NVIDIA Corporation entered a multi-year partnership with SB Energy Corp. to develop the PORTS-Pike (Portsmouth) Technology Campus in Pike County, Ohio as a large-scale AI data center site. Through residual value guaranty agreements, NVIDIA has secured land, power and shell capacity to host NVIDIA AI compute infrastructure, with an affiliate of OpenAI Group PBC as tenant under 20-year leases.

NVIDIA entered multiple residual value guaranties covering leases for approximately 4.25 gigawatts of IT load, with the ability, at its sole discretion, to provide credit support for approximately an additional 3.8 gigawatts. NVIDIA’s aggregate payment obligation for its initial commitment is capped at $105 billion, subject to specified conditions, including the lessor satisfying ready-for-service conditions, expected beginning in 2028. If OpenAI becomes insolvent or fails to pay rent, NVIDIA must make up any shortfall between the guaranteed minimum lease value and amounts recovered, with options to assume leases, relet, sell, or terminate.

NVIDIA will invest $1.5 billion in SB Energy. SB Energy and SoftBank plan to build at least 10 GW of new energy generation, enabling 8 IT-GW of AI factory capacity, and to invest at least $4.2 billion in regional grid infrastructure. A community benefits fund totaling $80 million is planned for the surrounding Ohio communities.

Positive

  • None.

Negative

  • NVIDIA’s residual value guaranties carry a potentially large obligation, capped at $105 billion over up to 20 years if OpenAI defaults and recovery is limited.

Filing Explained

The announced guarantee is conditional credit support: lease commencement and ready-for-service milestones precede the potential payment exposure.

Although the accompanying release headlines NVIDIA as guaranteeing the campus, the 8-K classifies the arrangements as a direct financial obligation or an obligation under an off-balance-sheet arrangement, while saying each agreement generally becomes effective when its applicable lease starts and payment duties depend on ready-for-service conditions expected beginning in 2028.

The residual-value support is a backstop: after an OpenAI payment failure or insolvency-related default, NVIDIA may owe the shortfall between the lease’s guaranteed minimum value and amounts recovered through replacement leasing or a sale. OpenAI has agreed to reimburse and indemnify NVIDIA for amounts it actually pays under the agreements.

The complete agreement forms are expected as exhibits to NVIDIA’s quarterly report for the quarter ended July 26, 2026, providing the next detailed source for the obligations’ terms.

Item 1.01 Entry into a Material Definitive Agreement Business
The company signed a significant contract such as a merger agreement, credit facility, or major partnership.
Item 2.03 Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement Financial
The company incurred a new significant debt or off-balance-sheet obligation.
Item 7.01 Regulation FD Disclosure Disclosure
Material non-public information disclosed under Regulation Fair Disclosure, often investor presentations or guidance.
Item 9.01 Financial Statements and Exhibits Exhibits
Financial statements, pro forma financial information, and exhibit attachments filed with this report.
Residual value guaranty cap $105 billion Aggregate payment cap for NVIDIA’s initial commitment under the residual value guaranty agreements
Initial IT load capacity 4.25 gigawatts IT load covered by leases at the Portsmouth site supported by NVIDIA’s guaranties
Optional additional IT load 3.8 gigawatts Approximate additional IT load for which NVIDIA may provide credit support at its discretion
Investment in SB Energy $1.5 billion NVIDIA’s planned investment to support SB Energy’s AI infrastructure development
Regional grid infrastructure investment $4.2 billion Planned investment by SB Energy and SoftBank in new regional grid infrastructure
Community benefits fund $80 million Total community fund combining SB Energy’s and OpenAI’s contributions for the Ohio region
New energy generation 10 GW At least 10 GW of new energy generation planned to support the campus
AI factory capacity 8 IT-GW AI factory capacity expected from the new energy generation at PORTS-Pike
residual value guaranties financial
"NVIDIA entered into multiple residual value guaranties with SB Energy relating to leases"
ready-for-service conditions regulatory
"payment obligations are subject to the Lessor having satisfied applicable ready-for-service conditions"
IT load technical
"relating to leases for approximately 4.25 gigawatts of IT load in the aggregate"
AI factory technical
"The AI factory will use NVIDIA’s full-stack DSX AI factory platform"
An "AI factory" is an organizational setup that combines data, software, computing power and repeatable processes to build, train, deploy and monitor artificial intelligence systems at scale — like an assembly line for AI models. Investors care because a well‑run AI factory can lower costs, speed product delivery and create predictable revenue streams from many AI-powered products, making a business more competitive and scalable in a measurable way.
off-balance sheet arrangement financial
"Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement"
An off-balance sheet arrangement is a financial commitment or asset that a company keeps out of its main financial statements so it does not show up as a direct asset or liability. Think of it like renting equipment or using a separate storage locker instead of putting the item in your home: the economic effects exist, but they aren’t listed on the company’s primary balance sheet. Investors care because these arrangements can hide risks, obligations or sources of cash flow that affect a company’s true financial strength and future performance.
community benefits fund financial
"anchored by an initial $80 million community benefits fund"

FAQ

What partnership did NVIDIA (NVDA) announce with SB Energy in Ohio?

