?

Mako reported 12,743 ounces of gold recovered and 11,581 ounces sold, with total revenue of ~$50 million.

Why did Moss Mine sell less gold than it recovered in Q3 2026?

Longer solution-return times associated with higher stacking lifts delayed the availability of gold-bearing solution for processing. Mako expects these deferred ounces to contribute to Q4 2026 sales, alongside production from newly stacked material.

What is required before Mt. Hamilton condemnation drilling can begin?

Drilling can begin once a $265,205 reclamation bond has been posted and accepted by the US Forest Service.

How much drilling did MAKO complete at Eagle Mountain in Q3 2026?

Eagle Mountain completed 54 drill holes totaling 4,467 meters during Q3 2026, compared with 45 holes totaling 2,253 meters during the first six months of 2026.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Available on EDGAR Accepted by SEC EDGAR Learn about SEC filing dates

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

FORM 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16
UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of October 19, 2026

Commission File Number: 001-43201

Mako Mining Corp.
(Translation of registrant's name into English)

Suite 700-838 West Hastings Street
Vancouver, British Columbia,
Canada V6C 0A6

(Address of principal executive office)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

Form 20-F ☐ Form 40-F ☒


EXHIBIT INDEX

Exhibit Description
   
99.1 Mako Mining Announces Q3 2026 Production Results and Positive Permitting Updates at Mt. Hamilton and San Albino


SIGNATURE

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, there unto duly authorized.

  Mako Mining Corp.
     
     
Date: October 19, 2026 By: /s/ Akiba Leisman
  Name: Akiba Leisman
  Title: Chief Executive Officer




October 19, 2026

NASDAQ: MAKO; TSX-V: MKO

Mako Mining Announces Q3 2026 Production Results with Gold Recovered of 12,743 oz
Au (Sales of 11,581 oz Au), and Positive Permitting Updates at Mt. Hamilton and San
Albino

Mako Mining Corp. (Nasdaq: MAKO; TSX-V: MKO) ("Mako" or the "Company") is pleased to provide its third quarter 2026 ("Q3 2026") production results for the Company's San Albino gold mine ("San Albino") in northern Nicaragua and the Moss Mine in Arizona ("Moss Mine") and a corporate update across all assets. Certain figures in this news release may not sum precisely due to rounding. Unless otherwise indicated, all amounts are expressed in U.S. dollars.

Q3 2026 San Albino Operational Highlights

  • 42,565 tonnes mined, containing 10,913 ounces ("oz") of gold ("Au") at an average grade of 7.97 grams per tonne ("g/t") Au and 11,489 oz of silver ("Ag") at 8.40 g/t Ag
    • 27,321 tonnes mined from diluted vein material containing 9,245 oz Au at 10.53 g/t Au and 9,690 oz Ag at 11.03 g/t Ag
    • 15,244 tonnes mined from historical dump and other mineralized material above cutoff grade ("historical dump + other") containing 1,667 oz Au at 3.40 g/t Au and 1,799 oz Ag at 3.67 g/t Ag
    • 40.7:1 strip ratio 
  • 53,046 tonnes milled containing 11,365 oz Au and 12,221 oz Ag grading 6.66 g/t Au and 7.17 g/t Ag, respectively
    • 48% and 52% from diluted vein and historical dump and other, respectively
    • 587 tonnes per day ("tpd") milled at 98% availability
    • Mill recovery of 80.5% for gold
  • At quarter-end, the stockpile was estimated at 109,868 tonnes at an average grade of 2.74 g/t Au for contained Au of 9,666 oz

Q3 2026 Mako Financial Highlights

  • Mako total gold recovered of 12,743 oz Au (sales of 11,581 oz Au) for total revenue of ~$50 million in Q3 2026
    • San Albino gold recovered of 9,145 oz Au (sales of 8,768 oz Au at $4,285(1) per ounce)
    • Moss Mine gold recovered of 3,599 (sales of 2,812 oz Au at $4,343 per ounce)
  • Delivered 894 oz Au in connection with gold stream related to the purchase of the Mt. Hamilton Project
  • Cash, securities and trade receivables of $119.3 million as of September 30, 2026

(1) Gold Price before Sailfish Adjustments. For the purpose of calculating revenue, payments to Sailfish are deducted from the Average Realized Price Gold.

