STOCK TITAN

Mayfair Gold (NYSE: MINE) details Fenn-Gib progress, $172K ad deal

Filing Impact
(Neutral)
Filing Sentiment
(Neutral)
Form Type
6-K

Rhea-AI Filing Summary

Mayfair Gold Corp. reported first-quarter 2026 progress on advancing and derisking its 100%-owned Fenn-Gib Gold Project in Northern Ontario. Work included integrating multi-year environmental baseline studies, submitting a Notification of Project Status, and appointing Egis Canada to lead environmental assessment and permitting.

The company advanced site investigations, including geotechnical drilling, condemnation drilling and pump testing, and began Front-End Engineering and Design with Ausenco for a planned 4,800 tpd processing facility. Planning is underway for updated mineral resource modeling, further geotechnical programs, power supply studies, and open pit drilling to support a potential construction decision in 2028.

Mayfair also entered a digital advertising service agreement with Native Ads Inc. for a US$172,000 campaign over up to 12 months. The Fenn-Gib Pre-Feasibility Study outlines initial development capital of C$450 million, a base case 2.7-year payback, and $896 million cumulative free cash flow over the first six years at a US$3,100/oz gold price.

Positive

  • None.

Negative

  • None.

Insights

Mayfair advances Fenn-Gib engineering, permitting and project definition.

Mayfair Gold outlines steady de-risking of the Fenn-Gib project through Q1 2026. The company progressed environmental baseline integration, filed a Notification of Project Status, and mandated Egis Canada to lead provincial environmental assessment and permitting activities.

Technical work advanced on multiple fronts: geotechnical and hydrogeological investigations, condemnation drilling, and Front-End Engineering and Design with Ausenco for a planned 4,800 tpd plant. These steps refine design, pit dewatering expectations and site layout, supporting eventual detailed engineering.

The Pre-Feasibility Study indicates initial capital of C$450 million, a 2.7-year payback, and $896 million cumulative free cash flow over six years at US$3,100/oz. A US$172,000 digital advertising campaign with Native Ads is modest relative to project scale. Overall, the filing is informative but not thesis-changing.

Digital advertising campaign cost US$172,000 Service agreement with Native Ads for up to 12 months
Initial development capital C$450 million Fenn-Gib Pre-Feasibility Study estimate
Payback period 2.7 years Base case payback in Fenn-Gib PFS
Cumulative free cash flow $896 million First six years of production in PFS
Gold price assumption US$3,100/oz Price basis for PFS economics
Planned plant throughput 4,800 tpd Processing facility design capacity in FEED
Target construction start 2028 Company goal for Fenn-Gib construction
Target initial production 2030 Company goal for first gold production
Environmental Assessment regulatory
"Egis will lead the preparation of the Ontario provincial as the Company initiates formal environmental approval activities later in 2026."
An environmental assessment is a process that evaluates how a project or activity might impact the natural surroundings, such as air, water, land, and wildlife. It helps identify potential environmental risks and ensures that any negative effects are managed or minimized. For investors, this assessment provides insight into the sustainability and long-term viability of projects, which can influence their financial decisions and risk management.
Front-End Engineering and Design technical
"the Company commenced Front-End Engineering and Design (FEED) with Ausenco Engineering for the planned 4,800 tpd processing facility."
Front-end engineering and design is the work of building the parts of a website or app that users see and interact with — like the layout, buttons, visuals, and how pages respond to clicks or taps. For investors it matters because a clear, fast, and attractive user interface is like a well-designed storefront: it helps attract and keep customers, improves conversion and engagement, and can lower support and development costs, all of which affect revenue and growth potential.
Notification of Project Status regulatory
"The Company submitted the Notification of Project Status (“NPS”) during the first quarter signalling the intent to advance the project into production"
One Project, One Process regulatory
"to support the upcoming application into Ontario’s One Project, One Process (“1P1P”) framework"
Pre-Feasibility Study financial
"The PFS outlines the potential to develop Fenn-Gib into a new Canadian gold producer"
A pre-feasibility study is an initial assessment that evaluates whether a proposed project or investment idea is worth exploring further. It involves examining basic factors like costs, potential benefits, and possible challenges, similar to conducting a preliminary check before deciding to invest more time and resources. This helps investors determine if pursuing the project further is practical and likely to be successful.
Mineral Resource Estimate technical
"all remaining assays from the 2025 Mineral Resource Estimate (MRE) confirmation drilling program were received"
A mineral resource estimate is a calculated approximation of how much metal or mineral material likely exists in a particular deposit and where it sits underground, similar to estimating how many cookies are in a jar by peeking at the layers. It matters to investors because it provides a data-based starting point for judging a project's potential value, future production and risks, while not guaranteeing recoverable or profitable amounts.