NVIDIA announced a multi-year partnership with SB Energy to develop the PORTS-Pike Technology Campus in Pike County, Ohio as a large-scale AI data center site, where NVIDIA will secure land, power and shell capacity and OpenAI will be the tenant under long-term leases.

How large is the AI infrastructure commitment in NVIDIA’s (NVDA) SB Energy deal?

The agreements cover leases for approximately 4.25 gigawatts of IT load, with NVIDIA able to provide credit support for about 3.8 additional gigawatts at the Portsmouth site, enabling very large-scale AI factory capacity for OpenAI using NVIDIA’s DSX AI factory platform.

What is NVIDIA’s maximum financial exposure under the residual value guaranties?

NVIDIA’s aggregate payment obligation for its initial commitment is capped at $105 billion. Payments would arise after specific trigger events, such as OpenAI insolvency or nonpayment, and are limited to making up any shortfall versus the guaranteed minimum lease value after reletting or sale.

When are the PORTS-Pike AI facilities expected to begin operating?

Capacity at the PORTS-Pike Technology Campus is expected to come online in phases beginning in 2028. The lessor must first satisfy ready-for-service conditions under the leases before NVIDIA’s residual value guaranty obligations become effective for each applicable lease.

What community and infrastructure investments are tied to NVIDIA’s (NVDA) Ohio project?

SB Energy and SoftBank plan to build at least 10 GW of new energy generation and invest at least $4.2 billion in regional grid infrastructure, alongside a community benefits fund totaling $80 million to support local energy affordability, jobs, and economic development.

How much is NVIDIA investing directly into SB Energy under this arrangement?

NVIDIA will invest $1.5 billion in SB Energy. This investment is intended to support SB Energy’s growth as an AI infrastructure developer and its commitments to the PORTS-Pike campus and surrounding communities.

AI-generated analysis. How Rhea-AI works. Not financial advice.

See more from StockTitan in Google Search and AI answers. Adds StockTitan as a preferred source · opens Google
Add on Google
Learn about SEC filing dates
0001045810false00010458102026-08-172026-08-17

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, DC 20549
______________
FORM 8-K
CURRENT REPORT
PURSUANT TO SECTION 13 OR 15(d) OF
THE SECURITIES EXCHANGE ACT OF 1934

Date of Report (Date of earliest event reported): August 17, 2026
NVIDIA CORPORATION
(Exact name of registrant as specified in its charter)
Delaware0-2398594-3177549
(State or other jurisdiction(Commission(IRS Employer
of incorporation)File Number)Identification No.)
2788 San Tomas Expressway, Santa Clara, CA 95051
(Address of principal executive offices) (Zip Code)
Registrant’s telephone number, including area code: (408) 486-2000
Not Applicable
(Former name or former address, if changed since last report)

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
Securities registered pursuant to Section 12(b) of the Act:
Title of each classTrading Symbol(s)Name of each exchange on which registered
Common Stock, $0.001 par value per shareNVDAThe Nasdaq Global Select Market
Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).

     Emerging Growth Company
If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ☐




Item 1.01.    Entry into a Material Definitive Agreement

On August 17, 2026, NVIDIA Corporation (“NVIDIA”) announced a multi-year partnership with SB Energy Corp. (collectively with its affiliates, “SB Energy”) to advance the development of the PORTS Technology Campus, a large-scale AI data center campus in Pike County, Ohio (the “Portsmouth Site”). Through the partnership and the credit support described below, NVIDIA has secured land, power, and shell capacity at the Portsmouth Site to host NVIDIA AI compute infrastructure. An affiliate of OpenAI Group PBC (such affiliate, “OpenAI”) will be the tenant.

Residual Value Guaranties

On August 17, 2026, NVIDIA entered into multiple residual value guaranties (collectively, the “Agreements”) with SB Energy (the “Lessor”) relating to leases for approximately 4.25 gigawatts of IT load in the aggregate at the Portsmouth Site. An Agreement generally will become effective upon commencement of the applicable lease. NVIDIA also can provide credit support to secure approximately an additional 3.8 gigawatts at the Portsmouth Site, exercisable in its sole discretion.