Akiba Leisman, Chief Executive Officer of Mako states "Following 2 quarters of overperformance, San Albino delivered a solid, inline Q3 2026, related entirely to processing more lower grade historical dump material relative to higher grade diluted vein material (48% in Q3 2026 vs. 54% in H1 2026) leading to gold recoveries of 9,145 oz Au (sales of 8,768 oz Au).  Moss continued to be mechanically constrained by our legacy plant. After detailed engineering over the course of 2026, our team has identified a way to significantly expand our crushing circuit without triggering a major permitting review; equipment has been procured, and by Q3 2027 Moss is expected to process more than 12,000 short tons per day, 40% above the August 2026 Technical Report, and 130% above Q3 2026, which lead to gold recoveries of 3,599 oz Au (sales of 2,812 oz Au). At Mt. Hamilton, we received the condemnation drilling permit amendments last Friday, removing the main bottleneck for construction, and the minor amendment to the plan of operation is expected later this year, with no interruption to our construction schedule. At Eagle Mountain, we executed our Mineral Agreement, and received comments on our Draft ESIA, with our Final ESIA expected to be submitted later this year with approval shortly thereafter. Despite significant capital investments across all four assets, our cash and securities balance has grown to US$119.3 million, more than enough, including future operating cash flow, to fund the construction of both Mt. Hamilton and Eagle Mountain." 

Table 1 - Operating Results San Albino and Moss

  Units Q1 2026 Q2 2026 Q3 2026
         
SAN ALBINO        
Tonnes Mined ore + waste 2,254,180 1,804,920 1,774,621
Tonnes Milled tonnes 53,638 53,120 53,046
Feed Grade Gold g/tonne 7.70 7.54 6.66
Gold Recovery % 80% 81% 80.5%
Gold Recovered oz 10,640 10,392 9,145
Gold Sold oz 10,398 10,612 8,768
Avg. Realized Gold Price US$/oz sold 4,901 4,156 4,285
         
MOSS MINE        
Tonnes Mined ore + waste 1,550,906 1,362,934 1,460,247
Ore Stacked tonnes 490,156 481,812 426,755
Feed Grade Gold g/tonne 0.31 0.32 0.35
Feed Grade Silver g/tonne 1.96 1.89 2.03
Au Recovery % 74% 75% 74%
Ag Recovery % 36% 37% 37%
Gold Recovered oz 3,624 3,631 3,599
Gold Sold oz 3,323 3,998 2,812
Silver Sold oz 16,023 17,013 16,048
Avg. Realized Gold Price US$/oz sold 4,912 4,321 4,343

Table 2 - Detailed Operating Results for San Albino 

  Units Q4 2025 Q1 2026 Q2 2026 Q3 2026
Mined          
Diluted Vein          
Tonnes tonnes 34,600 31,033 29,142 27,321
Gold Grade g/t 9.65 10.64 10.93 10.53
Silver Grade g/t 9.56 10.50 9.89 11.03
Contained Gold oz 10,740 10,613 10,237 9,245
Contained Silver oz 10,636 10,476 9,270 9,690
Historical Dump + Other*          
Tonnes tonnes 22,977 19,200 19,747 15,244
Gold Grade g/t 2.93 3.12 3.39 3.40
Silver Grade g/t 3.20 3.21 3.18 3.67
Contained Gold oz 2,166 1,925 2,153 1,667
Contained Silver oz 2,368 1,984 2,019 1,799
Waste          
Tonnes tonnes 2,241,182 2,203,947 1,756,030 1,732,056
Strip Ratio (1) w:o 38.9 43.9 35.9 40.7
           
Milled          
Diluted Vein % 53% 55% 53% 48%
Historical Dump + Other* % 47% 45% 47% 52%
Tonnes  tonnes 54,076 53,638 53,120 53,046
Gold Grade g/t 6.77 7.70 7.54 6.66
Silver Grade g/t 6.92 7.70 6.86 7.17
Contained Gold oz 11,767 13,277 12,874 11,365
Contained Silver oz 12,039 13,274 11,714 12,221
Mill Availability % 98% 97% 97% 98%
Average Tonnes per Day t/day 599 614 599 587
Recovered          
Gold Recovery % 81.8% 80.1% 80.7% 80.5%
Gold Recovered oz 9,621 10,640 10,392 9,145
Gold Sold oz 9,307 10,398 10,612 8,768
Avg. Realized Price Gold ** US$/oz 4,340 4,901 4,156 4,285

* Includes historical dump, hanging wall, footwall, historical muck and all other non-vein mineralized material above cutoff grade.