 

 

 

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549

 

FORM 6-K

 

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16
UNDER THE SECURITIES EXCHANGE ACT OF 1934

 

For the month of April 2026

 

Commission File Number: 001-43060

 

 

 

                             Mayfair Gold Corp.                       
(Translation of registrant’s name into English)

 

489 McDougall Street
           Matheson, Ontario P0K 1N0, Canada          

(Address of principal executive office)

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

 

¨ Form 20-F          x Form 40-F

 

 

 

 

- 2 -

  

SUBMITTED HEREWITH

 

Exhibit  
99.1 Press Release dated April 27, 2026 

 

 

- 3 -

 

SIGNATURE

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

Date: April 28, 2026

 

Mayfair Gold Corp.  
   
By:  
   
By: /s/ Kevin Annett  
Name: Kevin Annett  
Title: Chief Financial Officer  

 

 

 

Exhibit 99.1

 

 

 

Mayfair Gold Provides Update on Project Work in the First Quarter of 2026

Advancing and Derisking the Fenn-Gib Gold Project

 

VANCOUVER, British Columbia, April 27, 2026 – Mayfair Gold Corp. (“Mayfair”, “Mayfair Gold”, or the “Company”) (NYSE American: MINE;TSX-V: MFG) is pleased to provide this update progress achieved for the first quarter 2026, and highlight key work streams for the remainder of 2026 at the Fenn-Gib Gold Project in Northern Ontario .

 

The progress achieved in the first quarter reflects the disciplined, methodical approach we are taking as we advance and derisk the Fenn-Gib Gold project through the permitting process toward development. Each workstream is moving forward with clarity and purpose, and as the team grows, we continue to deliver the technical foundations required for a successful build,” said Nick Campbell, President and CEO. “We look forward to maintaining this momentum as we enter the next phase of engineering, environmental assessment, and regulatory and stakeholder engagement.

 

Drew Anwyll, P.Eng., Chief Operating Officer, added: “We entered 2026 with a clear execution plan, and the progress achieved this quarter reflects both the strength of that approach and the quality and commitment of the team advancing the work. Multiple critical-path activities are progressing in parallel, supported by a highly capable group focused on disciplined delivery. This work will allow us to maintain schedule confidence as we move toward detailed engineering later this year, and progress permitting and regulatory approvals. Our objective remains clear: to advance the Project efficiently targeting a construction decision in 2028, positioning us well ahead of our peers.

 

The aspects of the work advance in Q1 2026 include the following:

 

Compilation of Environmental Baseline Study work

 

Throughout Q1 2026, the Company advanced the integration and interpretation of the multi-year environmental baseline studies initiated in 2023. Work this quarter focused on advancing and consolidating studies concerning fish and fish habitat, hydrology, hydrogeology, geochemistry, wildlife, and vegetation into technical packages to support the upcoming application into Ontario’s One Project, One Process (“1P1P”) framework and advancement of the Environmental Assessment (“EA”) processes with the Province of Ontario.

 

 

 

 

Notification of Project Status

 

The Company submitted the Notification of Project Status (“NPS”) during the first quarter signalling the intent to advance the project into production and is now awaiting formal guidance and next-step requirements from the Ministry of Energy and Mines (“MEM”). Following the receipt of MEM’s review of the NPS, their feedback will be integrated into the Company’s permitting strategy to help align upcoming technical, environmental, and indigenous engagement workstreams with the identified communities.

 

Environmental Assessment

 

In the first quarter, the Company awarded the EA and permitting mandate to Egis Canada Ltd. (“Egis”), previously operating as Ecometrix Incorporated, for the Project. Building on the consolidated baseline interpretations completed to date, Egis will lead the preparation of the Ontario provincial EA as the Company initiates formal environmental approval activities later in 2026. This work will include the development of regulatory submissions, continued engagement with Indigenous communities and stakeholders, and the preparation of discipline-specific technical reports.

 

Highway 101 Realignment

 

Work commenced in late Q1 on the environmental assessment process for the proposed Highway 101 realignment. TBT Engineering has initiated early coordination with the Ministry of Transportation of Ontario (“MTO”) to confirm process requirements and advance initial scoping. Upcoming work will include route evaluation, environmental and geotechnical field studies, and continued collaboration with MTO to progress the preferred alignment.