NVIDIA’s aggregate payment obligation is cumulatively capped at $105 billion for its initial commitment under the Agreements. NVIDIA’s payment obligations are subject to specified conditions, including among other things, that the Lessor has satisfied applicable ready-for-service conditions under the lease for the relevant premises, expected beginning in 2028.

Pursuant to the Agreements, OpenAI is the tenant; however, in the event of (i) OpenAI’s insolvency resulting in a default under a lease, or (ii) OpenAI’s failure to make payments under a lease (each a “Trigger Event”), NVIDIA will pay an amount generally equal to any shortfall between the guaranteed minimum value of a lease (as set forth in the Agreements) and amounts recovered through a replacement lease or sale.

Upon a Trigger Event, NVIDIA may elect to (i) assume the applicable lease, (ii) require the Lessor to seek to relet the applicable premises, (iii) initiate a sale process, (iv) allow the applicable lease to be terminated, or (v) defer the exercise of these remedies for up to one year while paying specified project agreement costs. NVIDIA’s obligations under an Agreement will terminate upon the earliest to occur of (i) the 20th anniversary of the commencement of the applicable lease, (ii) the termination of the applicable lease by OpenAI in accordance with its terms, (iii) OpenAI achieving a satisfactory credit rating, and (iv) other customary termination events. OpenAI has agreed to reimburse and indemnify NVIDIA for any and all amounts actually paid by NVIDIA to the Lessor under the Agreements.

The foregoing description of the Agreements does not purport to be complete and is qualified in its entirety by reference to the full text of the Agreements, the form of which will be filed as an exhibit to NVIDIA’s Quarterly Report on Form 10-Q for the fiscal quarter ended July 26, 2026.

OpenAI, as the tenant, will utilize capacity at the Portsmouth Site supporting approximately 4.25 gigawatts of IT load to deploy NVIDIA’s full-stack DSX AI factory platform, subject to limited exceptions.

Item 2.03.    Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement of a Registrant

The information set forth in Item 1.01 above is hereby incorporated by reference into this Item 2.03.

Item 7.01.    Regulation FD

On August 17, 2026, NVIDIA issued a press release announcing the partnership with SB Energy. The press release is attached as Exhibit 99.1 hereto and is incorporated herein by reference.

The press release is furnished and shall not be deemed "filed" for purposes of Section 18 of the Securities Exchange Act of 1934, as amended, or subject to the liabilities of that Section or Sections 11 and 12(a)(2) of the Securities Act of 1933, as amended. The information in this Item 7.01 of this Current Report on Form 8-K, including Exhibit 99.1, shall not be incorporated by reference in any filing with the U.S. Securities and Exchange Commission made by NVIDIA, whether made before or after the date hereof, regardless of any general incorporation language in such filing.







Forward-Looking Statements

Certain statements in this Current Report on Form 8-K, including, but not limited to, statements as to: NVIDIA’s partnership with SB Energy and the expected benefits and impacts of the partnership; the development, timing, scale, capacity, and operation of the Portsmouth Site; OpenAI’s role as the tenant and the expected deployment of NVIDIA’s DSX AI factory platform at the Portsmouth Site; the potential expansion of the Portsmouth Site and related commitments; the amount, timing, and conditions of any payments by NVIDIA under the Agreements; the expected timing of the Lessor’s satisfaction of the applicable ready-for-service conditions; and other statements that are not historical facts are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended, which are subject to the “safe harbor” created by those sections based on management’s beliefs and assumptions and on information currently available to management and are subject to risks and uncertainties that could cause results to be materially different than expectations. Important factors that could cause actual results to differ materially include: global economic and political conditions; NVIDIA’s reliance on third parties to manufacture, assemble, package and test NVIDIA’s products; the impact of technological development and competition; development of new products and technologies or enhancements to NVIDIA’s existing products and technologies; market acceptance of NVIDIA’s products or NVIDIA’s partners’ products; design, manufacturing or software defects; changes in consumer preferences or demands; changes in industry standards and interfaces; unexpected loss of performance of NVIDIA’s products or technologies when integrated into systems; NVIDIA’s ability to realize the potential benefits of business investments or acquisitions; and changes in applicable laws and regulations, as well as other factors detailed from time to time in the most recent reports NVIDIA files with the Securities and Exchange Commission (the “SEC”) including, but not limited to, its most recent Annual Report on Form 10-K and subsequent Quarterly Reports on Form 10-Q. Copies of reports filed with the SEC are posted on NVIDIA’s website and are available from NVIDIA without charge. These forward-looking statements are not guarantees of future performance and speak only as of the date hereof, and, except as required by law, NVIDIA disclaims any obligation to update these forward-looking statements to reflect future events or circumstances.

