New Found Gold (NYSE: NFGC) signs EPCM deal to advance Queensway Phase 1
Rhea-AI Filing Summary
New Found Gold Corp. outlines key steps toward developing its 100%-owned Queensway Gold Project in Newfoundland and Labrador. The company has entered into a Phase 1 engineering, procurement and construction management contract with WSP Canada Inc. for site development and detailed engineering of an offsite milling facility, tied to its 2025 preliminary economic assessment.
New Found Gold plans to upgrade and expand its fully permitted Pine Cove Mill to process both Hammerdown and Queensway Phase 1 ore, and has substantially completed environmental baseline work, with an Environmental Registration targeted for submission in late Q1/26 to start the provincial environmental assessment process. The company has engaged Cutfield Freeman & Co. Ltd. as project finance advisor and expects to file an updated Queensway technical report with a new mineral resource estimate in mid-2026, with a goal of first gold pour from Queensway Phase 1 in H2/27, pending all required permits.
Positive
- None.
Negative
- None.
Insights
New Found Gold takes concrete steps to advance Queensway toward planned first gold in H2/27.
New Found Gold is moving Queensway from study stage toward development by signing a Phase 1 engineering, procurement and construction management services contract with WSP Canada Inc.. This work focuses on Queensway site development and detailed engineering for an offsite mill, aligned with the 2025 preliminary economic assessment. Using an established EPCM firm can help define project design, schedule and capital requirements more clearly.
The company plans to upgrade and expand its fully permitted Pine Cove Mill so it can treat both Hammerdown and Queensway Phase 1 ore through a single facility. It has substantially completed environmental baseline work and aims to submit an Environmental Registration in late Q1/26, initiating the provincial environmental assessment process. Progress through permitting will be a key dependency, as the targeted first gold pour from Queensway Phase 1 in H2/27 is explicitly contingent on receiving all required permits.
On the funding side, New Found Gold has appointed Cutfield Freeman & Co. Ltd. as project finance advisor to help structure capital for initial Phase 1 development. The company also plans an updated technical report with a new mineral resource estimate in mid-2026, which will refine the project’s resource base and economic framework. Subsequent disclosures on permitting status, financing arrangements and that updated report will further clarify how closely execution tracks this development timeline.
FAQ
What key milestone did New Found Gold (NFGC) announce for the Queensway Gold Project?
New Found Gold announced it has entered into a Phase 1 engineering, procurement and construction management services contract with WSP Canada Inc. for Queensway Phase 1 project development, covering site development and detailed engineering for an offsite milling facility.
How does New Found Gold plan to process ore for Queensway Phase 1?
The company plans to upgrade and expand its fully permitted Pine Cove Mill in central Newfoundland so it can process ore from both the Hammerdown Operation and Queensway Phase 1 through a single facility, leveraging existing milling and tailings infrastructure.
What is the status of environmental permitting for Queensway Phase 1?
New Found Gold has substantially completed environmental baseline work at Queensway and plans to submit an Environmental Registration to the Newfoundland and Labrador Department of Environment, Conservation and Climate Change in late Q1/26 to initiate the environmental assessment process.
How is New Found Gold approaching project financing for Queensway Phase 1?
The company has engaged Cutfield Freeman & Co. Ltd., an independent global mining finance advisory firm, as its project finance advisor to help identify and structure an optimal financing package for the initial capital expenditure for Queensway Phase 1.
When does New Found Gold expect to file an updated Queensway Technical Report?
The company plans to file an updated Queensway Technical Report, including an updated mineral resource estimate, in mid-2026, following the 2025 preliminary economic assessment.
What timeline does New Found Gold target for first gold pour at Queensway Phase 1?
New Found Gold indicates that work is underway with the objective of achieving first gold pour from Queensway Phase 1 in H2/27, pending receipt of all required permits.
Who is the Qualified Person for the technical information in New Found Gold’s update?
Keith Boyle, P.Eng., the company’s Chief Executive Officer, reviewed and approved the scientific and technical information and is identified as the Qualified Person under National Instrument 43-101.