 

Advancement of Site Investigations and Site Drilling

 

During the quarter, the Company advanced expanded site investigation programs. Geotechnical fieldwork resumed in early 2026, advancing work initiated in 2025, for the proposed tailings storage facility (“TSF”), site infrastructure areas, and the process plant. In parallel, condemnation drilling commenced across priority infrastructure zones to confirm the absence of mineralization and delineate the final site layout.

 

The Company also advanced pump testing activities to strengthen the understanding of groundwater conditions across the project area. These tests provide information on sub-surface water characteristics, hydraulic conductivity, and groundwater flow responses under sustained pumping that is vital to ongoing site engineering. The results will be incorporated into updated hydrogeological models to refine predictions of pit dewatering requirements, assess potential interactions with nearby water bodies, and support EA and permitting submissions.

 

 

 

 

Front-End Engineering and Design (“FEED”) Initiated with Ausenco

 

In the first quarter, the Company commenced Front-End Engineering and Design (FEED) with Ausenco Engineering for the planned 4,800 tpd processing facility. This phase of work includes completing applicable financial trade-off studies, advancing Process Design Criteria (PDC) and Piping and Instrumentation Diagrams (P&ID) to formalize Project design and will support advancing into detailed engineering in the second half of 2026. Q1 FEED activities focused on refining the comminution circuit and flotation layouts, integrating outcomes from third-party reviews, and establishing the engineering basis to support continued advancement of the plant design.

 

Next Steps

 

The first quarter of 2026 also allowed the Team to advance the planning and coordination of the following work:

 

Metallurgical Testing

 

To support comminution circuit design and establish additional data for rock competency characterization, large-diameter diamond drill core will be collected to generate expanded A×b rock hardness data. These results will refine parameters and inform equipment sizing and energy requirements for the operating plant. In parallel, follow-on work from the tailings settlement testing program completed in Q1 will be undertaken to better define the settled density of tailings material within the TSF.

 

Advancing the Mineral Resource Estimate drilling program

 

In the first quarter, all remaining assays from the 2025 Mineral Resource Estimate (MRE) confirmation drilling program were received. With the full 2025 MRE confirmation dataset now complete, the geology team, together with the Mineral Resource Qualified Person, are advancing the development of an updated localized model and evaluation of preliminary ore block designs within the area drilled. Upon completion, the updated local model will be compared against the MRE used in the Pre-Feasibility Study (PFS) to assess changes in grade distribution, geological continuity, and provide insight into any variability on future mine planning and operational predictability.

 

Ongoing Site Investigations and Geotechnical Programs

 

Site investigation activities will continue through the second quarter, including additional geotechnical drilling, test pitting, and material characterization across the TSF, plant site, and infrastructure locations. These programs will further refine foundation design parameters and support the advancement into the detailed engineering phase.

 

 

 

 

Power Supply to Site

 

The Company along with TWD Engineering are advancing work to define the preferred power-to-site solution, including evaluation of transmission routing and supply voltage, interconnection requirements, and technical specifications. Engagement with the relevant utilities and regulatory bodies including Hydro One Network (“HONI”) and the Independent Electricity System Operator (“IESO”) will continue as the Company progresses toward a finalized power supply strategy to support the Project.

 

Open Pit Geotechnical Drilling

 

Additional open pit geotechnical drilling is to commence in the third quarter. Initial geotechnical work completed in 2023 supported the open pit designs developed for the PFS. Building upon this foundation, the program will gather supplementary structural, geomechanical, and hydrogeological data to enhance the accuracy of open pit slope designs and facilitate pit optimization and operational stability evaluations.

 

Mayfair is growing the core team to advance Fenn-Gib and support the ongoing initiatives to derisk the Project, support the Provincial permitting process and make preparations in advance of the start of construction.

 

Advertising Service Agreement

 

The Company also announces it has entered into a service agreement with Native Ads Inc. ("Native Ads") in connection with a digital advertising campaign. Native Ads will provide the Company with services which include sponsored articles, media buying, content distribution services and ad campaign analytics. Pursuant to the agreement, the company has agreed to pay US$172,000 to facilitate the program. The digital advertising campaign is planned for the 12-month term of the agreement, or until budget exhaustion. The majority of the campaign budget will be disbursed by Native Ads to satisfy its obligations under the agreement. Native Ads is led by Jon Malach and is an arms-length Delaware Corp. with a registered office located in New York. Native Ads has no present interest, directly or indirectly, in the securities of the Company.