Item 9.01.    Financial Statements and Exhibits.

(d) Exhibits
 
ExhibitDescription
99.1
Press release, issued August 17, 2026
104The cover page of this Current Report on Form 8-K, formatted in inline XBRL (included as Exhibit 101)






SIGNATURE

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

NVIDIA Corporation
Date: August 17, 2026By: /s/ Colette M. Kress
Colette M. Kress
Executive Vice President and Chief Financial Officer



NVIDIA Guarantees SB Energy's PORTS-Pike Technology Campus in Ohio to Exclusively Host NVIDIA AI Compute
NVIDIA will be the exclusive AI compute infrastructure provider at PORTS-Pike
NVIDIA to provide credit support on land, power, and shell buildout to secure initial 4.25 IT-GW, with an option to take the remaining 3.75 IT-GW
OpenAI will be the customer for 8-IT GW
PORTS-Pike campus project will create tens of thousands of Ohio jobs, pay for its power infrastructure, and invest hundreds of millions in the community anchored by an initial $80 million community benefits fund
NVIDIA to invest $1.5B in SB Energy now to support SB Energy’s growth and commitments to the Ohio community

SANTA CLARA and REDWOOD CITY, Calif. August 17, 2026 – NVIDIA announced that it has secured land, power and shell (LPS) capacity through a partnership with SB Energy at the PORTS-Pike Technology Campus in Pike County, Ohio, to host NVIDIA compute. OpenAI will be the customer. SB Energy will build, own and operate the data center under a 20-year lease to OpenAI.
Demand for AI is growing at an extraordinary pace. AI is becoming infrastructure, requiring a full stack of critical resources, including LPS. To meet this moment, NVIDIA is securing the LPS capacity at PORTS-Pike to exclusively host NVIDIA AI factories. This unique campus development will lay the foundation for tomorrow’s breakthroughs, enabling communities to drive scientific discovery, health care advances and regional economic development.
OpenAI will utilize the capacity at the site. The AI factory will use NVIDIA’s full-stack DSX AI factory platform, including GPUs, CPUs and networking. The initial deployment is designed to support 4.25 IT-GW of AI factory capacity. NVIDIA has the option to extend the opportunity at PORTS-Pike beyond the initial capacity. The DSX AI factory architecture used at PORTS-Pike will deliver resiliency across the full stack – facilities, hardware, and software together – reducing infrastructure overhead and accelerating time to tokens for the next generation of AI factories.
“AI is becoming infrastructure – the foundation for intelligence in every industry – and land, power and shell have become vital in the age of AI. Now is the time to scale the AI infrastructure that will power the next industrial revolution,” said Jensen Huang, founder and CEO of NVIDIA. “We are securing long-lived infrastructure for NVIDIA compute so OpenAI can deploy the most productive AI factories that can be upgraded repeatedly with each new generation delivering more intelligence and better economics.”
1



“Infrastructure is vital for the AI economy. With SoftBank Group, OpenAI and NVIDIA, SB Energy is building power-first infrastructure at unprecedented scale while strengthening the communities that make it possible – protecting ratepayers, creating tens of thousands of well-paying jobs, and investing in infrastructure to revitalize Southern Ohio that has long shaped America’s future,” said Rich Hossfeld, co-CEO of SB Energy.
“This is going to be a huge site, with enough computing power to help millions of people use AI to do things we can only start to imagine today, from finding new medicines to starting businesses and solving hard problems,” said Sam Altman, CEO of OpenAI. “We’re proud to build it in Pike County, a place that is once again at the heart of American industry and leading the future. We want the people who live here to feel the benefits too, through good jobs, more opportunity for local businesses, and investment in the community for years to come.”
“The next era of intelligence will transform every industry — and require infrastructure built at unprecedented speed and scale. Together with our partners, SoftBank will help unlock the power of AGI and move humanity forward,” said Masayoshi Son, Chairman and CEO of SoftBank Group Corp.
Campus to Bring New Jobs and Benefits to Ohio
SB Energy’s PORTS-Pike Technology Campus is reindustrializing the decommissioned Portsmouth Gaseous Diffusion Plant and the surrounding area, bringing a new generation of jobs to Appalachian Ohio, while creating an opportunity for the region to play an important role in the next era of American industry. Spanning private and federal land, the campus is being developed in collaboration with AEP Ohio, the U.S. Department of Energy, and the U.S. Department of Commerce. The planned capacity is expected to come online in phases beginning in 2028.
In support of the surrounding Ohio community, SB Energy and SoftBank will build at least 10 GW of new energy generation, which results in 8 IT-GW of AI factory capacity, and invest at least $4.2 billion in new regional grid infrastructure through an innovative partnership with AEP Ohio designed to protect ratepayers. OpenAI has agreed to build on SB Energy’s originally announced $40 million community benefits fund with an incremental $40 million designed to support local priorities, including affordable energy, job creation and workforce development, and community and economic development.
NVIDIA Invests in SB Energy
NVIDIA will invest $1.5 billion in SB Energy, joining existing investors SoftBank Group and OpenAI. The investment supports SB Energy’s continued evolution into a leading AI infrastructure developer, while supporting Pike County and other local
2