** Average realized gold price per ounce sold is calculated by dividing total gold revenue by the total gold ounces sold into the spot market and before deductions from Sailfish. For the purpose of calculating revenue, payments to Sailfish are deducted from the Average Realized Price Gold.

(1) Strip Ratio calculation does not include waste material that is capitalized


Table 3 - San Albino Quarter-End Stockpile Statistics

  Units Q4 2025 Q1 2026 Q2 2026 Q3 2026
           
Historical Dump + Other**          
Tonnes  t 127,755 124,350 120,119 109,868
Gold Grade g/t 2.76 2.65 2.62 2.74
Contained Gold oz 11,328 10,558 10,105 9,666

 ** Includes historical dump, hanging wall, footwall, historical muck and all other non-vein mineralized material above cutoff grade.

San Albino

During Q3 2026, San Albino processed 53,046 tonnes of mineralized material at an average gold grade of 6.66 g/t, achieving gold recoveries of 80.5% and producing 9,145 ounces of recovered gold. The mine sold 8,768 ounces of gold at an average realized price of US$ 4,285 per ounce. Compared to Q2 2026, mill throughput remained relatively stable, while gold recoveries were largely unchanged from 80.7%. Average feed grades were lower from previous quarters due to a higher percentage of stockpile being processed relative to run of mine material.

In October 2026, Mako received drilling permits to begin exploration for the newly granted concession of Eureka two months ahead of schedule. Preparatory work has started at Eureka with drilling expected to begin later this quarter.

Moss Mine

In Q3 2026, Moss Mine recovered approximately 3,599 ounces of gold, with sales totaling approximately 2,812 ounces. Gold recovery during the quarter was impacted by longer solution return times associated with higher stacking lifts, which delayed the availability of gold-bearing solution for processing. The Company expects these deferred ounces to contribute to gold sales during Q4 2026, alongside production from newly stacked material. Additionally, the Company is in the final stages of completing a new leach pad, expected to become operational during Q4 2026, which will allow for lower stacking lifts and shorter gold recovery cycles.

During Q3 2026, crushing plant throughput averaged 5,113 short tons per day, below the 8,500 short tons per day initial throughput for 2026-2027 (ramping to 10,000 short tons per day in 2028-2030 and 14,000 short tons per day beginning in 2031) described in the NI 43-101 Technical Report for the Mineral Resources, Mineral Reserves and Mine Plan for the Moss Mine, Oatman Mining District, Mohave County, Arizona (the "Technical Report") dated August 17, 2026, primarily due to mechanical constraints and operational bottlenecks. To address these limitations, the Company has completed extensive maintenance and improvement work on the crushing circuit to enhance equipment reliability and reduce unplanned downtime. In parallel, a new production well is now supplying additional water to the heap-leach pads, supporting improved irrigation and more consistent solution flows. Together, these initiatives are expected to improve operating efficiency, increase throughput, and support more consistent gold production.

Building on these operational improvements, the Company has procured a significant crushing circuit upgrade, including additional crushing and screening capacity, conveyor modifications, and supporting electrical infrastructure. Together with the improvements already implemented, this upgrade is expected to increase crushing plant throughput to more than 12,000 short tons per day by Q3 2027, substantially exceeding both the 8,500 short tons per day outlined in the Technical Report and the 5,113 short tons per day achieved in Q3 2026. The anticipated increase in throughput, combined with expected improvements in head grades as the Company begins accessing higher-grade material from the East Pit in early 2027, is expected to more than double gold production compared to current operating levels.


Mt. Hamilton Project

On October 16, 2026, the Company received permits from the US Forest Service ("USFS") to begin condemnation drilling at the Mt. Hamilton Project once a $ 265,205 reclamation bond has been posted and accepted by the USFS. This was the principal bottleneck to begin full scale construction. The US Forest Service will continue to review the amended plan of operation which calls for a minor adjustment to the crusher and overland conveyor placement. We anticipate approval for this modification to occur later this year, and we do not anticipate the timing of this approval to impact our schedule.

Long lead items for the Mt. Hamilton construction project, including the crusher and overland conveyor, will be procured later this month. First gold pour is anticipated in December 2027.

Eagle Mountain Gold Project

During Q3 2026, exploration and technical activities accelerated significantly following the mobilization of a contractor drill rig and the onset of the dry season. A total of 54 drill holes totaling 4,467 meters were completed during the quarter, compared to 45 holes totaling 2,253 meters during the first six months of 2026. Q3 drilling included 185 meters of geotechnical drilling, 2,001 meters of metallurgical drilling, and 2,281 meters of infill and exploration drilling. These activities support ongoing engineering, resource evaluation, and project development planning.