 

 

 

 

About Mayfair Gold

 

Mayfair Gold is a Canadian gold development stage company focused on advancing the 100% controlled Fenn-Gib Project in the Timmins region of Northern Ontario. The PFS outlines the potential to develop Fenn-Gib into a new Canadian gold producer for initial development capital of C$450 million, with a base case payback period of 2.7 years and cumulative free cash flow of $896 million over the first six years of production based on a US$3,100/oz gold price. The Company is advancing permitting activities, detailed engineering and stakeholder engagement with the goal of starting construction in 2028 with initial production in 2030.

 

The content of this news release has been reviewed on behalf of the Company and approved by Drew Anwyll, P.Eng., Chief Operating Officer of Mayfair, a QP as defined in NI 43-101.

 

Cautionary Note Regarding Forward-Looking Information

 

This news release contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation (collectively “forward-looking Information”). The use of the words “will” and “expected” and similar expressions are intended to identify forward-looking information. This information includes statements regarding the scope, timing and expected outcomes from future workstreams. Although Mayfair Gold believes that the expectations reflected in such forward-looking statements and/or information are reasonable, readers are cautioned that actual results may vary from the forward-looking information. The Company has based these forward-looking statements and information on the Company’s current expectations and assumptions about future events. This information also involves known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking information, including the risks, uncertainties and other factors identified in the annual information form of the Company for the year ended December 31, 2025, available at www.sedarplus.ca. Furthermore, the forward-looking statements contained in this news release are made as at the date of this news release and Mayfair does not undertake any obligation to publicly update or revise any of these forward-looking statements except as may be required by applicable securities laws.

 

Neither the TSX Venture Exchange (“TSXV”) nor its Regulation Services Provider (as that term is defined in the policies of the TSXV) accepts responsibility for the adequacy or accuracy of this news release.

 

 

 

 

For further information, please visit www.mayfairgold.ca or direct enquiries to:

 

Nicholas Campbell
CEO

Mayfair Gold Corp.
489 McDougall St

 

Matheson, ON P0K 1N0 Canada
+1 (855) 350-5600
info@mayfairgold.ca

 

 

 

FAQ

What progress did Mayfair Gold (MINE) report on the Fenn-Gib project for Q1 2026?

Mayfair Gold reported advancing environmental baseline integration, submitting a Notification of Project Status, and appointing Egis Canada to lead environmental assessment and permitting. It also progressed geotechnical drilling, pump testing, condemnation drilling, and initiated Front-End Engineering and Design for a planned 4,800 tpd processing facility.

What are the key economics from Mayfair Gold’s Fenn-Gib Pre-Feasibility Study?

The Fenn-Gib PFS outlines initial development capital of C$450 million, a base case payback period of 2.7 years, and cumulative free cash flow of $896 million over the first six years of production, based on a US$3,100/oz gold price assumption for the project.

When does Mayfair Gold plan to start construction and production at Fenn-Gib?

Mayfair Gold is advancing permitting, detailed engineering and engagement with the goal of starting construction in 2028 and achieving initial production in 2030. These targets depend on successful completion of engineering, environmental assessment, permitting, and stakeholder processes described in the company’s update.

What engineering work did Mayfair Gold initiate with Ausenco in Q1 2026?

In the first quarter of 2026, Mayfair Gold commenced Front-End Engineering and Design with Ausenco for a planned 4,800 tpd processing facility. Work includes financial trade-off studies, Process Design Criteria, and Piping and Instrumentation Diagrams to support moving into detailed engineering in the second half of 2026.

What is the scope and cost of Mayfair Gold’s digital advertising agreement with Native Ads?

Mayfair Gold entered a service agreement with Native Ads for a digital advertising campaign including sponsored articles, media buying, content distribution and analytics. The company agreed to pay US$172,000, with the campaign planned over a 12-month term or until the budget is exhausted, whichever occurs first.

How is Mayfair Gold advancing environmental and permitting work at Fenn-Gib?

Mayfair is compiling multi-year environmental baseline studies and submitted a Notification of Project Status. It awarded Egis Canada the mandate to lead Ontario provincial environmental assessment, prepare regulatory submissions, and continue engagement with Indigenous communities, stakeholders and regulators as formal approval activities start later in 2026.

Filing Exhibits & Attachments

1 document