communities, with the vast opportunity ahead to deliver compute infrastructure at speed and scale.
This press release shall not constitute an offer to sell or a solicitation of an offer to buy any securities, nor shall there be any sale of any securities in any state or other jurisdiction in which such offer, solicitation or sale would be unlawful prior to the registration or qualification under the securities laws of any such state or other jurisdiction.
Advisors
Goldman Sachs and JP Morgan served as financial advisors for SB Energy. Morgan Stanley served as NVIDIA’s financial advisor.
About NVIDIA
NVIDIA (NASDAQ: NVDA) is the world leader in AI and accelerated computing.
About SB Energy
SB Energy is a leading integrated data center and power infrastructure company purpose-built for the AI economy. The company develops, constructs, and operates gigawatt-scale data center campuses and utility-scale power generation assets. Through its vertically integrated, power-first model, SB Energy addresses the industry's primary bottleneck and accelerates speed-to-compute, with a focus on community, reliability, and cost discipline. For more information, visit
www.sbenergy.com.
About OpenAI
OpenAI is making powerful AI accessible, useful and abundant for people and businesses everywhere to build, solve problems and expand what they’re able to do.
Media Contacts
NVIDIA
Press@NVIDIA.com
SB Energy
press@sbenergy.com
OpenAI
press@openai.com
NVIDIA Forward-Looking Statements
3



Certain statements in this press release including, but not limited to, statements as to: AI becoming infrastructure and AI infrastructure powering the next industrial revolution; NVIDIA’s partnership with SB Energy and the expected benefits and impacts of the partnership; NVIDIA’s investment in SB Energy; the development, timing, scale, capacity and operation of the PORTS-Pike campus; the exclusive hosting of NVIDIA systems at the PORTS-Pike campus; OpenAI’s expected customer role and DSX deployment at PORTS-Pike; the potential expansion of the PORTS-Pike campus and related commitments and the expected economic and community impacts of the campus; NVIDIA’s credit support; expectations with respect to demand for AI; expectations with respect to performance, availability, and benefits of NVIDIA’s products, services and technologies, and related trends and drivers; expectations with respect to technology developments, and related trends and drivers; expectations with respect to AI and related industries; and other statements that are not historical facts are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended, which are subject to the “safe harbor” created by those sections based on management’s beliefs and assumptions and on information currently available to management and are subject to risks and uncertainties that could cause results to be materially different than expectations. Important factors that could cause actual results to differ materially include: global economic and political conditions; NVIDIA’s reliance on third parties to manufacture, assemble, package and test NVIDIA’s products; the impact of technological development and competition; development of new products and technologies or enhancements to NVIDIA’s existing products and technologies; market acceptance of NVIDIA’s products or NVIDIA’s partners’ products; design, manufacturing or software defects; changes in consumer preferences or demands; changes in industry standards and interfaces; unexpected loss of performance of NVIDIA’s products or technologies when integrated into systems; NVIDIA’s ability to realize the potential benefits of business investments or acquisitions; and changes in applicable laws and regulations, as well as other factors detailed from time to time in the most recent reports NVIDIA files with the Securities and Exchange Commission, or SEC, including, but not limited to, its Annual Report on Form 10-K and Quarterly Reports on Form 10-Q. Copies of reports filed with the SEC are posted on the company’s website and are available from NVIDIA without charge. These forward-looking statements are not guarantees of future performance and speak only as of the date hereof, and, except as required by law, NVIDIA disclaims any obligation to update these forward-looking statements to reflect future events or circumstances.
4

Filing Exhibits & Attachments

4 documents