On September 10, 2026, the Company announced the execution of a mineral agreement with the Government of Guyana and the Guyana Geology and Mines Commission (GGMC), establishing a 10-year stability framework for key legal, fiscal, and operating terms applicable to the project. This agreement represents an important milestone in advancing Eagle Mountain toward development.

In early October the Guyana EPA provided their comments on the draft Environmental and Social Impact Assessment (ESIA), identifying areas requiring additional detail or clarification. The Company and lead ESIA consultants expect to submit the final ESIA in the fourth quarter of 2026 with approval shortly thereafter.

Pre-development activities continued during Q3 2026, including the completion of bridge surveys, site preparation, and construction-readiness planning. The Company also entered into a contract for upgrades to the camp access road, with work scheduled to commence in October 2026.

On behalf of the Board,

Akiba Leisman

Chief Executive Officer


For the latest details, please refer to the unaudited condensed interim consolidated financial statements and the associated management's discussion and analysis for the six months ended June 30, 2026, available under the Company's profile on SEDAR+ (www.sedarplus.ca), on EDGAR at www.sec.gov or on the Company's website (www.makominingcorp.com).

Non-GAAP Measures

The Company has included certain non-GAAP financial measures and non-GAAP ratios in this press release such as Average realized gold price per ounce sold. These non-GAAP measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. In the gold mining industry, these are commonly used performance measures and ratios, but do not have any standardized meaning prescribed under IFRS and therefore may not be comparable to other issuers. The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate the Company's underlying performance of its core operations and its ability to generate cash flow.

"Average realized gold price per ounce sold" is calculated by dividing total gold revenue by the total gold ounces sold into the spot market before deductions from Sailfish.

Qualified Person

John Rust, a metallurgical engineer and qualified person (as defined under NI 43-101) has read and approved the technical information contained in this press release. Mr. Rust is a senior metallurgist and a consultant to the Company.

About Mako

Mako Mining Corp. is a publicly listed gold mining, development and exploration company. The Company operates the high-grade San Albino gold mine in Nueva Segovia, Nicaragua, which ranks as one of the highest-grade open pit gold mines globally and offers district-scale exploration potential. Mako also owns two assets in the US: the Moss Mine in Arizona, an open pit gold mine in northwestern Arizona and the Mt. Hamilton Project, a heap leach project in Nevada. Mako also holds a 100% interest in the PEA-stage Eagle Mountain Project in Guyana, South America. Eagle Mountain is the subject of engineering, environmental and mine permitting activity.

For further information: Mako Mining Corp., Akiba Leisman, Chief Executive Officer, Telephone: 917-558-5289, E-mail: aleisman@makominingcorp.com or visit our website at www.makominingcorp.com and SEDAR www.sedarplus.ca.

Forward-Looking Information:  Statements contained herein, other than historical fact, may be considered "forward-looking information" within the meaning of applicable securities laws. The forward-looking information contained herein is based on the Company's plans and expectations and assumptions as of the date of this news release. Such statements forward looking statements include: expectations stated regarding Q3 2026 production at San Albino and financial highlights for the Company, expected timing for development activities at Eagle Mountain and ramp up activities at the Moss Mine and construction plans at Mt. Hamilton. Such forward-looking information is subject to a variety of risks and uncertainties which could cause actual events or results to differ materially from those reflected in the forward-looking information, including, without limitation, uncertainty related to mining exploration and development activities and shifts in the timing thereof; political risks and uncertainties involving the Company's mineral properties; the inherent uncertainty of cost estimates and the potential for unexpected costs and expense; commodity price fluctuations and other risks and uncertainties as disclosed in the Company's public disclosure filings on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov. Such information contained herein represents management's best judgment as of the date hereof, based on information currently available and is included for the purposes of providing investors with the Company's expectations regarding the Company's Q3 2026 production and operating results at San Albino gold project, financial highlights for Q3 2026 and current corporate updates, and may not be appropriate for other purposes. Mako does not undertake to update any forward-looking information, except in accordance with applicable securities laws.


Cautionary Note to U.S. Investors Regarding Mineral Disclosure

NI 43-101 is a rule of the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Technical disclosure contained in this news release has been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Classification System. These standards differ from the requirements of the U.S. Securities and Exchange Commission ("SEC") and resource information contained in this news release may not be comparable to similar information disclosed by domestic United States companies subject to the SEC's reporting and disclosure requirements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.